Will AI revision comparison catch a specification change when the drawing looks the same?

A drawing-to-drawing comparison can't see a specification change, because nothing on the sheet moved. Where spec changes hide in a reissue, how to catch them by hand, and what to ask an AI vendor about which documents its comparison covers.

TL;DR: A drawing-to-drawing comparison won't catch it, whether a person or AI runs it, because nothing on the sheet changed. A specification change gets caught 2 ways - by comparing the new specification against the previous issue, and by re-checking the specification against the drawings and schedules every time either one is reissued. Ask any vendor which documents its revision comparison reads.

Say you're pricing an 84-apartment job. The door schedule calls up door type D2 for every internal apartment door and sends you to the specification for the leaf.

Rev A of the spec says hollow core. Addendum 2 reissues the spec at rev B, and the same clause now says solid core.

The door schedule didn't change. The plans didn't change. 84 apartments at 6 internal doors each is 504 leaves, and every one of them is now a different rate.

That's a made-up example. The mechanism is real, and it catches people because the drawing comparison comes back clean.

Why does a drawing comparison miss it?

A drawing comparison puts the old sheet next to the new sheet and reports what's different between them. An overlay does that with colour. AI revision comparison does it by reading both sheets.

Either way, it's comparing drawings. The tag still says D2, in the same spot, on the same sheet. There's nothing to find.

The change lives in a different document. A tool or a person will only see it if they open that document as well.

Where do specification changes hide?

These are the usual places.

In every case the drawings point at the spec by code or by "refer to specification", and the pointer stays the same while the thing it points at changes.

How do I catch a spec change by hand?

It's a 5-step job, and the first step is the one that gets skipped.

  1. Put the specification on the drawing register, with its own revision, and treat a new issue like a new sheet.
  2. Run a text comparison between the old PDF and the new one, section by section.
  3. List every clause that changed, with the old wording and the new.
  4. For each clause, find what relies on it - the drawing tags, the schedule codes and the trade packages that priced from it.
  5. Update the takeoff and the trade scope, and record which revision each price is now based on.

Step 4 is where the time goes. One changed clause for D2 touches the door supplier, the hardware, the carpenter's labour and maybe the acoustic compliance.

More on the drawing side in how to compare drawing revisions, and on updating quantities in quantity takeoff after a drawing revision.

What should I ask an AI vendor?

4 questions will tell you most of it.

  1. Does your revision comparison read the specification and reports, or the drawings only?
  2. When a new spec is issued, do your spec-against-drawing checks run again?
  3. Does a finding cite the spec clause and the revision it came from?
  4. If the spec changed and the drawing didn't, where would I see it?

A tool that compares drawing pairs is doing a useful job. If that's all it compares, the spec is still yours to check.

How does CIM Build handle it?

2 separate things, and it's worth keeping them apart.

Revision tracking compares drawing sets. It matches the earlier and later sheets and lists the detected differences for review, including the changes nobody clouded. That's the drawing side.

The spec side comes from the cross-document checks. CIM Build reads every drawing, specification, consultant report and brief on every revision, and checks them against each other, with the sheet and clause behind each finding. Schedule Creator reconciles the door schedule with the plans and audits hardware, fire ratings, acoustic ratings and finishes against the specification.

It also shows up in the pricing documents. CIM Build reads the drawings and the specification into a scope of works for each trade, and every line in the bill of quantities carries the sheet or clause it came from. When a clause changes, you can see which lines were built on it.

A person still decides what the change means for the price.

Book a briefing and bring 2 issues of the same tender, specs included.

Frequently asked questions

If the specification and the drawings disagree, which one wins? The contract decides. Many building contracts set an order of precedence between the documents, and that clause is often amended job by job. Some also require you to notify a discrepancy when you find one. Read the precedence clause in your contract, and ask a lawyer where it's unclear.

Is a specification change after contract a variation? It can be, and that depends on the contract and on who made the change and why. What helps in every case is a record of which specification revision your price was based on, and the old and new wording of the clause. Without that, scope added by a quiet spec change gets built at your cost. The contract and a lawyer decide whether you're entitled to claim it.

Do I need to compare the whole specification every time? Compare all of it, then spend your time on the sections that changed. A text comparison of 2 PDFs takes minutes. The work is in tracing each changed clause to the trades and quantities that depend on it.