How do I take off windows, glazing and facade from the drawings and window schedule?

Windows are counted by type from the window schedule and reconciled against the elevations. Curtain wall and facade are measured in m² by system. What to read where, and the glass requirements that sit outside the schedule.

TL;DR: Count windows and glazed doors by type from the window schedule, then count them again off the elevations and plans and reconcile the 2. Measure curtain wall, shopfronts and other facade systems in m² by system type from the elevations. Then check the glass itself against the Section J report and the acoustic report, because the performance those reports ask for often isn't on the schedule.

The window schedule lists 412 windows. Count the tags on the elevations and you get 428.

16 windows is a number nobody enjoys finding after the glazing package is let. Whoever built the schedule missed a stack of W07s on the south elevation, and the glazier priced the schedule.

That's a synthetic example. The count is still the first thing to check.

What units are windows and facade measured in?

Shower screens and mirrors are glass, but they're usually a separate package. Put them somewhere on purpose.

What do I read off the window schedule and what off the drawings?

How do I reconcile the schedule with the elevations?

Count twice from 2 sources and compare by type.

Go through the elevations and tally each tag - W01, W02, D05 - per elevation and per level. Add them up by type. Put that next to the schedule's quantity for each type.

Where they agree, move on. Where they don't, go to the floor plans for that level and find the opening. It'll be one of 4 things - a window on the drawings with no schedule line, a schedule line with no window, a tag that's wrong, or a type that changed in a revision on one document and not the other.

Then check sizes on a sample. Scale 1 window of each type off the elevation and compare it to the schedule's width and height. A W03 scheduled at 1,800 wide and drawn at 2,400 is a different window.

For curtain wall and window wall, measure the area of each system on each elevation, slab edge to slab edge or as the details show. Keep vision glass and spandrel as separate areas. Count the doors, operable sashes and corners inside the system as extras.

What's in the reports that isn't on the schedule?

Glass performance, mostly.

The schedule might say "double glazed, clear". The Section J report gives the thermal values the glazing has to achieve, and they can differ by elevation. The acoustic report might call for a thicker laminated build-up on the 2 elevations that face the road.

If the schedule and the reports disagree, the glazier prices the schedule. The building still has to meet the reports. So the upgrade lands after the package is let, and unless it's a design change you can claim, it's at the builder's cost.

Read both reports against the schedule before you send the package out, and raise an RFI for every type where they differ. There's more on the thermal side in what is a Section J report and on the acoustic check in how to check an acoustic report against the drawings.

What else gets missed?

As an example, on a 6-storey block of 84 apartments, a missed restrictor on every bedroom window is a small item 150 or more times.

How does AI takeoff handle windows and facade?

Counting windows off the plans and reconciling them to the schedule is work a machine can do on every sheet, where a person tends to sample.

CIM Build's Schedule Creator reads the schedule, locates every door and window on the plans and reconciles the 2. It flags what's missing from the schedule, and where no schedule exists it builds one from the drawings.

For facade areas, AI takeoff calibrates the scale on each sheet, measures lengths, areas and counts, and returns a table with a marked-up copy of the sheet so you can see what was measured. And report compliance reads every consultant report against the drawing set and the specification, with each finding cited to the clause and the sheet.

Book a briefing and bring the tender.

Frequently asked questions

Should windows be measured in m² or counted? Both. Count them by type, because that's how they're made and ordered, and carry the m² per type so you can compare rates across quotes and check a quote that prices by area. Curtain wall and shopfront systems are measured in m².

Who measures the glass thickness? Nobody at takeoff. Glass thickness is designed by the glazier or facade engineer to AS 1288 for the wind load and the panel size. The takeoff carries the glass type and performance from the schedule and reports, and the glazier's price carries the thickness.

What if there's no window schedule at tender? Build one from the elevations and plans - tag, type, size, count, level - and send it out with the package, stated as your schedule. Every glazier then prices the same list, and when the architect's schedule arrives you compare the 2.