If AI finds every issue at tender, will we price ourselves out of the job?

Finding an issue and pricing it are 2 separate decisions. Every finding at tender can go 4 ways: price it, qualify it, raise an RFI, or carry it as a known risk. How to choose for each one, and how to sort 60 findings in a tender week.

TL;DR: No. Finding an issue and pricing it are 2 separate decisions. Every finding at tender can go 1 of 4 ways - price it, qualify it, raise an RFI, or carry it as a known risk. The other tenderers have the same issues in the same documents whether they found them or not, so the review gives you the choice of which ones go in your number.

Say an AI review of an 84-apartment tender comes back with 60 findings. The estimator's first reaction is fair enough. If we price all 60, we're 3% over the builder who priced none of them, and we lose.

That's a made-up example, and it's a fair worry.

It assumes every finding gets priced. It doesn't have to.

Does finding an issue mean I have to price it?

No. A finding is information. What you do with it is a commercial call, and it's the same call a good estimator already makes on the issues they find by hand.

The difference is how many you get to make the call on. If the acoustic report asks for a heavier party wall than the drawings show and nobody on your team saw it, you've already made a decision. You've priced it at nothing and taken the risk, without knowing you did.

Your competitors are in the same position. The issue is in their documents too. Whoever wins the job builds the wall.

What are the 4 options for a finding?

OptionUse it whenWhat it does to your priceWhat you're left holding
Price itThe work will clearly have to be built, and the documents support itGoes up by the cost of the workNothing. It's covered
Qualify itThe documents conflict or are silent, and you've priced 1 readingStays at the reading you pricedA written record of what your price is based on
Raise an RFIThere's time for an answer before the tender closesDepends on the answerAn answer, usually issued to every tenderer
Carry it as a known riskIt's small, or you've decided to wear it to stay competitiveNo change, or a contingency you chooseA line on the risk register with a value against it

None of the 4 is wrong. Pricing something at nothing because you never saw it is the only bad outcome, because you can't manage a risk you don't know about.

When should I raise an RFI and when should I qualify?

Raise an RFI when the answer changes what everyone should price, and there's time to get it.

The response commonly goes out to all tenderers as an addendum. That takes the issue off the table for everybody. You lose a private advantage and you gain a level field, which suits you if you'd otherwise be the only one carrying the cost. There's a format in how to write an RFI.

Qualify when there's no time, or when the answer didn't come back. State which reading you priced and which sheet or clause it came from.

One caution. Some conditions of tendering treat a qualified tender as non-conforming, or limit what you can qualify. Read them before you write the letter, and get advice if they're unclear. More in tender qualifications and exclusions.

How do I sort 60 findings in a tender week?

Sort them before you decide on any of them.

  1. Put a rough dollar figure on each finding. Order of magnitude is enough.
  2. Take the top 10 by value. That's usually where most of the money is.
  3. For each of those, ask 2 questions. Will it definitely be built? Can the consultant answer before close?
  4. Definitely built, documents clear - price it.
  5. Unclear, and there's time - RFI.
  6. Unclear, and there's no time - price 1 reading and qualify it.
  7. Everything small goes on the risk register in 1 pass, with a single allowance if you want one.

On the example job, that might turn 60 findings into 6 priced items, 8 RFIs, 5 qualifications and 41 lines on a risk register. Those numbers are invented to show the shape. The price moves by the 6, and you know exactly what's sitting in the other 54.

What happens to the findings after we win?

A qualification that says "priced to wall type W3 as drawn on A-501 rev B" is a baseline. If a later revision upgrades that wall, you can show what you priced and what changed. Whether that's a variation is for the contract and a lawyer to decide, and the record is what lets you make the claim at all.

Without it, the extra scope gets built and nobody raises it.

The risk register carries across to delivery as well. The project team starts the job knowing the 41 things estimating already knew, which beats finding them 1 by 1 on site. There's more in what a scope gap is and what a variation is in construction.

Where CIM Build fits

CIM Build reads the drawings, specification, consultant reports and brief, checks them against each other, and returns findings. What happens to each finding stays with your team.

Every finding cites the sheet, the clause and the document it came from. The team triages each one as reviewed, needs action or RFI, and nothing goes to a consultant until a person sends it. AI-suggested RFIs, currently in beta, drafts the RFI from the finding for a person to review.

Findings sit in registers with the source sheet and revision, an owner and a status, and the registers re-run as revisions land. With lessons learnt, what was assumed at pricing stays attached to the scope it was priced on, so delivery inherits what estimating knew.

Book a briefing and bring the tender.

Frequently asked questions

Won't a competitor who ignores the issues always be cheaper? On the day, sometimes. They've priced the same building with some of it at nothing, and if they win they build it anyway. You can match their number on any finding by choosing to carry it as a known risk. The difference is that you chose it and put a value on it.

Should I tell the client about issues I've found in their documents? An RFI during the tender period is the normal way, and the conditions of tendering usually say how and by when. Some builders hold a finding back and qualify it in the tender letter. Check what the tender conditions allow, because they decide what a qualification does to your tender.