What is the difference between a cost plan, an estimate and a bill of quantities?

A cost plan is the client's budget split across the building while the design develops. An estimate is the builder's price for the work as documented. A bill of quantities is the measured, described list that gets priced. Who prepares each, when, and how they connect.

TL;DR: A cost plan is the budget for a project split across the parts of the building, prepared early and updated as the design develops, usually by a quantity surveyor for the client. An estimate is a priced forecast of what the work will cost, and for a builder it's the number behind the tender. A bill of quantities (BoQ) is the measured, described list of the work, sorted by trade, that rates get put against. The cost plan sets the target, the BoQ sets out what's being priced, and the estimate is the price.

Why do the 3 get mixed up?

Because all 3 are spreadsheets with a total at the bottom.

Say a developer's QS has a cost plan at $42 million for an 84-apartment building, and the builder's tender estimate comes in at $45 million. Both numbers describe the same building. They were prepared by different people, at different stages, from different information, for different reasons.

What is a cost plan?

A cost plan is how the client's budget gets allocated across the building while it's still being designed.

The Australian Institute of Quantity Surveyors describes a cost planner as someone who investigates financial feasibility in the early stages of a proposed project. Its competency standards put cost planning under its own unit. Its steps include clarifying the cost objectives with the client and weighing up alternative design solutions. The same document describes cost management as setting the budget, reporting against it and cost planning the evolving design.

So a cost plan moves. It's usually set out by element - substructure, columns, upper floors, roof, external walls, services - and reissued at each design stage as the drawings firm up.

Early cost plans run on rates per square metre and benchmarks from similar jobs, because there's little to measure yet. Later ones carry measured quantities.

Its job is to steer the design. Say the facade is 8% over its allowance at design development. That's the moment to change it, while it's still lines on a drawing.

What is an estimate?

An estimate is a priced forecast of what the work will cost.

The AIQS standards give cost estimating its own unit too. It covers preparing detailed estimates, developing unit rates and productivity factors, and advising on how accurate the estimate is.

For a builder, the estimate is the working behind the tender price. Quantities come off the drawings in a quantity takeoff. Rates come from subcontractor quotes and the builder's own cost history. Then preliminaries, risk and margin go on top.

A cost plan asks what the building should cost. A builder's estimate says what this builder will charge to build what's documented, and the builder carries the result.

What is a bill of quantities?

A bill of quantities is the measured list of the work, set out so it can be priced line by line.

The AIQS standards list what preparing one involves. Items are described, measured and quantified, sorted into sequence, and grouped under preliminaries and trade headings. Preamble clauses say what the rates include.

A BoQ has no prices in it until someone prices it. That's the difference from an estimate. In Australia, a QS-prepared bill usually follows the ANZSMM, and builders preparing their own trade bills often use a simpler house format.

A BoQ is easy to confuse with a schedule of rates. We cover that in bill of quantities vs schedule of rates.

How do the 3 compare side by side?

Cost planEstimateBill of quantities
What it isThe budget split across the buildingA priced forecast of the costA measured, described list of the work
Usually prepared byThe client's quantity surveyorThe builder's estimator, or a QSA quantity surveyor, or the builder for its own trades
WhenFrom feasibility, updated each design stageAt tender, and again for variationsOnce the design is documented enough to measure
Set out byBuilding elementTrade, to match the quotesTrade, with items in sequence
Has prices in itYesYesOnly once it's priced
Used toSteer the design to the budgetSet the tender priceGet quotes on the same basis

How do they connect on a real job?

In order, on a traditional job.

The QS writes the cost plan during design and updates it at each stage. When the documents go to tender, the builder measures them, sends trade packages out for quotes and builds an estimate. If a BoQ exists, the subcontractors price the same quantities and the quotes can be compared line by line. Without one, each subcontractor measures the job their own way.

Then the tender lands and someone lines it up against the cost plan.

The gaps between the 2 numbers are usually scope. The cost plan carried an allowance for something the drawings now show in detail, or the documents changed after the last cost plan was issued. A requirement in a consultant report that never reached the drawings will be in neither.

Where does CIM Build fit?

At the measuring end.

AI takeoff measures lengths, areas and counts off the PDF set, calibrates the scale on each sheet and marks up every measurement. CIM Build reads the drawings and the specification into a scope of works for each trade, then measures against it to build that trade's bill of quantities, with the unit, the quantity and the source sheet or clause on every line. It exports to Excel.

The rates, the allowances and the cost plan stay with your estimator or QS.

Book a briefing and bring the tender.

Frequently asked questions

Is a cost plan the same as an estimate? A cost plan is a kind of estimate that's structured to manage a budget through design. It's set out by building element and updated as the design develops. A builder's tender estimate prices the documented work by trade, and the builder is bound by it once the contract is signed.

Who prepares a bill of quantities in Australia? Usually a quantity surveyor, when the client wants every tenderer pricing the same quantities. Builders also prepare their own trade bills at tender so subcontractor quotes come back on the same basis.

Does a bill of quantities form part of the contract? Sometimes. It depends on the contract and what the tender documents say about the bill's status. Some contracts make the bill a contract document and others issue it for information only. The contract decides, so read it and get legal advice if the answer matters.