How do I check the drawings against the Principal Project Requirements?
Turn the PPR into a numbered register, map every clause to the sheet, schedule or spec section that should carry it, and mark each one shown, missing, conflicting or exceeded. A step-by-step method for design and construct tenders.
TL;DR: Break the Principal Project Requirements (PPR) into a register of single, numbered requirements. Map each one to the sheet, schedule or specification section that should carry it, and mark it shown, missing, conflicting or exceeded. Raise an RFI or carry an allowance for every missing or conflicting clause before the tender closes, and run the check again on every design issue.
Why does the PPR check matter on design and construct?
Say you're pricing a 6-storey job with 84 apartments. The PPR runs to 140 pages. Clause 7.4 asks for a 2.7 m ceiling in living rooms, and the sections show 2.55 m because the services zone grew.
Nobody priced the fix, because nobody put the clause next to the section.
On design and construct you deliver the brief whether or not the consultants drew it. A clause the drawings missed becomes scope built at your cost later. Design that goes past the brief gets built too, and nobody priced the difference.
If you're new to the document itself, start with Principal Project Requirements explained.
What do I need before I start?
4 things.
- The PPR issue named in the tender, with every schedule and appendix. Room data sheets and finishes schedules often sit at the back and carry half the requirements.
- The current drawing set and the specification, with a drawing register that shows the revision of each sheet.
- Every addendum issued so far.
- The contract's order of precedence clause. It decides which document wins when 2 of them disagree.
Write down the PPR revision and the drawing revisions you checked. In 6 months someone will ask what the price was based on.
How do I turn the PPR into something I can check?
Split it into single requirements.
A PPR clause often holds 3 or 4 obligations in one paragraph - a ceiling height, an acoustic rating, a warranty period and a brand. Each one gets its own row with the clause number, the requirement in the PPR's own words and the measurable value if it has one.
Then sort the rows by where the answer should live:
- Dimensions and areas - plans and sections
- Ratings such as FRL and Rw - wall types, door schedule, specification
- Finishes and fixtures - finishes schedule, FFE schedule, specification
- Services capacity - services drawings and reports
- Warranties, testing and handover - specification and preliminaries
A 140-page PPR usually lands somewhere in the hundreds of rows. That's normal.
How do I check each clause against the drawings?
Go row by row. Open the sheet, schedule or spec section that should carry the requirement and give the row 1 of 4 statuses.
| Status | What it means | What you do |
|---|---|---|
| Shown | The documents carry the requirement, and the values match | Record the sheet or clause and move on |
| Missing | The documents are silent | RFI, or price it and say so |
| Conflicting | The documents show something different | RFI, citing the PPR clause and the sheet |
| Exceeded | The design goes past what the brief asks for | Flag it for a fee or value conversation |
Record the evidence on every row, including the ones marked shown. "A-301 rev C, section 2" takes 5 seconds to write and saves the next reviewer from finding it again.
Then run it the other way. Walk the drawings and the schedules and ask where the brief allows for each major item. A rooftop plant enclosure the PPR never mentions is a question worth asking before you price it.
What do I do with missing and conflicting clauses?
Each one needs a decision before the tender closes.
- Raise an RFI while the question is still free to ask. Quote the clause number and the sheet. Our guide on how to write an RFI covers the wording.
- If there's no time for an answer, price the PPR requirement or price the drawings, and record which. Then cover the assumption in your tender qualifications.
Which document governs is a contract question. Design and construct contracts commonly set an order of precedence between the PPR and the design documents, and they vary. Read the clause in your contract and get a lawyer's view on anything that carries real money. Treat this article as a checking method only.
When should the check be run again?
Every time the documents move.
- On each addendum during the tender
- Before the contract is signed, against the documents the contract will list
- On every design issue after award, up to the construction issue
The register is what makes that practical. A row marked shown at tender can turn into a conflict at 70% design when a section changes, and you'll only see it if the row still exists.
Where does CIM Build fit?
PPR vs the drawings runs this check for you. CIM Build checks each clause of the brief against the drawings and the specification and cites the sheet behind every finding. Requirements the design missed come back as findings, and so does design that exceeds the brief. It runs in both directions on every issue.
The same read covers the consultant reports through report compliance, and a person reviews every finding before anything goes to a consultant.
Book a briefing and bring the brief and the set you're pricing.
Frequently asked questions
How long does it take to check drawings against the PPR by hand? It depends on the size of the brief and the set. A PPR with hundreds of clauses takes days to check in full, so most teams read the sections they already suspect and trust the rest. A register makes the second and third passes much faster because the mapping is already done.
What if the PPR and the drawings disagree? Raise an RFI that cites the PPR clause and the sheet, and price on a stated basis until it's answered. Which document governs depends on the order of precedence in your contract, so the contract and a lawyer decide that.
Can AI check drawings against the PPR? Yes. CIM Build runs the PPR and the drawing set against each other in both directions on every issue, so a requirement in the brief that the drawings don't show, or a drawn item the brief doesn't allow for, comes back as a finding. Each finding names the clause and the sheet so a person can confirm it.