How do I write an RFI that gets a clear answer?

An RFI gets a clear answer when it asks 1 question, cites the sheet, revision and clause on both sides of the conflict, and proposes an answer the consultant can confirm. The 7 parts of a good RFI, a worked example on an apartment job, and the mistakes that send it back.

TL;DR: Write an RFI so the consultant can answer it in one pass without opening anything you didn't cite. Ask 1 question, name the sheet, revision and clause on each side of the conflict, attach the extracts, propose the answer you think is right, and say when you need it and what it's holding up. Then log it, and update the price, the scope of works or the drawings when the answer comes back.

Why do RFIs come back with a non-answer?

"Please confirm bathroom setdowns."

That's a real style of RFI, and the usual reply is "refer to structural drawings". 4 days gone, and the question's still open.

The consultant didn't dodge it. They couldn't tell which bathrooms, which drawing, or what the conflict was. A good RFI removes every reason to write back with a question. For the basics of what an RFI is and when to raise one, start with what is an RFI in construction.

What goes in a good RFI?

7 parts.

  1. A subject line that names the location and the issue. "Level 2 bathroom slab setdowns - arch and structural conflict" can be found in a register 8 months later. "Query" can't.
  2. The references. Sheet number and revision, grid or room number, spec section, report clause. Cite both documents when 2 disagree.
  3. What you found. 2 or 3 plain sentences. Document A says this, document B says that.
  4. The question. 1 question, closed if you can make it closed. "Which governs?" or "Please confirm X" gets an answer. "Please advise" gets a paragraph.
  5. Your proposed answer. If you can see the likely fix, say so. A consultant can confirm a proposal in a minute.
  6. The date you need it and what it's holding up. "Required by 12 March - Level 2 formwork starts 19 March" gets prioritised. "ASAP" doesn't.
  7. The attachments. A marked-up extract of each sheet, with the conflict circled.

What does a good RFI look like?

Here's an example. It's made up, on a 6-storey job with 84 apartments, and the sheet numbers are invented.

The vague version

Subject: Bathroom setdowns

Please confirm slab setdowns to bathrooms.

The version that gets answered

Subject: Level 2 apartment bathrooms - slab setdown shown on architectural, absent on structural

References: A-510 Rev C, detail 4. S-203 Rev B, Level 2 slab plan, apartments 2.01 to 2.14.

Detail 4 on A-510 Rev C shows a 40 mm slab setdown to apartment bathrooms. The Level 2 slab plan S-203 Rev B shows a flat slab with no setdown at the bathrooms in apartments 2.01 to 2.14.

Question: Is the 40 mm setdown required to the Level 2 bathrooms?

Proposed: Setdown applies as per A-510, and S-203 is reissued to show it. Please confirm, and confirm whether Levels 3 to 6 are the same.

Required by: 12 March. Level 2 formwork starts 19 March.

Attached: marked-up extracts of A-510 detail 4 and S-203.

The second one takes 10 minutes longer to write. It names 14 apartments, 2 sheets and 2 revisions, so the engineer can open S-203, look at the bathrooms and answer.

It also asks about Levels 3 to 6 in the same RFI. That's still 1 topic. A separate question about balcony falls would be a second RFI.

Who should the RFI go to?

Send it to whoever owns the document that needs to change, through the route the contract or tender conditions set.

In the example that's the structural engineer, with the architect copied because their detail is on the other side of the conflict. On a design and construct job the consultants often work for the builder, so the design manager sends it direct. On construct-only it usually goes to the superintendent or the principal's representative.

At tender, follow the tender conditions. Questions commonly go to a single contact by a cut-off date. There's more on tender-stage questions in how to reduce RFIs during a tender.

What mistakes send an RFI back?

What do I do when the answer comes back?

Read it against the question. If it doesn't answer what you asked, say so the same day and keep the RFI open.

Then follow it through. An RFI response is a written clarification. Check whether a revised drawing follows, and update the scope of works, the quantities or the subcontractor's instruction that depended on it.

If the answer adds scope after contract, it may be a variation the builder can claim. An RFI response alone commonly doesn't amount to a direction or a notice under the contract, so check your contract's notice provisions and get advice where it's unclear.

Can software draft the RFI?

It can draft it. A person still decides whether it goes.

In CIM Build, AI-suggested RFIs drafts the RFI from a finding - the question, the sheets it concerns, the revision and the extract, in the wording your team uses. A person reviews every draft before anything is sent. It's currently in beta with a small group of builders. Findings sit in a register with the sheet and revision they came from, an owner and a status, and AI RFI drafts and the RFI register covers how that works.

Book a briefing and bring the tender.

Frequently asked questions

How long should an RFI be? Short enough to read in a minute. A subject line, the references, 2 or 3 sentences on what you found, 1 question, a proposed answer and a date. The attachments carry the detail.

Should I propose an answer in an RFI? Yes, where you can see one. A proposal the consultant can confirm or correct usually comes back faster than an open question. The consultant still makes the design decision, and the RFI should say you're asking for confirmation.

How many questions can go in 1 RFI? 1 topic. Follow-on parts of the same issue can sit together, like the same setdown on other levels. A different issue gets its own RFI so it has its own status, owner and answer in the register.

Is an RFI response a variation? Not automatically. A response records a clarification. Whether it changes the contract scope, and what notice the builder has to give, depends on the contract, so read the notice provisions and get legal advice if you're unsure.


Published by CIM Build. This is the text of https://www.cim.build/uk/blog/how-to-write-an-rfi without the site design. Index of all pages. Contact.