What is the difference between a provisional sum and a prime cost item?

A prime cost item is an allowance for supplying an item that hasn't been selected. A provisional sum is an allowance for work that can't be priced yet. How each is adjusted in Australian contracts.

TL;DR: A prime cost (PC) item is an allowance in the contract sum for supplying an item that hasn't been selected yet, such as tapware or door hardware. A provisional sum (PS) is an allowance for work that can't be properly priced when the contract is signed, such as rock excavation, and it usually covers labour as well as materials. Both are adjusted to actual cost once the item is chosen or the work is done. How margin is treated on the adjustment is set by the contract.

What is a prime cost item?

The finishes schedule says "tapware - TBC by client". The estimator still needs a number in the tender.

So the tender carries a PC item. Say 84 apartments with an allowance of $450 supply per kitchen mixer.

The Australian Institute of Architects' practice note on prime cost items and provisional sums describes a prime cost item as an allowance in the contract for supplying necessary items that haven't been finally selected, and gives taps and door furniture as examples.

A PC item usually covers the cost of the item delivered to site. The labour to install it, and the builder's margin on that labour, sit in the fixed part of the price.

What is a provisional sum?

A provisional sum is an allowance for a piece of work. The same practice note describes it as an allowance for the cost of foreseeable necessary work, which can include materials that weren't fully specified when the contract began.

Rock in the excavation is the usual example. So is an authority connection, a landscaping package with no design yet, or signage the client will brief later.

A provisional sum normally includes everything needed to do that work - labour, materials, plant and subcontractors.

What's the difference at a glance?

Prime cost itemProvisional sum
What it allows forSupply of an item not yet selectedWork that can't be priced yet
Usually coversThe item, deliveredLabour, materials, plant and subcontractors
Typical examplesTapware, door hardware, appliances, tiles at a $/m2 supply rateRock excavation, authority works, undesigned landscaping
Installation labourIn the builder's fixed priceInside the allowance
Adjusted whenThe item is selected and boughtThe work is scoped and done

Consumer Affairs Victoria draws the same line for housing in its guide to changing a domestic building contract price. A prime cost item is a fitting the client hasn't selected or whose price isn't known at signing. A provisional sum is a reasonable estimate of the cost of work the builder can't give a definite price for.

How are they adjusted?

At the end, the allowance comes out of the contract sum and the actual cost goes in.

If the client picks a $600 mixer against the $450 allowance, the contract sum goes up by the difference across 84 kitchens. If they pick a $380 one, it goes down.

What gets added on top is the part to read closely. Commercial forms such as AS 4000 and AS 4902-2000 deal with provisional sums in the contract conditions, and the percentage for the builder's profit and attendance is commonly a figure the parties write into the contract. If it's left blank or struck out, the margin on a PS that doubles may be very thin.

So 3 things to check in your own contract before pricing.

  1. Whether the adjustment is on the difference only, or on the whole actual cost.
  2. What percentage applies for margin and attendance, and whether it applies both up and down.
  3. Whether the provisional sum work can be taken out and given to someone else.

Housing is regulated state by state. The Consumer Affairs Victoria guide says a domestic building contract must include a detailed list of the PC and PS items with a breakdown of the cost estimate for each, and that the builder must give the client the invoice or receipt showing the actual cost as soon as possible after getting it.

This is general information. The contract sets how each allowance is adjusted, and a construction lawyer should read it with you.

Is a provisional sum the same as a provisional quantity?

No. A provisional sum is a dollar allowance for the whole of a piece of work. A provisional quantity is an estimated quantity priced at a fixed rate, and the work is remeasured later. Rock at a rate per cubic metre against a provisional 300m3 is a provisional quantity. More in provisional quantities explained.

Where do builders lose money on allowances?

Allowances protect a builder when they're written tightly. The losses come from loose ones.

The second and third are document problems, and they're visible at tender.

CIM Build's scope of works reads the drawings and the specification into a scope register for each trade, with the sheet and clause behind every line. Quotes match against the register, so installation that a supply-only allowance leaves out shows up as an open line. Revision tracking brings matched drawing pairs and detected findings into one review workflow, so the team can see when a later issue draws what an allowance was covering.

Book a briefing and bring the tender.

Frequently asked questions

Does a prime cost item include installation? Usually it covers supply and delivery only, with installation in the builder's fixed price. Some contracts define it differently, so the description of each PC item should say whether fixing is included.

Does the builder get margin on a provisional sum? Commonly yes, at a percentage stated in the contract for profit and attendance. Whether it applies to the whole cost or only to the amount over the allowance, and whether it comes off when the cost is under, depends on the wording.

Is an adjustment to a provisional sum a variation? Many contracts treat it as its own adjustment to the contract sum under the provisional sums clause, separate from the variations clause. If the client changes the scope of the provisional sum work itself, that change may be a variation. The contract decides.