How does a tender team find time to action AI drawing review findings during a live tender?

Run the review the day the documents land, give one person an hour to sort the findings by money, and send each one down 1 of 4 paths: price it, ask it, qualify it or park it for contract stage.

TL;DR: A tender team doesn't action every finding - one person sorts the list by what each finding could cost, and the team acts on the top of it. Each finding that survives goes 1 of 4 ways: it gets priced, it becomes an RFI, it becomes a qualification, or it's parked for contract stage. Run the review the day the documents land, because an RFI raised in week 1 gets answered and one raised in week 3 usually doesn't.

Say it's a 4-week tender on an 84-apartment job. The documents land on a Monday, the review runs overnight, and on Tuesday morning there's a register with 140 findings in it.

The estimator has 30 trades to send out by Friday.

That's a made-up example. The worry behind it is real though, and I hear it in most first meetings. The team's already flat out, and now there's a list.

How many of the findings does the team need to act on?

A small share of them. Most of the time on a list goes on sorting it.

A finding matters during a tender if it changes the price, changes what you ask, or changes what you exclude. A door tagged D14 on the plan and D41 in the schedule is a real finding and it's worth nothing this month. A fire engineering report that calls for a 2-hour wall where the drawings show 1 hour is worth pricing today.

So sort by money first. For each finding, ask what it costs if it's right and nobody picks it up. Big number, act now. Small number, leave it in the register and move on.

Some findings will be wrong, or right and irrelevant. Close those and keep going. There's more on that in how to deal with false positives.

Who should do the sorting, and when?

One person, in one sitting, on the first morning.

It should be whoever knows the job best - usually the lead estimator or the design manager on the bid. Give them an hour with the list before the trade packages go out. They mark each finding with a status and an owner and that's the triage done.

Don't share the raw list with the whole team. 6 people reading 140 findings is 6 hours gone, and everyone assumes someone else has the important ones.

What happens to each finding after that?

It goes down 1 of 4 paths.

Price it. The documents are clear enough to price and the scope is yours. A requirement in the acoustic report that never made it onto the wall types gets added to the partition package before it goes to market, so the subcontractors price it too.

Ask it. The documents conflict and the answer changes the price. That's an RFI, and it should go in the first week. Keep it to one question with the sheet and clause references attached. How to write an RFI covers the wording.

Qualify it. The question won't be answered before close, or the answer you got didn't settle it. Write the assumption you priced on into the submission. Tender qualifications and exclusions covers how these are commonly written. How much weight a qualification carries depends on the conditions of tendering and the contract, so have a lawyer read the ones that carry real money.

Park it. It's real, and it's a design coordination item for after award. Leave it in the register with its sheet reference. If you win, it's the start of the design manager's list.

How a finding moves the number is its own topic. See how AI findings affect the tender price.

When in the tender should the review run?

Day 1. Then again each time documents are reissued.

The value of a finding drops every day of the tender. In week 1 it can still become an RFI, change a trade package, and come back answered. In the last week all you can do is qualify it, and a submission with 40 qualifications reads badly to a client.

Running it early also changes what the subcontractors price. If the scope gap is in the package they receive, their quotes cover it. If you find it after the quotes are in, you're ringing 4 subbies for a revised number 2 days before close.

Addenda need the same treatment. A reissued sheet can undo an answer you already relied on, so re-run the comparison when it arrives. See whether addenda need re-checking against the drawings.

What does CIM Build do to cut the time?

Most of the time on a finding goes on confirming it and then writing it up. CIM Build shortens both.

Every finding cites the sheet, the clause and the document it came from, so the person reviewing it can open the source and confirm it in seconds. The team triages each finding as reviewed, needs action or RFI, and nothing goes to a consultant until a person sends it.

Findings sit in live registers with an owner and a status, and the register exports into the templates your contract admin already uses. So the parked items are still there, with their sheet and revision, when the job is won.

For the ones that become questions, AI-suggested RFIs drafts the RFI from the finding - the question, the sheets it concerns, the revision and the extract - for your team to review before anything is sent. That feature is in beta with a small group of builders.

The checks themselves cover the documents against each other. Report compliance checks each consultant report against the drawings and schedules, which is where a lot of the findings worth pricing come from.

Book a briefing and bring the tender.

Frequently asked questions

Is it worth running AI drawing review on a 2-week tender? Yes, if it runs in the first day or 2. On a short tender there's less time to raise RFIs, so more findings end up as qualifications or priced allowances, and you still want to know about them before the trade packages go out.

Who owns the findings once the tender is submitted? Whoever picks the job up if it's won - usually the design manager or the project manager. Hand over the register with each finding's status, the RFIs raised and the qualifications that went in, so the delivery team knows what was priced and what was assumed.

What if the review finds something in the last 2 days? Decide whether it changes the price by enough to matter. If it does, price an allowance or write the assumption into your qualifications. If it doesn't, leave it in the register for contract stage.