What is a window schedule, and what should it contain?

A window schedule is the table that lists every window on a job by tag, with its location, size, operation, frame, glazing and performance ratings. At tender, the blank cells and the windows on the elevations with no row are where the unpriced scope sits.

TL;DR: A window schedule is a table, usually prepared by the architect, that lists every window on a project by its tag with its location, size, operation, frame, glazing make-up and performance ratings. Estimators use it with the plans, elevations, specification and consultant reports to price the window package. A good one lets you count each window type and see what glass goes in it. At tender, check every tag against the drawings and treat every blank cell as a question.

W03 appears 84 times on the elevations. The schedule gives it a size and a frame colour, and the glazing column says "refer spec".

That's an example, but it's a common one. Until someone finds what the spec, the acoustic report and the Section J report each say about that glass, 84 windows have no price.

What does a window schedule include?

It ties each window tag on the drawings to what the supplier needs to price and make it. I'd expect 9 fields on a tender schedule.

Behind those fields sit 2 standards the specification will normally call up. AS 2047 covers windows and external glazed doors in buildings, and AS 1288 covers the selection and installation of glass. The wind and water ratings and the safety glass they lead to change the price of a window.

What does a window schedule look like?

Here are 3 rows from an example schedule for an 84-apartment building. The blanks are left in on purpose, because that's how a tender schedule arrives.

TagLocationSize (W x H)OperationFrameGlazingAcousticStatus
W01Living2,400 x 1,500SlidingAluminium, powder coatTo confirmTo confirmConfirm glass make-up and acoustic rating
W03Bedroom1,200 x 1,500Awning over fixedAluminium, powder coatRefer specTo confirmConfirm restrictor and facade acoustic rating
W07Bathroom600 x 900LouvreAluminium, powder coatObscure-Confirm safety glass and screen

The sizes and operations give you a count. The price sits in the columns that are still blank, and glass is where the money moves. Say the acoustic report asks for a heavier laminated glass on the bedrooms facing the road, and the schedule shows 1 glazing type for every W03. Half those windows are a different product. If nobody picks that up at tender, the builder ends up supplying the upgrade at its own cost.

What should you check before pricing the window package?

5 checks, in this order.

  1. Reconcile every tag both ways. Every window on the plans and elevations should have a row, and every row should have a window. Count each type off the elevations and compare it to the schedule quantity.
  2. Check the size basis. Confirm whether the scheduled size is the frame or the structural opening, then compare it with the opening on the structural drawings and the head and sill details.
  3. Check the glazing against the reports. Compare the glass make-up with the acoustic report, the Section J or energy report and the specification. What is a Section J report? explains where the U-value and SHGC targets come from.
  4. Check the revision. A schedule at Rev B priced against elevations at Rev D will be wrong somewhere. Note the revision of both.
  5. Check the trade interfaces. Who supplies the subframe, the flashings, the sealant, the flyscreens and the site glazing. Put it in the scope of works so it's priced once.

If the schedule and the drawings disagree, raise an RFI that names the tag, the schedule revision and the sheet. Which document governs depends on the precedence clause in the contract, so read that first.

We've also covered the door schedule and the finishes schedule, and the glazing takeoff guide covers measuring curtain wall and shopfronts that sit outside the window schedule.

Checking a window schedule with CIM Build

CIM Build's Schedule Creator reads the schedule, locates every door and window on the plans and reconciles the 2. You get the windows on the drawings with no line in the schedule, and the lines with no window behind them.

It audits hardware, fire ratings, acoustic ratings and finishes against the specification, with each finding referenced to its sheet. Where no schedule exists, it builds one from the drawings. It re-runs as revisions land and exports into the format your contract admin already uses.

For the reports, report compliance checks the acoustic and ESD reports against the drawings and the specification and cites the clause and the sheet for each finding. Your team decides what each finding means for the price.

Book a briefing and bring the tender.

Frequently asked questions

Who prepares the window schedule? The architect usually prepares it as part of the architectural set. The acoustic, energy and fire consultants set performance requirements in their own reports, and someone has to carry those into the schedule.

Is a window schedule the same as a glazing schedule? They overlap. A window schedule lists framed windows by tag. A glazing schedule lists glass types by code, and can cover curtain wall, shopfronts, balustrades and internal glazing as well. Some sets have both, and the window schedule points to the glazing schedule for the glass make-up.

Can I price windows from the schedule alone? No. The schedule gives you the count, the size and the operation. The price also depends on the glass make-up, the frame system, the wind and water rating and the hardware, and those often sit in the specification and the consultant reports. Leave unconfirmed fields visible and raise an RFI before award.