How do I take off doors and door hardware from the drawings and schedule?

Count doors by tag off the plans, reconcile the count to the door schedule, then group by door type and hardware set. Hardware is the set quantity multiplied by the doors that carry it, with pairs, fire doors and electrified hardware checked one by one.

TL;DR: Count every door off the plans by tag, then reconcile that count to the door schedule line by line. Group the doors by leaf type, frame type and hardware set, and count each group in number. Hardware is each item in a set multiplied by the doors that carry the set, with pairs, fire doors and electrified hardware checked individually.

The schedule says 612 doors. The plans show 631.

19 doors with no leaf type, no rating and no hardware set. Most of them are riser cupboards and a run of store rooms in the basement that got added after the schedule was last issued.

That's a synthetic example, and it's the first thing a door takeoff is for. Count what's drawn, then find out why the schedule disagrees.

If you want the background on what a schedule should contain, start with what a door schedule is in commercial construction.

What do I count, and in what units?

Doors are counted in number. The work is in the grouping.

A pair of doors is 1 opening, 1 frame and 2 leaves. Count it wrong and every hinge, bolt and closer on that opening is out.

Which drawings and schedules do I read?

  1. The floor plans, for the door tags and locations.
  2. The door schedule, for the leaf, frame, ratings and hardware set against each tag.
  3. The hardware schedule, for what's inside each set.
  4. The door and frame details and elevations, for vision panels, undercuts and thresholds.
  5. The specification section for doors and hardware.
  6. The fire engineering report and the acoustic report, for ratings the schedule might not have picked up. Checking an acoustic report against the drawings and door schedule goes through that one.
  7. The electrical and security drawings, for card readers, electric strikes and door hold-open devices.

How do I reconcile the plans to the schedule?

Both ways.

Go through the plans level by level and tick each door tag against a schedule line. A tag with no line is a door nobody has specified. Then go down the schedule and find each line on the plans. A line with no door behind it is usually a door that was deleted or renumbered.

Apartments need extra care. Say a job has 84 apartments in 6 unit types, and type 2B has 7 doors and appears 30 times. That's 210 doors from one unit plan, so an error in the 2B count gets multiplied by 30.

Check the mirrored and adaptable variants as well, because the handing and the leaf widths can change.

Then count the common areas door by door. Fire stairs, lobbies, riser cupboards, bin rooms, plant rooms, the basement. These are the rated and the expensive ones, and they don't repeat.

How do I take off the hardware?

Hardware is multiplication, once the doors are grouped.

Count the doors against each hardware set. Then multiply each item in the set by that number.

Say set H3 is an apartment entry - 3 hinges, 1 mortice lock, 1 lever set, 1 closer, 1 door viewer, 1 set of perimeter and drop seals. 84 entries is 252 hinges, 84 locks, 84 closers, and so on down the set.

Things to check before you trust the multiplication:

What gets missed?

Each of these ends up supplied and fitted. If it wasn't in a trade package at tender, the builder pays for it.

How does AI takeoff handle doors?

Counts of doors are a standard request in CIM Build's AI takeoff. You ask for doors by fire rating or by type, and it returns a results table with a marked-up copy of the sheet, so you can see every door that was counted.

Schedule Creator does the reconciliation. It reads the schedule, locates every door and window on the plans and reconciles the 2 - doors on the drawings with no line in the schedule, and lines with no door behind them. It audits hardware, fire ratings, acoustic ratings and finishes against the specification. Where no schedule exists, it builds one from the drawings.

The estimator still decides how the hardware sets are priced and what goes in the qualifications.

Book a briefing and bring the tender.

Frequently asked questions

Do I count doors off the plans or off the schedule? Both, and then reconcile them. The plans tell you what's drawn and the schedule tells you what's specified. Price from the schedule only after every tag on the plans has a line in it.

How do I count a pair of doors? As 1 opening with 1 frame and 2 leaves. Hinges and leaf hardware are counted per leaf, and the set usually adds flush bolts or a second closer. Check the hardware schedule for that set.

Who prices electric strikes and card readers? It depends on how the trade packages are split on your job. Commonly the electrified lock sits with the door hardware supplier and the reader, cabling and power supply sit with security or electrical. Write the split into each scope of works so nothing sits between the 2.