How do I update a takeoff when a new drawing revision arrives?

Find what changed between the 2 revisions, including what nobody clouded. Re-measure only the lines those changes touch, record the old and new quantity against the revision, then decide what the difference means for the price.

TL;DR: Find what changed between the old revision and the new one, sheet by sheet, including the changes nobody clouded. Re-measure only the takeoff lines those changes touch. Record the old quantity, the new quantity and the difference against the revision that caused it. Then decide what the difference means - a price update at tender, or scope to check against the contract after award.

Say Rev C lands 4 days before tender closes. 38 sheets reissued on an 84-apartment job, and the transmittal says "general amendments".

Nobody has 4 days to measure the building again. And if you measure nothing, the price goes in on Rev B quantities for a Rev C building.

The method below gets you to the lines that moved.

What should the takeoff record before a revision arrives?

2 things, and they decide how painful the update is.

Every line needs the sheet number and revision it was measured from. "Partitions W1, Level 3, 579 m², A-1103 rev B" can be updated. "Partitions W1, 579 m²" has to be measured again from scratch.

And keep the markup. If you can see what was traced on Rev B, you can lay it over Rev C and see where it stops matching.

How do I find what changed?

Work from 4 sources, because each one misses things.

The overlay is the one that finds the wall that moved 300 mm with no cloud. How to compare drawing revisions covers the method.

Then check the documents that aren't drawings. A wall type can keep its tag while the specification or the wall types schedule changes what the tag means, and the drawing looks identical. That's covered in specification changes between revisions.

Which quantities do I re-measure?

List each change, then list every takeoff line it touches. 1 change usually touches more than 1 trade.

Here's an example with made-up changes.

Change in Rev CLines it touchesWhat to do
Corridor walls on Level 3 change from W1 to W3Partitions W1, partitions W3, insulationMove the area between lines. Total may stay the same and the rate changes
Apartment ceiling drops from 2,700 to 2,400 at the corridorBulkheads, partition heights, paintingAdd bulkhead in m, re-check wall areas
1 door added to each of 12 apartmentsDoors, frames, hardware, partitions, paintingAdd 12 to the counts, deduct the openings
Balcony waterproofing detail revised, same extentNone by quantityCheck the description and the rate

Re-measure those lines on those sheets. Leave the rest alone, and note on the takeoff that the other sheets were compared and showed no change.

The last row is worth a second look. A change with no quantity attached can still move the price.

How do I record the change?

Keep a change register next to the takeoff. 1 row per change:

Keep the old takeoff. Save the Rev B version and work on a copy for Rev C.

It's tempting to overwrite the number and move on. Then 6 months later somebody asks what the job was priced on and nobody can show it.

What does the difference mean commercially?

It depends where the job is.

At tender, the difference goes into your price. If the subcontractors quoted on Rev B, send them the changed sheets and the changed bill lines and ask for a revised price, then level the quotes again on the same revision.

After the contract is signed, a revision that adds scope may be a variation. Whether it is depends on what the contract was priced against and what the contract says about changes, and standard forms commonly set a time limit for giving notice. Your contract and your lawyer decide that. The takeoff's job is to give them the facts - the baseline revision, the new revision and the measured difference.

The cost of skipping this is scope that gets built and never claimed. A wall type upgraded with no cloud reaches site, the subcontractor builds it, and the builder pays for it.

Updating a takeoff with CIM Build

CIM Build's revision tracking compares each new revision against the last one sheet by sheet and lists every change, including the changes nobody clouded. Each change is boxed on the sheet and recorded against the revision it arrived in. Your team checks the source and decides which changes affect scope, procurement or work already underway.

For the lines that moved, AI takeoff measures the new sheets. It calibrates the scale on each sheet and returns a table with a marked-up copy of the sheet, so you can check the new quantity against the old markup.

Book a briefing and bring the previous and current drawing sets.

Frequently asked questions

Do I need to re-measure the whole job when a revision arrives? No. Re-measure the lines the changes touch, and record that the other sheets were compared and showed no change. A full re-measure makes sense when the floor plate or the structural grid has changed, because most lines will have moved.

What if the revision has no clouds? Overlay every reissued sheet on the previous revision and read the differences. Clouds show what the consultant chose to flag, and a set can be reissued with real changes and no clouds at all. How to check a quantity takeoff starts with this check for the same reason.

Should subcontractors re-quote after a revision? If the revision changes their trade's quantities or specification, yes. Send them the specific sheets and bill lines that changed so the revised quote covers the same scope as everyone else's.