How do I take off structural steel from the drawings?

Structural steel is measured in tonnes. Read the section off the member schedule, the length off the framing plans, multiply by the kg/m, then add connections the way the engineer states. Plus the steel that never makes the structural set.

TL;DR: Structural steel is measured in tonnes, member by member. Take each member's section from the steel schedule, its length from the framing plans and sections, and multiply the length by the section's mass in kg/m. Add connections the way the engineer's notes state, list surface treatment and fixings separately, then go through the architectural drawings for the steel the structural set doesn't show.

A fabricator's quote comes back at 41 tonnes. Your takeoff says 36.

Nobody's wrong yet. The fabricator added plates, cleats and bolts, and you measured members only. Until both numbers are built the same way you can't compare them, and that's most of what a steel takeoff is about.

What unit is structural steel measured in?

Tonnes. Fabricators price supply, fabrication and erection by the tonne, so the takeoff has to end there.

You get to tonnes through length. Each hot-rolled section has a mass per metre, and for universal beams and columns it's in the name. InfraBuild's universal beam table lists the 310 UB at 40.4 kg/m, which is the section drawn as 310UB40.4.

So a 310UB40.4 that's 7.2 m long is 7.2 x 40.4 = 291 kg. Do that for every member, add them up, divide by 1,000.

Plates go by area x thickness x 7,850 kg/m³. Cold-formed purlins and girts are usually measured in metres by section, because that's how they're bought.

What do I read off the steel schedule and what off the framing plans?

The schedule and the plans each hold half the answer.

Set the takeoff out by mark - section, kg/m, length, number off, total kg. Keep columns, beams, bracing and secondary steel as separate groups so the tonnage can be checked group by group.

Then run one check before anything else. Every mark on the plans should have a line in the schedule, and every line in the schedule should appear on a plan. A mark with no section is an RFI.

How do I allow for connections?

The way the engineer states it. Don't pick your own number if the documents give one.

Structural notes often give a percentage to add to member mass for connections - plates, cleats, bolts and welds. As an example, if the notes say to allow 10% and the members total 36 tonnes, the connections line is 3.6 tonnes and the total is 39.6.

Show it as its own line. A fabricator checking your bill needs to see whether 39.6 includes connections or not.

If the notes are silent, you've got 2 options. Measure the connections off the details, which is slow and only works when the details are complete. Or state your own allowance in the bill and in your tender qualifications, and raise an RFI. Heavily detailed connections - moment frames, transfer structure - are worth measuring even when there's a percentage, because that's where a flat allowance runs short.

What gets missed in a steel takeoff?

Mostly steel that isn't on the structural drawings, and work that isn't tonnes.

Anything on that list that nobody priced gets built anyway, at the builder's cost.

There's more on which unit suits each trade in takeoff units of measurement, and the concrete side of the structure is in the concrete takeoff guide.

How does AI takeoff handle structural steel?

The measuring is lengths and counts, which is what AI takeoff does. The kg/m multiplication is a spreadsheet step either way.

CIM Build's AI takeoff calibrates the scale on each sheet against the dimensions printed on it, measures lengths, areas and counts, and returns a table with a marked-up copy of the sheet. So you can see which members were picked up on which framing plan and check them the way you'd check a junior's work.

In the bill of quantities, each line sits under the scope item it measures, with its unit, quantity and the sheet or clause it came from. Because CIM Build reads the drawings and the specification into the trade's scope first, steel shown on an architectural sheet has a scope line, and a scope line with no quantity stands out.

Book a briefing and bring the tender.

Frequently asked questions

Should I measure steel net or add waste? Net. Measure the length each member is fixed at and let the fabricator's rate carry offcuts and rolling margin. The ANZSMM, published by the AIQS, is the method of measurement to follow if your bill is prepared to it.

Do bolts count in the tonnage? Only if your connections line says so. Where the engineer gives a connection allowance, read what it covers. Where you measure connections yourself, state whether bolts are in the tonnes or priced as an item, so the fabricator's quote and your bill are built the same way.

How close should my tonnage be to the fabricator's? There's no standard figure. Compare group by group - columns, beams, bracing, secondary steel, connections. A gap in 1 group tells you what to look at. A gap spread evenly across all of them usually means one side has connections in and the other doesn't.


Published by CIM Build. This is the text of https://www.cim.build/uk/blog/steel-takeoff-guide without the site design. Index of all pages. Contact.