Customer stories

CIM on live jobs

The discrepancies caught before packages were let, and the tenders won without the lowest price. Builders and projects anonymised.

Australia · Commercial construction · Lump sum · $15M

Catching a $50K+ discrepancy before the package was let

A three-document coordination error - RW35 required, RW30 scheduled, no seals specified - caught, cited and confirmed before the window package was let.

Read the story

Australia · Fit-out and refurbishment · A national contractor · $10M tender won

Winning a $10M job without the lowest price

Full tender set reviewed from day one, the material gaps raised as RFIs, and the saved hours spent on value management and the client. The cheapest bid lost.

Read the story

Published by CIM.BUILD. This is the text of https://www.cim.build/au/case-studies without the site design. Index of all pages. Contact.