What is value engineering in construction, and how does a builder keep track of what changed?

Value engineering is a structured review of a design to get the required function for less cost. When it happens on Australian jobs, where accepted items go missing, and how a builder tracks each one through the drawings, the brief and the trades.

TL;DR: Value engineering (VE) is a structured review of a design to deliver the function the client needs for less cost. On Australian building jobs it mostly happens between tender and contract, when the builder and the principal agree a list of changes to bring the price to budget. Every accepted item changes the scope, and the drawings usually catch up later. A builder keeps track with a VE register that ties each item to its saving, the sheets and clauses it touches, and the revision where the change shows up.

The tender came in over budget. 3 weeks later there's a spreadsheet with 60 lines on it, 41 of them accepted, and a revised price everyone has shaken hands on.

The drawings still show the old building.

What does value engineering mean?

Reviewing a design to find a cheaper way to get the same function.

RICS publishes practice information on it, Value management and value engineering, which treats value as the relationship between the benefits delivered and the cost of getting them. Value management is the wider process, and Australia has a standard for it, AS 4183-2007 Value management. Value engineering is the part applied to the design itself.

So a VE item should hold what the building does and lower what it costs. Swapping one compliant wall system for a cheaper compliant wall system is VE.

Is value engineering the same as cost cutting?

In the textbook, no. On a VE list, both turn up.

Some lines keep the function and change the method. Others drop something - a lower finish grade, a smaller gym fit-out, a deleted awning. That second kind is a scope reduction with the principal's agreement.

Both are legitimate. They need different handling. A change of method has to be checked against the reports and the code, and the consultant responsible has to confirm it still complies. A scope reduction has to be written out of the brief, or the brief still asks for it.

When does value engineering happen?

Most often between tender and contract, when the preferred builder and the principal negotiate the price down to budget.

It also happens during the tender, when builders offer alternatives with their price, during early contractor involvement, and during design development on a design and construct job.

What does a VE item touch?

Usually more than the line on the spreadsheet says.

Here's a made-up example on an 84-apartment job. VE item 17 changes the party walls between apartments from masonry to a lightweight plasterboard system.

The saving is priced on the wall. But the change also touches:

If the consultants only update the wall type legend, the other 6 are still sitting in the documents as they were.

Where do VE items go missing?

In 4 places, and each one ends in cost the builder wears.

The drawings never catch up. The item is agreed, the price drops, and the issued for construction set still shows the original. Site builds what's drawn. The builder has given away the saving and built the dearer version.

The brief still asks for the original. On design and construct the builder owes the Principal's Project Requirements. If the PPR still calls for the item that was engineered out, the agreed saving and the contract disagree. See the PPR explained.

The knock-on scope isn't in anyone's price. The saving was priced on one trade and the extra work landed on another. That's a scope gap.

The subcontractor quoted before the VE. The package gets let on a quote that prices the old scope, or a new one that leaves out part of the changed scope.

How does a builder keep track of what changed?

With a VE register, started the day the list is agreed.

For each accepted item record:

Then do 3 things with it.

Get the accepted list into the contract. A schedule of accepted VE items listed as a contract document, with the brief amended to match, is what ties the price to the scope. How the documents rank against each other is a precedence question, so the contract and a lawyer decide. More in our tender-to-contract guide.

Check every later issue against the register. Each accepted item should show up as a change in the next revision. An item with no matching change is an open action. A change with no matching item is a question for the consultant, and it may be a variation the builder should claim. Methods are in how to compare drawing revisions.

Re-measure and re-quote. Update the quantities each item touches and send the affected trades the changed scope before the package is let.

Where does CIM Build fit?

CIM Build's revision tracking brings matched drawing pairs, comparison status and detected findings into one review workflow, so the team can check each issue for the changes the VE register expects and the ones it doesn't. Report compliance reads the consultant reports against the drawing set and the specification, and PPR vs the drawings re-runs the brief against every design issue. Each finding cites the clause and the sheet, and a person decides what to do with it.

Book a briefing and bring the VE list and the latest set.

Frequently asked questions

Who keeps the saving from value engineering? It depends on when it's agreed and what the contract says. A saving negotiated before contract is usually built into the contract sum. After contract, some contracts share the saving between the parties and others treat the change through the variation clause. Check your contract and get legal advice.

What is the difference between value engineering and value management? Value management is the wider, earlier process of agreeing what the project needs to achieve, covered in Australia by AS 4183-2007. Value engineering is applied to the design, looking for a cheaper way to deliver those needs.

Is a value engineering change a variation? Before the contract is signed it's part of the negotiation and should be written into the contract documents. After signing, a change to the agreed scope is commonly handled under the variation clause. The contract decides.


Published by CIM Build. This is the text of https://www.cim.build/us/blog/value-engineering-in-construction without the site design. Index of all pages. Contact.