What are tender qualifications and exclusions, and how should a builder write them?

A qualification is a condition attached to a tender price. An exclusion is work left out of it. How Australian builders write them so they hold up, and how they get lost between tender and site.

TL;DR: A tender qualification is a condition the builder attaches to its price, such as an assumption about the documents or a departure from the contract terms. An exclusion is a piece of work the price doesn't cover. A good one names the drawing, revision or clause it relies on, says what was allowed, and puts a dollar value on the difference. Then it has to make it into the signed contract, because a qualification left in the tender letter may not bind anyone.

What is the difference between a qualification and an exclusion?

Say it's 4pm the day before the tender closes. The hydraulic drawings are at revision A, the specification refers to a stormwater detention tank, and no drawing shows one.

The estimator has 2 choices. Price a guess, or say what the price assumes.

An exclusion takes work out. "Stormwater detention tank excluded."

A qualification sets a condition on the price. "We've allowed a 20kL in-ground detention tank to the basement. No tank is shown on H-101 rev A."

How do clients treat a qualified tender?

It depends on the conditions of tendering, so read those first.

Public sector tenders are the strictest. The Tendering Guidelines for NSW Local Government (October 2009) show how one set of public clients is told to handle it. Where a tender comes in with qualifications or departures, the council can assess what they're worth and adjust the tendered price to compare tenders. If a qualification makes the tender non-conforming, the tenderer may be asked to withdraw it, and if it isn't withdrawn the tender may be treated as non-conforming. The guidelines also say an alternative tender shouldn't be accepted from a tenderer that hasn't lodged a complying one.

Standards Australia also publishes AS 4120-1994, Code of tendering, which its store lists as current.

Private clients are usually more relaxed. They read the qualifications, price them, and negotiate.

So every qualification has a cost on tender day. The assessor adds a number for it, and if you didn't give one they'll pick their own.

How should a builder write a qualification?

Think about who reads it. First the client's quantity surveyor, levelling 4 tenders. Then, 14 months later, a contract administrator who wasn't at the tender, trying to work out whether a change is claimable.

5 rules cover most of it.

  1. Name the document. Drawing number, revision, specification clause, report section. "As per drawings" tells nobody anything.
  2. Say what you allowed. A quantity, a product, a rate. The reader should know what's in the price without ringing you.
  3. Put a value on it. If the qualification falls away, what's the adjustment? Giving the figure stops the assessor inventing one.
  4. One item per line, numbered. Each line gets accepted, rejected or negotiated on its own.
  5. Drop the boilerplate. A 3-page standard list that excludes rock on a job with no excavation makes the client distrust the 4 lines that matter.

Compare 2 versions of the same line.

Weak - "Acoustic treatment as per drawings."

Stronger - "Party walls priced as wall type W3 on A-501 rev B. The acoustic report (section 4.2) calls for Rw+Ctr 50 and W3 as drawn may fall short. Upgrading 84 apartments to a compliant wall type is excluded. Estimated addition $[amount]."

The second one can be priced, accepted or argued with. It also tells the delivery team what was assumed.

Which things should be in every tender letter?

Do qualifications survive into the contract?

Only if the contract says so.

Most construction contracts list the documents that make up the agreement, and many set an order of precedence between them. Some also say the signed contract replaces everything exchanged before it. If the tender letter isn't one of the listed documents, the qualifications in it may not bind the client.

So before signing, check the tender letter or a schedule of agreed qualifications is in the contract documents, and check where it ranks. Record each line as accepted, rejected or withdrawn. Our guide to comparing tender drawings with contract drawings covers the same step for the drawings.

This is general information. The contract decides what's in and what ranks first, and a construction lawyer should check it before you sign.

How do qualifications get lost after the contract is signed?

They stay in the tender file.

The estimator moves to the next bid. The project manager gets the contract and the drawings. Nobody tells the site team the tank was priced at 20kL, so when the revision C drawing shows 45kL, it gets built and nobody claims the difference.

That's an exclusion you priced out, built anyway at your cost.

The same thing happens one level down. Subcontractor quotes arrive with their own exclusions on the last page, and any that no other trade picks up become scope gaps the builder carries.

CIM Build has 2 features that work on this. Lessons learnt takes your past defects, standard details and tender qualifications and runs them as checks on every new set, and what was assumed at pricing stays attached to the scope it was priced on, so delivery inherits what estimating knew. Bid leveling matches the inclusions, exclusions and qualifications in each subcontractor quote to the scope register built from the drawings and specification, with the sheet and clause on every line. The estimator decides how each gap is carried.

Book a briefing and bring the tender.

Frequently asked questions

Can a qualified tender be rejected? Yes. Where the conditions of tendering require a conforming tender, a qualification can make the tender non-conforming and the client may set it aside or ask for the qualification to be withdrawn. Read the conditions of tendering before deciding how much to qualify.

Is an exclusion the same as a provisional sum? No. An exclusion leaves the work out of the price. A provisional sum keeps the work in the contract with an allowance that's adjusted to actual cost later.

Should a builder qualify or raise an RFI? Raise the RFI first if there's time, because an answer fixes the documents for every tenderer. Qualify what's still open at close, and reference the unanswered RFI by number. More in what an RFI is in construction.