What is a quantity takeoff in construction?

A quantity takeoff is the measured list of everything the drawings show - lengths, areas, volumes and counts - before any rates go on. What gets measured, how it's done, how it differs from a bill of quantities and an estimate, and where takeoffs go wrong.

TL;DR: A quantity takeoff is the measured list of the work shown on the drawings - lengths, areas, volumes and counts - taken off before any rates are applied. It's the first step in pricing a job. The quantities then get rates put against them to make an estimate, or get organised by trade and described line by line to make a bill of quantities. A takeoff is only as good as the set it was measured from, so every quantity should trace back to a sheet and a revision.

What does a quantity takeoff look like?

A table. Each row has a description, a unit, a quantity and, if it's done well, the sheet it came from.

Here's a made-up example for 1 trade on an 84-apartment job.

ItemUnitQuantitySource
Wall type W3, 92 mm stud, 13 mm fire-rated board both sidesm²4,260A-201 to A-208
Wall type W5, inter-tenancy, double studm²3,120A-201 to A-208
Shaft wall to risersm²640A-201 to A-208, A-450
Bulkheads, 600 mm deepm1,180A-301 to A-308
Access panels, 450 x 450 mmno.168A-301 to A-308

No prices yet. Rates are the next step.

The term comes from taking dimensions off the drawings. You'll also see it written take-off.

What gets measured, and in what units?

Most building work falls into 4 kinds of measure.

  1. Counts for things you buy by the item. Doors, sanitary fixtures, access panels, fire dampers.
  2. Lengths in metres for things that run. Skirting, cornice, kerbs, balustrade, pipe.
  3. Areas in square metres for things that cover. Partitions, ceilings, floor finishes, waterproofing, paint.
  4. Volumes in cubic metres for things that fill. Concrete, excavation, backfill.

Some trades use weight - reinforcement and structural steel are usually in tonnes.

The unit follows how the subcontractor prices the work. We've set out the usual unit for each trade in which units each trade is measured in.

Who does the takeoff?

On the builder's side, the estimator. The Australian Institute of Quantity Surveyors describes an estimator as the person who quantifies the materials, labour and equipment needed to complete a project.

Subcontractors do their own for their trade. And where the client wants a formal bill of quantities, a quantity surveyor measures it, usually to the Australian and New Zealand Standard Method of Measurement (ANZSMM), which AIQS sells.

How is a takeoff done?

The same 5 steps, whatever the tool.

  1. Confirm the set. Check the drawing register and the latest transmittal so you're measuring the current revision.
  2. Check the scale. Measure a printed dimension on each sheet before trusting anything else on it. A PDF printed to fit is the classic way to be out on every wall.
  3. Measure by type. Trace the walls by wall type, the floors by finish, the ceilings by system, and count the items against their schedule.
  4. Mark up what you measured. Colour the sheet as you go, so anyone checking can see what's been picked up and what hasn't.
  5. Record the source. Sheet number and revision next to every quantity.

Most estimators now do this on-screen in a PDF measuring tool, clicking each corner. On a mid-size tender the estimator spends days tracing walls and counting symbols before any pricing starts.

How is a takeoff different from a bill of quantities and an estimate?

They get used as if they mean the same thing. They're 3 steps in a row.

The takeoff is the raw measure.

A bill of quantities is the takeoff organised into a document a subcontractor can price - sorted by trade, each item described, with preambles that say what the rates include. The AIQS competency standards list those steps under preparing a bill of quantities.

An estimate is quantities with rates on them, plus preliminaries, risk and margin. It's the number that goes in the tender.

More on how the 3 sit together in cost plan vs estimate vs bill of quantities.

Where do takeoffs go wrong?

Rarely in the arithmetic.

The cost is the same each time - work that's on the drawings and missing from the price gets built at the builder's cost. Our guide to checking a quantity takeoff before pricing covers the checks worth running.

Can software do the takeoff?

Yes, with a person checking it.

AI takeoff reads the PDF set and measures it for you. In CIM Build you ask for the quantity in plain English - wall lengths by type, floor areas by finish, doors by fire rating. CIM Build's AI takeoff calibrates the scale on each sheet against the dimensions printed on it, measures, and returns a table with a marked-up copy of the sheet. So the estimator checks it the same way they'd check a junior's work.

The quantities then sit under a scope of works for each trade and build that trade's bill of quantities, with the sheet or clause on every line. The estimator adds the rates.

Book a briefing and bring a drawing set and the quantities you need.

Frequently asked questions

Is a quantity takeoff the same as a bill of quantities? No. The takeoff is the measured quantities. A bill of quantities is those quantities sorted by trade, described item by item and set out so a subcontractor can put a rate against each line.

Who is responsible if the takeoff is wrong? It depends on the contract. On a lump sum tender the builder usually carries the risk of its own quantities, and where the client issues a bill of quantities the contract says whether it forms part of the contract and what happens if it's wrong. Read the contract, and ask a lawyer if it matters.

Do builders need to measure to the ANZSMM? Only if the tender documents or the contract call for it. Many builders measure their own trade quantities in a simpler house format, which works if it's consistent across the trade.


Published by CIM Build. This is the text of https://www.cim.build/uk/blog/what-is-a-quantity-takeoff without the site design. Index of all pages. Contact.