How do I find scope items with no quantity in a bill of quantities?

A bill of quantities only holds what somebody measured. How to list the scope for each trade, match every bill line to it, and decide what to do with each scope item that has no quantity against it.

TL;DR: Write the scope of works for each trade from the drawings and specification, with the sheet or clause behind every item. Then match every line in the bill of quantities to a scope item. Any scope item left with no line against it is unmeasured, and it's 1 of 5 things - missed, covered inside another line, unmeasurable yet, another trade's work, or a lump item. Decide which before the bill goes out for pricing.

The waterproofing bill has 2 lines. Wet area membrane in m² and balcony membrane in m².

The specification also calls for a membrane to the planter boxes on the podium, and there's a detail for it on a landscaping sheet the estimator never opened. No line, no quantity, no price.

That's a made-up example on an 84-apartment job, but it's the usual shape. Every line in the bill was right. The bill was still short.

Why can't I find the gap by reading the bill?

Because a bill of quantities only holds what somebody measured.

You can check every line for scale, arithmetic and units and it'll pass. The missing item isn't there to fail. So the check has to start from the scope and work towards the bill.

How do I build the list to check against?

Write a scope of works for the trade from the documents. For each item, record where it came from.

Keep each item to 1 line with its sheet or clause number. You'll need the reference when you raise the RFI.

How do I match the bill to the scope?

2 passes.

Scope to bill. Take each scope item and find the bill line that measures it. Write the bill line number next to the scope item. Where there's none, leave it blank and keep going. Don't stop to fix anything yet.

Bill to scope. Take each bill line and find the scope item it sits under. A line with no scope item is either work measured in the wrong trade or scope you missed when you wrote the list.

At the end you have a list of blanks. That list is what you came for.

What do I do with a scope item that has no quantity?

Sort each blank into 1 of 5.

  1. Missed. It's on the documents and it can be measured. Measure it and add the line.
  2. Covered inside another line. The corner beads are in the plasterboard rate, the flood test is in the membrane rate. That's fine if the line's description says so. If it doesn't, rewrite the description so the subcontractor prices it.
  3. Can't be measured yet. The design isn't finished or the extent isn't known, like rock or fire stopping around services nobody's coordinated. Carry it as a provisional quantity or a provisional sum and say so on the line. More in provisional quantities explained.
  4. Another trade's work. The screed sits with the tiler. Go to that trade's bill and confirm the line is there. If it isn't in either, it's a gap between 2 packages.
  5. A lump item. Mock-ups, shop drawings, commissioning. Add it as an item with no quantity so it's visible and priced.

Whatever's left after that is unclear on the documents. Raise an RFI with the sheet and clause while the consultant can still answer it during the tender.

Where should I look first?

If time's short, start where work crosses a boundary.

Then check the lines measured in "item" or "sum". Those hide the most, because nobody can tell what's inside them.

What if the bill came from someone else?

Same method. A bill issued by the principal's quantity surveyor still only holds what was measured, and how the contract treats an error or omission in it varies. Some contracts adjust for it and some put the risk on the builder. Read the clause, and ask your lawyer where it matters.

There's a longer guide on checking an existing bill of quantities against the drawings.

How does CIM Build show unmeasured scope?

CIM Build reads the drawings and specification into a scope of works for each trade, then measures against it to build that trade's bill of quantities.

Every bill line sits under the scope item it measures, with its unit, its quantity and the sheet or clause it came from. So a scope item with no quantity stands out before the tender closes, and the estimator decides how it's carried.

Book a briefing and bring the tender.

Frequently asked questions

What is a scope item with no quantity? It's work the drawings or specification require that has no measured line in the bill of quantities. It may have been missed, covered inside another line, left unmeasured because the design isn't finished, or measured in another trade's bill.

Is an unmeasured scope item always a mistake? No. Some work can't be measured at tender and is carried as a provisional quantity or provisional sum, and some is priced as a lump item. The mistake is leaving it invisible, with no line and no note, so nobody prices it.

Who pays if a bill of quantities leaves an item out? It depends on the contract. Some forms adjust the price for errors in a bill that forms part of the contract, and many lump sum contracts leave quantities at the builder's risk. The contract and your lawyer decide, so find the gap before you sign.

When should I run this check? Before the bill goes out with a trade package, again when quotes come back with exclusions, and after every addendum or reissued set.