How do I check structural drawings against the architectural set?
Confirm which architectural revision the structure was drawn over, then compare the 2 sets level by level - grids, columns, slab edges, set-downs, penetrations and beam depths. Where the mismatches usually sit and what to do with each one.
TL;DR: To check structural drawings against the architectural set, first confirm which architectural revision the structure was drawn over. Then compare the 2 sets level by level in a fixed order - grids, columns and walls, slab edges, set-downs, penetrations, then beam depths against ceiling heights. Finish by listing everything the architect drew that needs structure behind it, like awnings and lintels, and finding each one in the structural set. Every mismatch goes in a register with both sheet numbers and becomes an RFI.
What does a mismatch look like?
A made-up example. Say an 84-apartment job over 2 basement levels. The architectural plans show a 50mm set-down to every bathroom and balcony. The structural slab plans show flat slabs.
Nobody read the 2 sets side by side at tender. The formworker prices flat slabs, and the waterproofer and tiler price to the architectural details.
It surfaces when the level 1 deck is being formed. Either the slab gets redesigned in a hurry or the floor build-up changes in 84 bathrooms. At tender it was a free RFI.
Where do the mismatches usually sit?
- The background. Structural plans are drawn over an architectural background, and that background is often 1 or 2 revisions behind the current architectural set. Walls and openings have moved since.
- Columns and walls. A column drawn 300 wide on the architectural plan and 400 on the structural one. In a basement that narrows a car space. In an apartment it lands in a wardrobe or a doorway.
- Set-downs and levels. Wet areas, balconies, door thresholds and planter boxes. The architect shows the finished floor level and the engineer shows the structural slab level, and the build-up between them has to add up.
- Slab edges. The balcony outline or the facade line differs by 50 or 100mm between the 2 sets. The facade and the balustrades fix to that edge.
- Penetrations and voids. Risers, stair voids and lift shafts drawn at 1 size by the architect and another by the engineer, or missing from the slab plan altogether.
- Beams against ceilings. A transfer beam or band beam that hangs below the ceiling height on the architectural section. Basement ramps and car park headroom are the usual places.
- Steel nobody designed. Awnings, screens, lintels over wide openings, balustrade fixings, plant platforms. The architect draws them and the structural set has no member, no detail and no note.
How do I check it by hand?
- Check the revisions first. Write down the current revision of every architectural plan and every structural plan. Then look at the background on each structural sheet and work out which architectural issue it matches. If it's behind, that's your first RFI.
- Overlay level by level. Put the structural slab plan over the architectural plan for the same level, at the same scale, lined up on the grids. Any PDF markup tool with an overlay function does this. Work in the same order on every level - grids, columns, walls, slab edges, penetrations.
- Check the levels. Take the finished floor levels off the architectural sections and the slab levels off the structural plans. Subtract the floor build-up from the finishes schedule. What's left should match the set-down the engineer has drawn.
- Check the sections. Find the deepest beams on each level and compare the underside against the ceiling heights on the architectural sections and reflected ceiling plans.
- List what needs structure. Go through the architectural elevations and details and list every item that needs a structural member or a fixing. Find each one in the structural set.
- Raise the gaps. Each mismatch gets a line in the register and an RFI that cites both sheets.
A synthetic register line looks like this - "A-201 rev D shows 50 set-down to bathrooms, units 1.01 to 1.12. S-201 rev B shows flat slab. Conflicting. RFI to engineer and architect."
Where a typical floor repeats up the building, check 1 level properly and then confirm the others match it. The ground floor, the podium and the roof are different every time, so they get the full pass.
What happens when a revision lands?
The 2 sets rarely reissue together. The architect moves a wall at rev E and the structural set stays at rev B for 3 more weeks.
So the check runs again whenever either set moves, and the register records which pair of revisions was compared. Comparing each revision against the last tells you what moved in 1 discipline. You still have to ask whether the other discipline moved with it.
Doesn't BIM clash detection cover this?
Some of it. Clash detection finds geometry conflicts in a federated 3D model, and it covers what's been modelled. Plenty of jobs are still priced and built off 2D PDFs, and a set-down that's missing from a slab plan has nothing to clash with. More in AI drawing review vs BIM clash detection.
Doing it with CIM Build
CIM Build reads every drawing, specification, consultant report and brief on every revision and checks them against each other - drawings against specifications, one discipline against another. Each finding cites the sheet and the revision it came from.
Revision tracking compares each new issue against the last and lists every change, including the changes nobody clouded. Bulk compare runs the whole set on an instruction you write in plain English, like slab levels. And in the viewer you can overlay several drawings at once as synced layers to check a finding on the sheet.
Your team triages each finding as reviewed, needs action or RFI, and nothing goes to a consultant until a person sends it.
Book a briefing and bring the tender.
Frequently asked questions
Who is responsible when the structural and architectural drawings don't match? It depends on the contract. The consultants are meant to coordinate their own documents, and on a design and construct contract that coordination commonly ends up with the builder's design team. Check the design obligations and the order of precedence in your contract, and get a lawyer's advice on anything that turns on them.
What's the difference between SSL and FFL? SSL is the structural slab level, the top of the concrete. FFL is the finished floor level, the top of the tile, timber or carpet. The gap between them is the floor build-up - screed, membrane, adhesive and the finish itself. Structural drawings usually give SSL and architectural drawings usually give FFL, so the 2 numbers should differ by the build-up.
When should structural drawings be checked against architectural? At tender, again when the construction set is issued, and each time either discipline reissues. Most mismatches arrive when 1 set moves and the other stays put.