What is the difference between tender drawings and issued for construction (IFC) drawings?

Tender drawings are the set a builder prices. IFC drawings are the set the site builds from. What changes between the two, where the contract set sits, and how builders tell design development from a change in scope.

TL;DR: Tender drawings are the set issued for pricing, and the builder's tender is based on them. Issued for construction (IFC) drawings are the developed, coordinated set the site and the trades build from. The design keeps moving between the two, so the IFC set is larger and more detailed and it rarely carries exactly the scope that was priced. The builder's job is to compare each later issue against the set the contract was signed on, and separate design development from change.

What are tender drawings?

The drawings the principal sends out with the tender documents so builders can price the job.

They're a snapshot of an unfinished design. On construct only they might be close to complete. On design and construct they can be a preliminary design with the detail still to come, sitting behind a Principal's Project Requirements document that says what the building has to achieve.

Tender drawings are usually stamped "for tender" or "not for construction". Addenda issued during the tender period change them, and the priced set is the tender drawings plus every addendum.

What are IFC drawings?

IFC means issued for construction. It's a status the consultant puts on a drawing to say it's developed, coordinated with the other disciplines and ready to build from.

Some states attach legal weight to that step. In NSW, on class 2, certain class 3 and class 9c buildings, the designs lodged before work starts must be "construction issued regulated designs and not shop drawings or other drafts", each with a design compliance declaration from a registered design practitioner (NSW Government, design practitioner obligations). The building practitioner lodges them on the NSW Planning Portal before building work on those designs begins (NSW Government, building practitioner obligations).

IFC isn't the end of the revisions either. Drawings keep reissuing after IFC, each time a consultant fixes or coordinates their own work, right up to practical completion.

What sits between tender and IFC?

The contract set, and usually 2 or 3 design development issues.

SetWhat it's forWho relies on itWhat to check
Tender drawingsPricingEstimators and subcontractors quotingScope gaps, addenda, what each quote was based on
Contract drawingsDefining what was agreedContract administrator, commercial leadThe exact revisions listed in the contract
Design development issues (say 50%, 75%, 90%)Developing and coordinating the designDesign manager, consultantsMovement against the contract set
IFC drawingsBuildingSite team and tradesEvery difference from what was priced

The contract drawings are the ones listed in the contract. They're often the tender set plus addenda and anything agreed in post-tender clarifications, and sometimes a later issue. Getting from one to the other is covered in our tender-to-contract guide.

Why does the difference matter?

Because the price was built on one set and the building gets built from another.

Here's a made-up example on an 84-apartment job. The tender drawings show 1 layer of plasterboard each side of the corridor walls. The IFC set shows 2, because the acoustic and fire design got finished after tender. Nobody announces it. The wall type legend changed and the plans followed.

Who pays for the second layer depends on the contract.

On construct only, the builder priced the documents it was given. A change between the contract drawings and the IFC drawings is commonly a variation, and the builder can claim it if it's found and notified the way the contract requires.

On design and construct, the builder commonly carries design development. If the second layer was always needed to meet the Principal's Project Requirements or the code, it's likely the builder's cost. If the principal changed what it asked for, that's commonly a variation.

So the same drawing change can be claimable scope on one job and the builder's own design risk on the next. The contract and a lawyer decide which. What the builder controls is whether the change gets found at all. A change nobody noticed is scope built at the builder's cost on either form.

How do builders compare the IFC set against what they priced?

Start with the right baseline, then compare every sheet.

  1. Confirm which revisions form the contract set and keep a dated copy. See establishing a head-contract baseline.
  2. Compare each design issue against that baseline, and against the issue before it. They answer 2 different questions.
  3. Check sheets that were renumbered, split, added or withdrawn. The IFC set usually has more sheets than the tender set.
  4. Sort each difference - design development, principal change, consultant error, or a question for an RFI.
  5. Re-measure the quantities the changes touch and tell the trades whose quotes were based on the earlier set.
  6. Give any notices the contract requires, inside the time it allows.

Methods for step 2 are in how to compare drawing revisions, and step 5 is in updating a takeoff after a drawing revision.

Where does CIM Build fit?

CIM Build's revision tracking brings matched drawing pairs, comparison status and detected findings into one review workflow, so the team can check each difference against the earlier and later sheet. Bulk compare runs a whole set in one pass on an instruction written in plain English and keeps every run with its date, inputs and results.

On design and construct, PPR vs the drawings re-runs on the tender pack and on every design issue after it, so a clause satisfied at tender is checked again at IFC. A detection alone doesn't establish entitlement. Your team decides what each difference means.

Book a briefing and bring the tender set and the latest issue.

Frequently asked questions

Can a builder build from tender drawings? Tender drawings are issued for pricing and are usually marked not for construction. Site work should follow drawings with a construction status. In NSW, regulated buildings need construction issued regulated designs lodged before the work starts.

Are IFC drawings the same as contract drawings? Usually they're different sets. The contract drawings are the revisions listed in the contract, fixed at signing. IFC drawings are issued later, as the design is finished. The differences between them are where variations and design development risk sit.

Are IFC drawings the same as shop drawings? No. IFC drawings are the consultants' design. Shop drawings are prepared by a subcontractor or fabricator to show how they'll make and install their part. The NSW Government guidance draws the same line between construction issued regulated designs and shop drawings.

Is IFC the same thing as an IFC model file? No. On a drawing, IFC is a status meaning issued for construction. IFC is also the name of a file format for 3D building models. If someone asks for "the IFC", check which one they mean.