What is tender levelling?

Tender levelling puts every subcontractor quote for a trade onto the same scope so the prices can be compared. What gets levelled, when it happens in a tender, who does it, and a synthetic example with the numbers.

TL;DR: Tender levelling is the work of putting every subcontractor quote for a trade onto the same scope so the prices can be compared. The estimator reads each quote against the drawings and specification, finds what each one includes, excludes or says nothing about, and then prices or clarifies every gap before comparing totals. It's also called quote levelling or tender normalisation. Bid leveling is the US term for the same job.

Three waterproofing quotes come back 2 days before the tender closes. One is a lump sum on a single page. One is a schedule of rates. One is a letter with the exclusions on the last page.

The totals are within about 10% of each other and that tells you almost nothing, because each subcontractor has priced a slightly different job.

Levelling is how you find out which job each one priced.

What does tender levelling mean?

Every subcontractor reads the documents their own way and prices in their own format. So 3 quotes for one trade package are really 3 different scopes with 3 different prices.

Levelling brings them back to one scope. You take the trade scope from the drawings and specification, check each quote against it line by line, and mark every item as included, excluded or silent. Then you deal with each gap - carry your own allowance, or send the subcontractor a clarification.

Only after that do the totals mean anything.

What does a levelled comparison look like?

Here's a synthetic example. The numbers are made up to show the mechanics.

Quote AQuote BQuote C
Quoted total$182,000$165,000$171,500
Screed to fallsIncludedExcluded - allow $14,000Included
Flood testingIncludedExcluded - allow $6,500Silent - clarification sent
Drawing revision pricedRev DRev DRev B - clarification sent
Levelled total$182,000$185,500$171,500, 2 items open

Quote B looked $17,000 cheaper than Quote A. Once the screed and the flood testing are carried it's $3,500 dearer.

Quote C is still the lowest, but it's priced to a revision 2 issues old and it doesn't say whether testing is in. So it stays open until the subcontractor answers.

And keep the original quoted total on the sheet next to the levelled one. The allowance is yours. The subcontractor hasn't agreed to it.

What gets levelled?

More than price. On most trades the estimator is checking 6 things.

  1. Inclusions. What the quote says it covers, matched to the scope items.
  2. Exclusions. Often on the last page, sometimes in a covering email.
  3. Silent items. Scope the quote doesn't mention either way. These carry the most risk.
  4. Qualifications and provisional sums. Conditions on access, hours, sequencing, and any sum that will be adjusted later.
  5. Quantities and units. A rate per m² against a rate per lineal metre can't be compared until the quantity basis matches. A bill of quantities sent out with the package fixes this before the quotes come back.
  6. The revision. Which drawing issue and which addenda the quote was priced on.

The gaps that turn up most are testing and certification, cranage and access, spoil disposal, and work that sits between 2 trades. More on that last one in what is a scope gap.

When does it happen in a tender?

Late, usually. Subcontractor quotes arrive in the last week and the builder's price has to go in on the closing date, so levelling gets squeezed into the days nobody has.

It then happens a second time. After the builder wins the job, each package is levelled again before it's let, this time with updated quotes and the contract set. A gap missed at tender can still be caught there. After the package is let, it's a variation.

Who does the levelling?

The estimator at tender, and the contract administrator or project team when packages are let in delivery. On larger tenders a senior estimator checks the trades that carry the most money.

It's slow work. Each quote has to be read against the drawings, and that means opening the sheets. Say 30 trades and 3 quotes a trade - that's 90 documents to read against the set.

Is tender levelling the same as tender evaluation?

They overlap. Tender evaluation usually means the client's side - a principal or their quantity surveyor assessing the builders' tenders on price, schedule, methodology and experience. Levelling is the price-and-scope part of that work, and builders use the word for their own comparison of subcontractor quotes.

Tender normalisation and quote levelling mean the same thing as tender levelling.

Where does AI fit?

The reading takes the time, and software can do the reading.

CIM Build's tender levelling reads every quote against the trade scope from the drawings and specification, lines them up item by item with the sheet and clause behind each line, and shows where one quote has allowed for work the others left out. It exports the comparison to Excel and drafts the clarifications for each subcontractor.

On a healthcare tender, CIM Build levelled 6 trades in about 24 hours, where the senior estimator would normally allow 2 weeks. On a healthcare tender it also found a six-figure dynamic pile load testing allowance that only 1 of the piling quotes had included.

The estimator still decides how each gap is carried. That call depends on the job and the subcontractor.

If you want the method step by step, it's in how to level subcontractor quotes. If you're comparing tools, start with what to check in AI tender levelling software.

Frequently asked questions

Is tender levelling the same as bid leveling? Yes. Tender levelling is the Australian and UK term and bid leveling is the US one. Quote levelling and tender normalisation are also the same work.

Why can't I just compare the quote totals? Because each subcontractor has priced a different scope. One has left out testing, another has priced an old revision, and a third hasn't said whether disposal is in. The totals only compare once every quote is on the same scope.

What do I level the quotes against? The trade scope taken from the drawings and specification, with the sheet or clause behind each line. If you level quotes against each other, an item all 3 subcontractors missed never shows up.

Can AI level subcontractor quotes? Yes. CIM Build reads each subcontractor quote against the trade scope from the drawings and specification, lines the quotes up item by item, flags the allowances one quote carries and the others leave out, and exports the comparison to Excel for the estimator to check.