How to prepare a bill of quantities from drawings

A step-by-step method for builders: write the scope per trade, measure against it, describe each line so it can be priced, and check the bill against the current revision.

TL;DR: To prepare a bill of quantities, split the job into trades, write the scope for each trade from the drawings and specification, measure every scope item in a consistent unit, describe each line so a subcontractor can price it without opening the drawings, and record the sheet or clause behind every quantity. Check the bill against the current revision before it goes out. AI takeoff can do the measuring and the first draft. The estimator checks and signs it off.

What a bill of quantities is for

A bill of quantities (BoQ) puts every subcontractor on the same measured basis. Without one, each subcontractor measures the job their own way, and the quotes that come back price different quantities. With one, the quotes can be compared line by line and the gaps are visible.

In Australia, quantity surveyors usually measure to the Australian and New Zealand Standard Method of Measurement (ANZSMM). Builders preparing their own trade bills at tender often use a simpler house format. Either works if it is consistent across the trade.

The method

  1. Split the job into trades. Use the same trade breakdown as your tender packages: plasterboard and partitions, waterproofing, doors and hardware, and so on.
  2. Write the scope for each trade first. List what the drawings and specification require of that trade, with the sheet or clause behind each item. This is the checklist the quantities are measured against.
  3. Measure each scope item. Pick the unit the trade prices in: m for linear work, m² for areas, m³ for volumes, "no." for counts. Measure net, and keep waste and laps in the rates.
  4. Describe each line so it can be priced. "W3 acoustic partition, 92 mm stud, 2 × 13 mm each side, Rw 45, to underside of slab" can be priced. "Partition type 3" sends the subcontractor back to the drawings.
  5. Record the source. Put the drawing number, revision and detail, or the specification clause, against every line.
  6. Check for scope with no quantity. Any scope item with no measured line is either a gap in the bill or work that belongs to another trade. Decide which before the bill goes out.
  7. Check against the current revision. If a new revision has arrived since you measured, compare the sets and re-measure what changed.

A worked line

ItemUnitQtySource
W1 partition, full height, 92 mm stud, 1 × 13 mm each sidem²579.4A-1103 rev C, Spec 09 21
W3 acoustic partition, Rw 45m²232.7A-1103 rev C, acoustic report §4
Access panels, 600 × 600no.12RCP Level 3 rev B
Shaft wall to riser R2m²not measuredSpec 09 21 §3.4

The last line is the useful one. The specification calls for shaft wall at riser R2, and nothing on the plans has been measured for it. That is either a drawing gap to raise as an RFI or an allowance to carry.

The figures in this table are a synthetic example.

Common mistakes

Where AI helps

CIM Build reads the drawings and specification into a scope of works for each trade, measures the quantities against it with AI takeoff, and builds a bill of quantities with the unit, quantity and source on every line. Scope items with no quantity are flagged. The estimator checks the lines that carry the most cost, adds rates and exports the bill to Excel to send with the trade package. When the quotes come back, they can be levelled against the same quantities.