How should a builder run a pilot of AI drawing review on a live tender?

Pick one live tender, write the pass marks before you start, give the findings to the people already reviewing the set, and count what they confirm. A plain plan for a pilot that ends in a decision.

TL;DR: Run the pilot on one live tender with a real close date, alongside your normal review. Write down 4 or 5 pass marks before the first upload, clear data security first, and have the estimator and design manager triage every finding as confirmed, rejected or already known. Decide from the count of confirmed findings that changed an RFI, a qualification or the price.

Which tender should I pick?

A tender closes in 3 weeks. The set is 400 sheets, there are 6 consultant reports and a spec, and the estimator has 2 other jobs on the desk. That's the right one.

Pick a job that looks like your normal work. For most builders reading this, that's a mid-size new build - say 84 apartments over a basement - with a full consultant team and at least 1 addendum expected.

3 things make a tender a good test:

Some builders start on a tender they've already priced, because they know their own answers. That works as a first check. The live tender tells you more, because it tests whether the team uses the findings under deadline. We cover the timing in AI drawing review during a live tender.

What should I agree before the pilot starts?

The pass marks. In writing, before anyone sees a finding.

Without them, the pilot ends in "it seemed pretty good" and nothing happens. Write 4 or 5 lines like these:

  1. Every finding cites the sheet and the clause, and a reviewer can confirm it from the source.
  2. It finds issues our own review missed, and we can count them.
  3. It reports the changes in the addendum, including the ones nobody clouded.
  4. The findings export into the RFI register and Excel formats we already use.
  5. The estimator's checking time is less than the reading time it replaces.

Then agree who decides, and on what date. One director, one date, about a week after the tender closes.

Sort security before the first upload too. Your IT lead will ask where the documents are hosted, whether they train a model, and what independent testing exists. Get those answers in writing first. Our note on IT security approval for AI drawing review lists the questions.

Who should be involved?

Keep it small.

3 people is enough. Add a contract administrator if the job is design and construct and the brief is long.

Leave the normal review running. The pilot sits beside it, and the comparison between the 2 is the result.

What does the pilot look like week by week?

On a 3-week tender it runs roughly like this.

Week 1. Upload the set, the spec, the reports and the brief on day 1. Run the checks that match the job - reports against drawings, brief against drawings, code checks. The team triages the first batch of findings and raises RFIs while the question period is still open.

Week 2. The addendum lands. Compare it against the previous issue and check what changed. Run takeoff or a quote comparison on 1 or 2 trades if that's part of what you're testing.

Week 3. Close out the triage. Anything still open becomes an RFI, a qualification or an allowance. Submit the tender as normal.

How do I measure whether it worked?

Count 5 things.

MeasureHow to count it
Findings confirmedA reviewer opened the source and agreed
Findings rejectedA reviewer opened the source and disagreed, with a reason
Confirmed findings your own review hadn't raisedCompare against your RFI list and markups
Findings that changed somethingAn RFI, a qualification, an allowance or a price line
HoursTime spent triaging, against time normally spent reading

The rejected count matters as much as the confirmed one. If reviewers are wading through noise, they'll stop reading, and you want to know that in week 1. More on that in how AI drawing review tools handle false positives.

Also write down anything your team found that the tool didn't. A short, honest list of misses is the most useful thing to take back to the vendor.

What mistakes make a pilot useless?

4 common ones.

If the pilot goes well, the next question is cost against return. The business case for AI drawing review covers how to frame it for the board.

How does CIM Build run a pilot?

CIM Build's starting point is a briefing. You bring a current tender pack or a set from a job you know well, and the team runs it through CIM Build and walks you through what comes back, cited to your own sheets.

During a pilot the checks are the ones on the public feature pages. Report compliance reads each consultant report against the drawings and specification. Revision tracking compares each new issue against the last one and lists every change, clouded or not. Findings triage to reviewed, needs action or RFI, and nothing goes to a consultant until a person sends it.

Book a briefing and bring the tender.

Frequently asked questions

How long should a pilot of AI drawing review run? One full tender period is enough for a first decision, which is usually 3 to 6 weeks. It needs to cover the first review, at least 1 addendum or revision, and the week after close when you count the results.

Should the pilot use a live tender or one we've already priced? A priced tender is a fair first check because you know your own answers. A live tender tells you whether the team reads and acts on the findings under deadline, and that's what decides whether the tool gets used after the pilot.

Who should own the pilot inside the builder? One director owns the decision, and the estimator and design manager on the tender own the findings. Without a named owner the findings tend to sit unread until the tender has closed.