Who is responsible if an AI compliance check gets it wrong?
The same people who were responsible before. Designers and builders design and build to the NCC, the certifier decides compliance, and an AI check doesn't move either job onto the software. Here's what a wrong answer looks like and how a team catches it.
TL;DR: The same people who were responsible before the software turned up. Designers and builders are responsible for designing and building to the NCC, the certifier or building surveyor decides compliance, and running an AI check doesn't move either job onto the tool. Treat the check like a reviewer on your team - it finds problems and cites them, and a person confirms each finding before anyone acts on it. We're a software company, so this is how we see it. Run your own contracts and insurance past your lawyer and your broker.
This one usually comes from the commercial manager, and it's a fair question.
Here's a synthetic example to work with. A Class 2 apartment floor, sheet A-2104 rev C, and the corridor to the fire stair is dimensioned at 950 mm. Clause D2D8 of NCC 2025 Volume One asks for at least 1 m of unobstructed width on a path of travel to an exit.
The check either flags it or it doesn't. So who wears it if it doesn't?
Who is responsible for NCC compliance in the first place?
The people, and the list is short.
The ABCB's roles and responsibilities page says builders and designers make sure buildings are designed and constructed in accordance with the NCC and applicable standards. Certifiers review building plans and inspect construction work to confirm compliance. Councils and state regulators enforce the building laws.
There's no software on that list.
In NSW it goes further. Under the Design and Building Practitioners Act 2020, a person who carries out construction work owes a duty to take reasonable care to avoid economic loss caused by defects (section 37), and section 39 says that duty can't be delegated. Other states have their own legislation, so check yours.
And then there's your contract. On design and construct (D&C) you've taken on the design, and your consultants answer to you for their part of it under their own agreements.
None of that changes when somebody on the team runs a check.
What does a wrong answer look like?
2 ways it can go.
- It flags something that's fine. Say it reads the 950 mm to the face of a column and the clear width beside it is 1,050. If the finding carries the clause, the sheet and the measurement drawn on the sheet, a reviewer opens it and dismisses it in a minute. The cost is that minute. It only gets expensive if somebody sends an RFI without opening the sheet.
- It misses something. The corridor really is 950 mm and nothing comes back. You're now exactly where you'd be if a person on your team had read that sheet and missed it. The design still doesn't comply, the designer who drew it still drew it, and the certifier may or may not pick it up before it's built.
The second one is the one people worry about, and they should. A miss by the software is still your miss.
Does running an AI check change who carries the risk?
No. It changes how much you know, and how early.
That cuts both ways, so be straight about it. A finding the team saw and never actioned is a harder conversation later than one nobody found. So every finding needs an owner and a status, and somebody has to close it.
A clean result needs the same care. It tells you the check found nothing on the sheets it read, against the provisions it read, on that revision. Nobody should file it as a compliance certificate.
And a flagged issue does nothing on its own. If it needs an RFI or a notice under the contract, a person has to issue it.
How does a team make sure a wrong answer gets caught?
The same way you'd manage a sharp junior.
- Confirm every finding against the source. Open the sheet and the clause before anything goes to a consultant. This is why a finding with no citation is close to useless.
- Keep the record. Which documents went in, which revision, what date. If a problem turns up later you'll want to show what was read.
- Put senior time on the judgement calls. Performance Solutions, state variations and anything on a fire or structural sheet still get an experienced read.
- Leave everyone else's job where it is. The consultant still checks their own design. The certifier still certifies. Send what you find to whoever owns that part of the design, as an RFI.
- Read the vendor's terms. Ask what they say about reliance and liability before you sign. Tell your professional indemnity broker how the team's using the tool.
How CIM Build is set up for this
We built it on the assumption that a person makes every call.
BCA assessment reads the architectural set against the provisions that apply to the building's class and construction type. Every finding cites the clause, the sheet and the revision, with the measurement drawn where it was taken. So the senior is checking a conclusion, and it takes seconds.
The team triages each finding as reviewed, needs action or RFI, and nothing goes to a consultant until a person sends it. AI-suggested RFIs are drafts - a person reviews every one before anything is sent.
Findings land in a register with the sheet and revision they came from, an owner and a status. The assessment re-runs on each issue, and what was read is on record.
The estimator or design manager decides what a finding means for the price or the schedule. Your certifier still signs off.
More on what the check itself can be relied on for in can AI check drawings against the NCC accurately enough to rely on.
Send us a set and we'll assess it against the code and show you the clause behind every finding.
Frequently asked questions
Is the software vendor liable if an AI check misses something? That comes down to the contract you sign with the vendor, so read the clauses on reliance and liability before you buy. Whatever they say, the duties on the designer, the builder and the certifier stay with them.
Does a clean AI check mean the drawings comply with the NCC? No. It means the check found nothing on the sheets and provisions it read, on that revision. The certifier or building surveyor decides compliance.
Can we rely on an AI check and drop our own review? We wouldn't. Use it to give every sheet the same first read, then spend your senior people's time confirming the findings and on the parts of the design that need judgement.