Do tender addenda need re-checking against the drawings when they only contain RFI responses?

Yes. An RFI response issued by addendum commonly becomes part of the tender documents, and a 1-line answer can change a wall type, a finish or a quantity without a single sheet being reissued.

TL;DR: Yes. An RFI response issued by addendum commonly becomes part of the tender documents, so a written answer can change scope even when no drawing is reissued. Check each response against the sheets and specification clauses it touches, mark up what it changes, and tell the trades it affects. Which document wins when the response and the drawing disagree is set by the conditions of tendering and the contract.

Addendum 3 arrives on a Thursday afternoon. 2 pages, 11 RFI responses, no drawings attached. The tender coordinator files it, sends the acknowledgement and gets back to chasing quotes.

Response 7 says the corridor walls on Levels 2 to 6 are to be the fire-rated type shown on the wall type sheet, in place of the type tagged on the plans.

That's a made-up example on an 84-apartment job. Nobody reissued the plans. The drawings still show the old tag, the partition subcontractors priced the old tag, and the answer that changed it is sitting in a PDF nobody opened twice.

Why does a text-only addendum matter?

Because it can change what you're pricing, and the drawings won't show it.

When a sheet is reissued, there's a revision letter, usually a cloud, and a line on the transmittal. People look. When the same change arrives as a sentence in an RFI response, there's none of that. The drawing register doesn't move, so anyone working from the register thinks nothing changed.

And you get more than your own answers back. Most tenders send every tenderer's questions and answers to all bidders. An answer to someone else's RFI can undo an assumption you made and never asked about.

What goes wrong with RFI responses?

These are the patterns I'd check for.

How do I check an RFI response against the drawings?

It's about an hour for a typical addendum if you do it the day it lands.

  1. List every response as its own line. Addendum number, response number, the question and the answer in a few words.
  2. Find what each one touches. The sheets, the schedule rows and the specification clauses. Write them beside the line.
  3. Open them and compare. Does the answer agree with what's drawn and specified, change it, or leave it unclear?
  4. Mark it up. For each change, note the response on your working copy of the sheet so the next person to open it sees it.
  5. Decide what it does to the price. Nothing, a quantity change, a rate change, a new item, or a follow-up question.
  6. Tell the trades. Send the response to every subcontractor pricing the affected package and ask them to confirm their quote covers it.

Step 6 is the one that gets skipped. A subcontractor who priced from the first issue won't know about response 7 unless you send it.

If the addendum also reissues drawings, compare the new sheets to the old ones as well. See how to compare drawing revisions. An answer in the text and a change on the sheet don't always match.

Which wins if the response and the drawing disagree?

The tender conditions and the contract decide that, so read them before you assume.

Commonly, the conditions of tendering say that addenda form part of the tender documents and ask tenderers to acknowledge each one. Many contracts also set an order of precedence between documents, and some tell the builder to raise any discrepancy it finds for direction. The wording differs between contract forms and between clients' amendments to them.

So I can't tell you a later RFI response always beats an earlier drawing. On a lot of jobs it will. Check your documents, and get a lawyer to read the clause if real money turns on it.

In practice, when you find a conflict during the tender, ask. Raise a follow-up RFI with both references on it. How to write an RFI covers the format.

What should go in the tender submission?

2 things.

List the documents you priced, including every addendum by number and date. If a dispute comes up a year later about what was in the price, that list is where it starts.

State the assumption for anything an addendum left open. If the revised detail never arrived, say what you allowed for. Tender qualifications and exclusions covers how these are usually set out.

Where does CIM Build fit?

When an addendum reissues drawings, revision tracking compares each new revision against the last one sheet by sheet and lists every change, including the changes nobody clouded. You can then check whether the reissued sheets match what the RFI responses said.

CIM Build also reads the drawings and specification into a scope of works for each trade, with the sheet and clause behind every line, so when a response touches a wall type or a finish you can see which trades carry it.

Findings and changes sit in registers with the source sheet and revision, an owner and a status.

A detected change is a prompt for your team to review. Whether it's a variation, and what notice it needs, is for the contract and the people administering it.

Book a briefing and bring the tender and its addenda.

Frequently asked questions

Does an RFI response change the contract documents? It can. Conditions of tendering commonly say addenda form part of the tender documents, and RFI responses are often issued that way. Whether a particular response ends up in the contract depends on how the contract lists its documents, so check the list before signing and get legal advice if it's unclear.

What if an RFI response contradicts the drawings? Raise a follow-up RFI that cites the response and the sheet, and ask which applies. If there's no answer before close, state the assumption you priced on in your submission.

Do subcontractors need to see tender addenda? Yes, for any package an addendum touches. Send them the relevant responses and ask each one to confirm in writing that their quote allows for them. Otherwise the quotes you level are priced on different documents to your tender.