What are the Principal's Project Requirements (PPR) on a design and construct contract?

The Principal's Project Requirements are the principal's written requirements for the building on a design and construct contract. What goes in a PPR, where the term comes from, and why builders check every clause against the drawings.

TL;DR: The Principal's Project Requirements (PPR) are the principal's written requirements for the finished building on a design and construct contract. They form part of the contract, and the builder designs and builds to them for the contract sum. AS 4902-2000, the Australian Standard design and construct form, uses the term, and under it the principal provides the PPR and may also provide a preliminary design. A PPR clause is the builder's to deliver whether or not the consultants drew it, so the PPR gets checked against the drawings before the price goes in.

Here's a made-up example. You're pricing an 84-apartment job on design and construct. The tender pack has 300 drawings and a 140-page PPR.

Clause 14.6 of the PPR asks for EV charging provision to every residential car space. The electrical drawings show it to 12 of 96.

The electrical subcontractor prices the drawings. If nobody reads clause 14.6 against the set, the other 84 spaces are in nobody's price, and they're still in your contract.

What goes in a PPR?

Whatever the principal wants the building to be and do. It varies a lot between principals, and a PPR on an apartment job commonly runs to hundreds of clauses covering:

You'll see it written as Principal's Project Requirements, Principal Project Requirements or just PPR. Some principals call the same document the brief.

Where does the term come from?

It comes from AS 4902-2000 General conditions of contract for design and construct, published by Standards Australia as part of the AS 4000 suite.

The preface to AS 4902 covers 3 procurement methods - design and construct, design development and construct, and design, novate and construct. In all 3 the principal provides the Principal's project requirements. In the last 2 the principal also provides a preliminary design, and the builder develops it.

The same preface warns principals to make sure their requirements are fully incorporated in the PPR.

2 cautions. Most design and construct contracts in use are amended versions of AS 4902 or a bespoke form, so the definitions in your contract are the ones that count. And Standards Australia has said it will review and update AS 4902:2000 following the release of AS 4000:2025.

Why does the PPR matter so much to the builder?

On construct only, the builder builds what's drawn. On design and construct, the builder owns the design too, and the PPR is the test the design gets measured against.

Contracts based on AS 4902 commonly have the builder warrant that the finished works will comply with the PPR and be fit for their stated purpose. So a requirement the drawings never picked up is still owed. It gets found at handover, built wrong, and the correction comes out of the builder's margin.

It cuts the other way too. Design that runs past what the PPR asks for gets built, and nobody priced the difference.

Both are scope gaps. More in what is a scope gap.

What happens when the PPR and the drawings disagree?

It depends on the contract. Commonly, the party who finds the discrepancy has to notify the superintendent in writing, and the superintendent directs which way to go.

Who pays for the direction is the part to read closely. In AS 4902-based contracts it's common for the builder to bear the cost where the discrepancy is inside the design documents, or between the design documents and the PPR. Many contracts also add an order of precedence that ranks the PPR above the drawings.

So finding the EV clause after contract usually means building 96 and being paid for 12. Finding it at tender means an RFI, a tender qualification or a priced allowance.

A change the principal makes to the PPR after contract is a different thing. That's commonly a variation, and the builder should claim it - which is one reason to keep the exact PPR issue the contract was signed on.

None of this is legal advice. Your contract and your lawyer decide how precedence, discrepancies and variations work on your job. For the wider picture, see design and construct contracts explained.

How do builders check the PPR against the drawings?

Clause by clause, in both directions.

  1. Put every PPR clause in a register with its clause number.
  2. Map each clause to the sheet, schedule or spec section that should carry it.
  3. Mark each one shown, missing, conflicting or exceeded.
  4. Raise an RFI or a tender qualification for each missing or conflicting item.
  5. Run it again on every design issue, up to issued for construction.

By hand that's days of reading on every issue, so teams read the sections they already suspect and trust the rest. The step-by-step version is in how to check the drawings against the PPR.

Where does CIM Build fit?

CIM Build's PPR vs the drawings check runs each clause of the brief against the drawings and the specification. Requirements the design missed come back as findings, and so does design that exceeds the brief. Each finding names the clause number and the sheet it was checked against.

The audit re-runs on the tender pack and on every design issue after it, and findings sit in registers with an owner and a status. A person decides what to do with each one.

Book a briefing and bring the PPR and the set you're pricing.

Frequently asked questions

Is the PPR a contract document? Usually, yes. Under AS 4902-based contracts the Principal's project requirements are the principal's written requirements for the works and are identified in the contract annexure. Check the list of contract documents in your own contract.

Is the PPR the same as the preliminary design? No. The PPR is the written requirements. The preliminary design is the drawings and other design material the principal provides for the builder to develop. The AS 4902 preface treats them separately - a principal always provides the PPR, and provides a preliminary design under design development and construct or design, novate and construct.

Who pays when a PPR requirement is missing from the drawings? On design and construct it's commonly the builder, because the builder carries the design and has agreed to deliver the PPR. The exact answer sits in the discrepancy, precedence and warranty clauses of your contract, so get legal advice on your form.

Can the principal change the PPR after the contract is signed? A principal can usually direct a change through the contract's variation clause, and the builder is commonly entitled to claim it. Keep the contract issue of the PPR so the change can be shown clause against clause.