What is a door schedule in commercial construction?
Learn what a construction door schedule lists, how estimators check missing ratings and hardware against plans, and how to test one on a live tender.
A construction door schedule, sometimes called a schedule of doors, is a structured table, typically prepared by the project architect or compiled by the builder from project drawings, that lists every door by its tag, location, scheduled size, leaf and frame type, ratings, and ironmongery or hardware set. Estimators and commercial managers check the door schedule against floor plans, specifications, and consultant reports before pricing packages or placing orders.
What a construction door schedule includes
A complete door schedule links every door mark on the architectural floor plans to the specification and procurement details required to price and supply the doorset. As documented in Autodesk Revit's door schedule reference, schedules itemise model doors by instance and can be grouped or filtered by level to support quantity and cost work.
Estimating and quantity surveying teams expect a tender door schedule to carry 7 core fields:
- Door tag and location: A unique reference such as
D#01paired with the level and room or zone so each row maps back to a drawn opening. - Scheduled dimensions: Nominal leaf or structural opening width, height, and thickness as scheduled on the architectural sheet.
- Leaf and frame specification: Core construction, vision panels, finish, frame material, and architrave or shadow-gap detail.
- Fire rating: Required fire-resistance performance and intumescent or smoke seals where nominated by the architect or fire strategy.
- Acoustic rating: Required acoustic performance and perimeter or drop-seal requirements where nominated by the acoustic report.
- Hardware and ironmongery: Locksets, hinges, closers, access control interfaces, and kickplates linked to the ironmongery schedule.
- Notes and detail references: Undercuts, threshold details, glazing notes, and references to standard door elevation or detail sheets.
Authoring tools allow design teams to filter door schedule fields by level, phase, fire rating, or custom parameters when those attributes exist in the model. Blank or unconfirmed cells are common at tender stage, and spotting them early stops unpriced upgrades turning into variations on site.
Worked door schedule example
A tender door schedule rarely arrives with every column complete. The plan extract and table below show 3 scheduled doors from an anonymised residential unit plan, keeping every unconfirmed attribute visible so you can see what still requires clarification before pricing.

Illustrative reconstruction.
| Door tag | Location | Scheduled size | Fire rating | Acoustic rating | Hardware | Review status |
|---|---|---|---|---|---|---|
| D#01 | Entry | 870 × 2400 mm | To confirm | To confirm | To confirm | Confirm fire, acoustic, and ironmongery requirements before pricing |
| D#09 | Bedroom | 920 × 2400 mm | To confirm | To confirm | To confirm | Confirm leaf core, acoustic seals, and hardware set |
| D#13 | Ensuite | 720 × 2400 mm | To confirm | To confirm | To confirm | Confirm moisture-resistant finish and privacy hardware set |
The 3 scheduled sizes (870 × 2400 mm, 920 × 2400 mm, and 720 × 2400 mm) provide an initial count and nominal size list. Those figures are scheduled sizes from the door schedule. Before pricing or ordering doorsets, confirm whether each scheduled size states leaf, doorset, or structural opening dimensions and reconcile it with the frame profile, clearances, and drawn partition framing.
Fire rating, acoustic rating, and hardware all read To confirm. A room name alone cannot establish whether a doorset requires a fire rating, acoustic seals, or specific ironmongery. Pricing a standard internal door when the fire strategy, acoustic report, or Employer's Requirements later calls for a fire-rated or acoustically rated doorset creates a direct cost gap before subcontract award.
Practical checks before pricing and procurement
Before sending a joinery or doorset package out to tender or fixing a commercial allowance, run 5 checks across the tender pack:
- Reconcile every tag between plans and schedule. Confirm that every door drawn on the floor plans appears on the door schedule and that no scheduled row has been deleted from the plans.
