What is early contractor involvement (ECI)?

Early contractor involvement brings the builder in during design to advise on buildability, cost and risk before the construction price is fixed. How ECI works in Australia and what to watch.

TL;DR: Early contractor involvement (ECI) is a way of procuring a project in 2 stages. In the first stage the builder is engaged, usually for a fee, to work with the client and the designers on buildability, schedule, cost and risk while the design is still moving. At the end the builder offers a price for construction, and the client either accepts it, commonly under a design and construct contract, or takes the design to market. There are many variants, and the ECI agreement sets the terms.

How does ECI work?

Say the design is at 40%. The client wants a fixed price and the builders it has spoken to won't give one, because too much is still undrawn.

That's the usual reason for an ECI. The builder comes in early and helps close the unknowns before anyone fixes a number.

The Commonwealth's National Alliance Contracting Guidelines, Guidance Note 6 (September 2015) describes ECI as a collaborative procurement contract to develop a tender for the construction phase of a project. It also says there are many variants in use across Australia.

The ACT Treasury's outline of delivery models sets out one version in 3 steps.

  1. Tenderers bid a fixed price to develop the detailed design, and a target price for construction with fixed preliminaries, margin and overheads.
  2. The builder develops the design and finalises a fixed construction price.
  3. The client accepts that price, or tenders the work as a construct-only contract.

The same page says ECI suits a project where a builder is unwilling or unable to give a fixed price tender for D&C.

Is ECI a contract or a process?

It's a process with 2 contracts in it.

Guidance Note 6 describes the first as a services agreement, the ECI agreement, and the second as the design and construction contract. It lists the difference between the 2 as a disadvantage of the model, because they're substantially different documents.

In the first you're a consultant with a fee and a scope of services. In the second you're a builder with a lump sum and the design risk. Read our guide to design and construct contracts for what that second contract commonly puts on the builder.

Is ECI competitive?

On public work, usually yes. The default model in Guidance Note 6 has 2 builders engaged in parallel, each developing its own design, project plan, schedule and commercial proposal with the client, and each preparing a risk-adjusted price for construction delivered as a lump sum. A single-builder ECI is treated as the exception.

Private clients often run it with 1 builder, chosen on capability, preliminaries and margin. An independent quantity surveyor then checks the trade prices as they come in.

What does the builder do during the ECI stage?

The services vary by agreement. These are common.

What does the builder get out of ECI?

A better-informed price. Guidance Note 6 puts it this way - under ECI the risk-adjusted price is agreed after the risks can be assessed in more detail, where under a traditional D&C tender it's agreed before.

For a builder that means months with the documents where a tender gives 4 weeks. Scope and risk questions get resolved with the client in the room.

It usually comes with a fee for the first stage, and a strong position to win the second.

What should a builder watch in an ECI?

5 things. The ECI agreement and a construction lawyer decide how each one lands.

  1. The off-ramp. Most ECI agreements let the client walk away after stage 1 and tender the design. Check what you're paid if that happens, and who owns the design work and the ideas you contributed.
  2. The fee. ECI services take senior people for months. A fee that covers half of it is a discount on a job you haven't won yet.
  3. What you've seen. After 6 months with the drawings it's hard to argue you couldn't have known about something in them. Expect the stage 2 contract to say so.
  4. The price build-up. On an open-book ECI the client sees every trade quote. The allowances, provisional sums and qualifications in your offer get read line by line.
  5. Design that keeps moving. The price is built on one issue of the drawings. If the contract set is a later issue, somebody has to compare the 2 before signing.

Where do the documents come into it?

Point 5 is where ECI jobs leak.

Say an 84-apartment job in a 5-month ECI. The consultants issue 6 design revisions in that time. The trade quotes behind the final offer came back on issue 4, and the contract schedule lists issue 6.

Anything that changed between 4 and 6 is in the contract and missing from the price. That's a scope gap you signed up to.

CIM Build's revision tracking brings matched drawing pairs, comparison status and detected findings into one review workflow, so the team can check each design issue against the one the quotes were based on. PPR vs the drawings checks each clause of the brief against the drawings and the specification, and the audit re-runs on every design issue. Your team decides which changes go in the offer.

Book a briefing and bring the current design issue.

Frequently asked questions

Is the builder paid for the ECI stage? Usually, under a services agreement with a fixed fee or agreed rates. The amount and what it covers are set by the ECI agreement, and some builders accept a low fee in exchange for the position it gives them on the construction contract.

Does ECI guarantee the builder gets the construction contract? No. The client can commonly decline the offer and tender the work, and the ACT Treasury outline describes that step as part of the model. Check the agreement for what happens to your fee and your design input if it does.

What contract follows an ECI? Often a design and construct contract for a lump sum or a guaranteed maximum price, sometimes based on AS 4902-2000 with amendments. Government agencies commonly use their own forms.