How do the NCC edition and state variations affect an AI compliance check?

An AI compliance check is only as right as the edition and the state it was run against. NCC 2025 applies in some states now and in others from 1 May 2027, and each state varies clauses. Here's what to settle before anyone reads a finding.

TL;DR: They decide which clauses the check reads against, so a wrong edition or a missed state variation gives you findings against rules that don't apply to your job. NCC 2025 was published on 1 May 2026 and the states adopt it on different dates, with NSW and Queensland on 1 May 2027. Each state and territory can also vary or add clauses. Confirm the edition and the state with your certifier before the check runs, and make sure every finding names the edition it was checked against.

2 jobs, same builder, same week. An 84-apartment building in Melbourne and another in Sydney, both Class 2, both going to tender in November 2026.

Run the same code check on both and the findings should differ.

Why does the NCC edition matter to a code check?

Because the clauses change between editions, and so do their numbers.

The ABCB's list of editions shows how often. NCC 2019 was adopted from 1 May 2019, with Amendment 1 from 1 July 2020. NCC 2022 was adopted from 1 May 2023, with Amendment 1 on 1 May 2025 and Amendment 2 on 29 July 2025. Then NCC 2025.

That's 6 versions in 7 years. A job that started design in 2022 and reaches site in 2027 can touch 3 of them.

The numbering moved as well. NCC 2022 brought in a new Section-Part-Type-Clause referencing system, and the ABCB says NCC 2022 shows the NCC 2019 numbering alongside the new references. So a finding cited to a 2019 clause number and a finding cited to a 2022 number can be the same provision.

For a check, that means 2 things. The requirement itself may be different in the edition that applies to you. And a finding that doesn't name its edition can't be confirmed at the source, because nobody knows which book to open.

When does NCC 2025 apply in each state?

It depends on the state, and the dates are a year apart.

The ABCB's adoption page says NCC 2025 was published on 1 May 2026. At the time of writing it lists these adoption dates.

State or territoryNCC 2025 adoption
Victoria1 May 2026
ACT1 May 2026, with a 12-month transition
Western Australia1 May 2026, with a 12-month transition
NSW1 May 2027
Queensland1 May 2027
South AustraliaBCA 1 May 2027, PCA 1 May 2026
Northern TerritoryNot adopted

Tasmania has a staged arrangement, set out on the ABCB page.

So the Melbourne job and the Sydney job in the example sit either side of a line. Victoria adopted NCC 2025 on 1 May 2026. NSW adopts it on 1 May 2027.

Which edition applies to a particular project is a state question. The ABCB's general FAQ says the NCC is given legal effect through its adoption into the regulatory frameworks of each state and territory, and it sends readers to their state or territory building and plumbing administration for which version applies to a specific project. Your certifier will know which side of the line the job falls.

What are state and territory variations?

Clauses a state has changed, added or switched off.

The same ABCB FAQ says each jurisdiction has the authority to modify the NCC to suit local conditions. The variations are listed at the back of each PDF volume and shown as overrides in the online NCC. If your state isn't listed for a clause, the standard provision applies.

In Volume One each state has its own schedule. NSW's is Schedule 5, and it includes NSW versions of Part J1 on energy efficiency and Part G7 on livable housing design.

The adoption page adds a warning. Some NCC requirements may apply at different times or not at all because of state or territory variations.

How does this change what an AI check returns?

A check run against the wrong book returns confident, cited, wrong findings.

Here's a made-up example. A NSW job gets checked against the national Part J1 with no NSW variation applied. The check returns 12 energy efficiency findings. The team spends a day on them before the ESD consultant points out NSW has its own Part J1. Some of the 12 don't apply, and whatever the NSW part asks for wasn't checked at all.

The second half is the one that costs money. A finding that shouldn't be there wastes a day. A requirement that was never checked gets priced at nothing and built at your cost.

What should you settle before running a check?

4 things, and it takes 1 phone call.

  1. The state or territory the building is in.
  2. The NCC edition and amendment the approval sits under. Ask the certifier, and get it in writing.
  3. Whether any state variation or transition arrangement changes the parts that matter most on this job - energy efficiency, livable housing, fire.
  4. Whether the consultant reports were written to the same edition. An acoustic or Section J report written to an earlier edition than the drawings is a finding by itself.

Then ask the software vendor 3 questions. Which editions does it hold? Does each finding name the edition and the clause? And how does it treat the state schedules?

If the vendor can't answer the third, check the varied parts by hand.

How CIM Build handles editions

BCA assessment assesses the architectural set against the provisions that apply to the building's class and construction type, and cites the clause, the sheet and the revision behind every finding.

The BCA/NCC volumes from 2019 to 2025 and the Red Book are preloaded, so the team can query them directly against the job.

The assessment re-runs on each issue, and what was read is on record. Consultant reports go through report compliance, which reads each report against the drawing set and the specification.

The certifier still decides compliance, as covered in can AI check drawings against the NCC, and the structure of the code in NCC volumes explained.

Book a briefing and tell us the state and the edition your job sits under.

Frequently asked questions

Which NCC edition applies to my project? Your state or territory decides, and the ABCB directs that question to the state building administration. Ask your certifier which edition and amendment the approval sits under before running any compliance check.

Has every state adopted NCC 2025? No. At the time of writing the ABCB lists Victoria, the ACT and Western Australia as adopting from 1 May 2026, NSW and Queensland from 1 May 2027, and the Northern Territory as not adopted. Check the ABCB adoption page for the current table.

Which NCC editions does CIM Build hold? The BCA/NCC volumes from 2019 to 2025 and the Red Book are preloaded, so the team can query them directly against the job.


Published by CIM Build. This is the text of https://www.cim.build/uk/blog/ncc-edition-and-state-variations without the site design. Index of all pages. Contact.