- Verify room location and door swing on the floor plan. Schedule room labels can fall out of step after late drawing edits. Autodesk's room information guidance for door schedules warns that
From RoomandTo Roomfields do not automatically follow later door-swing changes, so check swing direction and room adjacency directly on the current plan. - Reconcile scheduled sizes with the dimension basis and opening details. Confirm whether scheduled widths and heights state leaf, doorset, or structural opening dimensions, then reconcile them with the frame profile, clearances, installation tolerances, lintels, and ceiling heights shown on architectural and structural drawings.
- Cross-check ratings against consultant reports and specifications. Compare the door schedule against the fire strategy, acoustic report, Employer's Requirements (ER), and specification so missing ratings or conflicting seal requirements surface before contract award.
- Confirm ironmongery and trade interfaces. Check which trade supplies and installs frames, leaves, ironmongery, access-control containment, and decoration. Clear trade boundaries belong in your scope of works.
Checking door schedules with CIM Build
Estimators and commercial managers normally reconcile door schedules against floor plans, specifications, and consultant reports sheet by sheet in PDFs and spreadsheets. CIM Build's preconstruction modules operate as an AI-first service that delivers results in hours through interactive software with visible workings and verifiable measurements, depending on pack size, document quality, and review scope.
CIM Build extracts the door schedule, locates door marks on drawings, and links written report and specification requirements so your team inspects schedule rows alongside marked-up 2D sheets and linked 3D elements where drawn without repeating the whole takeoff themselves, while source review and commercial judgement remain with your team.
- Start the schedule or review run. A person starts schedule extraction for the door schedule. When checks against consultant reports, specifications, or Employer's Requirements are needed, the team separately starts a scoped requirements review.
- Get source-linked rows and cited findings. CIM Build extracts the door schedule, locates door marks on drawings, and returns source-linked rows. A separate written-requirement review checks those clauses against the drawings and cites conflicts or gaps so estimators check doorset packages faster before tender pricing and procurement.
- Review, export, or issue an RFI. Your team inspects incomplete or conflicting evidence and exports the reviewed schedule to Excel, CSV, or PDF. When you choose to raise a query, CIM Build drafts the RFI, and your reviewer edits it, selects recipients, and issues it by email or connected Aconex project mail or Procore RFI.
Frequently asked questions
What is the difference between a door schedule and a schedule of doors?
In UK construction, door schedule and schedule of doors describe the same document. Both list each door tag with its location, scheduled dimensions, leaf and frame construction, performance ratings, and ironmongery reference.
Can you price a doorset package from scheduled sizes alone?
No. Scheduled widths and heights let you count doors and check nominal leaf sizes, but pricing depends on leaf core, frame profile, fire rating, acoustic seals, glazing, and ironmongery. Keep unconfirmed fields visible, state any provisional allowance clearly, and issue an RFI before subcontract award.
What should you do when the door schedule and floor plan disagree?
Check the tender conditions or contract precedence clauses and raise a written RFI citing the exact door tag, schedule revision, and floor plan sheet. Do not assume the floor plan or the schedule governs without consultant confirmation.
Does CIM Build certify fire or acoustic compliance on a door schedule?
No. CIM Build extracts schedule rows, locates door marks on drawings, and cites matching or missing clauses across project documents. Your team and the project consultants remain responsible for compliance, ratings, and sign-off.
How is CIM Build priced for schedule and document checks?
CIM Build is priced per project, with the project price determined by the number of pages we process for that project. Contact CIM Build for a quote on your project.
Test your door schedule on a live tender pack
See how a real door schedule stands up against your floor plans, Employer's Requirements, and consultant reports before tender return. Contact CIM Build to walk through a live tender pack with your team.
Send us a live tender and see what it finds
Your first live tender project comes at a discount. We scope the review with you, run your drawings, schedules, and specifications, and walk through the evidence with your team. Get results in hours inside interactive software where your team can trace sources and verify every measurement and finding. Timing depends on pack size, document quality, and review scope.
Book a demoLeave your contact details first. Our team will follow up to arrange safe document sharing and a walkthrough.