What is a design and construct (D&C) contract, and what risk does the builder take on?

Under a design and construct contract the builder finishes the design and builds it for a fixed price. How D&C works in Australia, what novation does, and the design risk the builder carries.

TL;DR: Under a design and construct (D&C) contract the principal gives the builder a brief and a part-finished design, and the builder completes the design and builds it, usually for a lump sum and a fixed date. The builder becomes the single point of responsibility for both design and construction. So the builder carries the risk that the finished design meets the brief, the cost of whatever the drawings missed, and often the consultants who drew them. The contract you sign sets the detail.

How does a D&C contract work?

Say the tender pack arrives at 30% design. There's a brief of a few hundred clauses, a set of preliminary drawings, 6 consultant reports, and 4 weeks to price it.

That's a normal D&C tender. You're pricing a building that hasn't been fully drawn yet.

The ACT Treasury's outline of delivery models describes it plainly. Under D&C the client procures design and construction as one integrated outcome, generally on a concept or preliminary design, for a fixed price and timeline. It lists a single point of accountability for design and construction as one of the advantages to the client.

The same page describes the other route, design then construct, where the client has the design finished to a construction-ready standard first. There, it says, the client bears the risks of design integration and constructability.

D&C moves those 2 risks to the builder.

Which contract forms are used for D&C in Australia?

The common standard form is AS 4902-2000, the Standards Australia general conditions of contract for design and construct. The Standards Australia store lists it as current.

In practice most D&C contracts are AS 4902 with amendments, or a bespoke form written by the principal's lawyers. Government agencies often have their own.

The amendments matter more than the base form. 2 contracts both described as AS 4902 can allocate design risk very differently.

What risk does the builder take on?

Here's what commonly moves to the builder. Each one is set by the wording of the contract, so treat this as a list of things to look for.

The last line of the design development point is where a lot of margin is decided. If the principal changes what the brief asks for, the builder has a variation to claim. If the drawings grow to meet a brief that never changed, there's usually nothing to claim.

This is general information. What your contract says, and what a construction lawyer tells you about it, decides who carries what.

What is novation?

On many D&C jobs the principal engages the architect and engineers first, then transfers their agreements to the builder when the contract is signed. That transfer is called novation.

The builder inherits a design team it didn't choose, on fees it didn't negotiate, with a design already under way. The builder also becomes responsible to the principal for their work.

Before signing, a builder will commonly check what each consultant's scope covers from here to practical completion, what's been left out of their fee, and whether the consultant's liability to the builder matches the builder's liability to the principal.

Where do D&C builders lose money?

In the gap between the brief and the drawings.

Say an 84-apartment job. The PPR asks for party walls at Rw+Ctr 50. The preliminary drawings show a wall type that won't get there. The estimator prices the wall as drawn, because that's what was measured.

The upgraded wall still has to be built. On D&C there's usually no variation in it, because the brief said so all along.

It runs the other way too. A design team that draws past the brief - a higher finish, a bigger plant room - adds cost nobody priced and nobody asked for.

Both are scope gaps, and both are in the documents on tender day.

How do you check the brief against the drawings?

Clause by clause. Each PPR clause goes in a register, mapped to the sheet, schedule or specification section that should carry it, and marked shown, missing or conflicting. Then the same for each consultant report.

By hand that's a week most tenders don't have.

CIM Build's PPR vs the drawings checks each clause against the drawings and the specification and cites the sheet behind every finding. Requirements the design missed come back as findings, and so does design that exceeds the brief. Report compliance does the same for the consultant reports - geotech, acoustic, ESD, fire, traffic, waste. Your team decides what goes in the price, what becomes an RFI and what becomes a tender qualification.

Book a briefing and bring the tender.

Frequently asked questions

Is D&C the same as a lump sum contract? No. Lump sum describes how the price is fixed, and D&C describes who is responsible for the design. Most D&C contracts are lump sum, and so are many construct-only contracts.

Who owns the design risk under a D&C contract? Mostly the builder, from the date of the contract, and in some contracts for the preliminary design that came before it. The exact split sits in the design, warranty and PPR clauses of the contract you sign, so have a lawyer read those before tender close.

Can a builder claim a variation on a D&C contract? Yes, where the principal changes the brief or directs a change to the work. Design development needed to meet a brief that hasn't changed is commonly at the builder's cost.

What's the difference between D&C and early contractor involvement? D&C is a contract for delivery. Early contractor involvement is a stage before it, where the builder works on the design and the price with the client, and it often ends in a D&C contract. More in early contractor involvement explained.