Shouldn't the consultants be checking their reports against the drawings, so builders don't have to?
Consultants check their own discipline. At tender, nobody is engaged to check every report against every sheet, and under many contracts the builder carries what falls between them. Who checks what, who pays, and what to do with what you find.
TL;DR: They should, and good consultants do check their own discipline. But each one is engaged for its own scope, and at tender nobody is engaged to check every report against every sheet. Where the contract puts the design risk on the builder, a requirement that sits in a report and never reached the drawings gets built at the builder's cost. So the builder checks before pricing, and sends what it finds back to the consultant as an RFI.
Say the acoustic report on an 84-apartment job calls for Rw+Ctr 50 on the party walls. The architect's wall type schedule shows a system that tests lower.
The acoustic consultant wrote a correct report. The architect drew a wall. Both did their job, and the 2 documents still disagree.
That's a made-up example. Most estimators can tell you a real one.
What are consultants engaged to check?
Their own work, mostly.
The acoustic consultant is engaged to write the acoustic report. The fire engineer writes the fire engineering report. The architect draws the plans, the wall types and the door schedule. Each of them reviews their own document before it goes out.
Carrying a requirement from 1 consultant's report onto another consultant's drawing is design coordination. That usually sits with the lead consultant or a design manager, and how much of it they're paid to do is set by their consultancy agreement.
At tender you usually haven't seen those agreements. You've got a set of documents and a closing date.
And the documents were often finished in a different order than they should have been. The report lands a week after the drawings were issued for tender, or the drawings get revised and the report doesn't.
Doesn't a design declaration cover it?
Partly, and later than you need it.
In NSW, registered design practitioners have to declare regulated designs for class 2, 3 and 9c buildings. The NSW Government's guidance says the declaration applies to construction-issued designs, and that they're lodged on the NSW Planning Portal before the relevant building work starts.
So that check happens on the construction set. Your tender price went in months earlier, on a tender set.
It's also a declaration about each design complying with the Building Code of Australia. A wall type can be a compliant wall and still be a cheaper wall than the one the acoustic report or the client's brief asks for.
Other states have their own rules. Check with your state regulator.
Who pays when a report and the drawings disagree?
The contract decides, and it's the first thing to read.
On a construct-only job the design commonly stays with the principal, and a discrepancy gets raised for direction. On design and construct the builder commonly takes on the design, often with the consultants novated across. Standards Australia publishes AS 4000 and AS 4902 as general conditions of contract, AS 4902 being the design and construct form, and both are commonly amended job by job.
So I can't tell you who pays on your job. The contract and a lawyer can.
What I can tell you is how it goes when the builder carries the design. The report's requirement was priced at nothing because nobody saw it. It turns up on site, the wall gets upgraded, and the builder wears the difference. More on that in design and construct contracts explained.
What should a builder check at tender?
Each report, against the sheet that's meant to show it.
- Acoustic report against the wall types, floor build-ups and door schedule. We've written that one up in how to check an acoustic report against the drawings.
- Fire engineering report against the fire door ratings and wall ratings on the drawings and schedules. See how to check a fire engineering report against the drawings.
- Geotech report against the footing and piling notes on the structural drawings.
- ESD or Section J report against the glazing and insulation shown in the schedules and sections.
- The brief or PPR against all of it.
Under tender pressure the team reads the reports it already worries about. The others get a skim. That's where the unpriced requirement sits.
What do I do with what I find?
Send it back to the consultant.
A conflict raised as an RFI in tender week costs the consultant an hour to fix. The same conflict found on site costs somebody a wall. So in a way you are getting the consultants to check their reports - you're telling them where to look.
Give them the report clause, the sheet number and the revision of each, and ask 1 question. There's a format in how to write an RFI.
If the answer doesn't come back before the tender closes, you still know about it. You can price it or qualify it.
Where CIM Build fits
Report compliance in CIM Build reads each consultant report - geotech, acoustic, ESD, fire, traffic, waste - and checks every requirement in it against the drawings and schedules. A wall drawn at a lower acoustic rating than the acoustic report calls for comes back as a finding cited to both documents.
The PPR check runs the brief and the drawing set against each other in both directions.
Each finding carries the clause, the sheet and the revision. A person triages it as reviewed, needs action or RFI, and nothing goes to a consultant until a person sends it.
Book a briefing and bring a set with its consultant reports.
Frequently asked questions
Can a builder rely on the consultants' reports being reflected in the drawings? I wouldn't price on that assumption without checking. Whether you're entitled to rely on it is a contract question, and the answer differs between construct-only and design and construct, and between a standard form and an amended one. Check the documents against each other, and ask a lawyer what your contract says about discrepancies.
Who is responsible for coordinating the consultants? It's set by each consultant's engagement. Commonly the architect or a design manager leads coordination, and on design and construct the builder often takes over that role after novation. At tender, assume nobody has checked every report against every sheet until you've seen evidence that they have.
Is checking the reports the builder's job on a construct-only contract? You may have less design risk, but the check still pays. A conflict you find at tender becomes an RFI and a clear price. A conflict nobody finds becomes an argument on site about who should have seen it. Whether you can claim for it later depends on your contract.