How long does AI drawing review take to set up, and how long to review a full tender set?

Setup is getting the documents in and deciding who reviews the findings. The machine read is the short part. What setup involves, what CIM Build's feature pages say about run time, where your team's hours go, and how to time it on your own tender.

TL;DR: Setup is mostly getting the documents in - upload the PDF set or connect the system they live in - and deciding who reviews what comes back. CIM Build doesn't publish a setup duration or a stopwatch time for a full tender set. Its feature pages say the whole set is assessed against the code in minutes and the week-long read of consultant reports is done in minutes. The time to plan for is your team's review of the findings, and the way to measure all of it is to run a tender you've already priced.

What does setup involve?

The tender closes in 3 weeks and the estimator is already measuring. Nobody on that team has a spare week to configure software, so the question is fair.

Setup for drawing review has 4 parts.

Getting the documents in. The review needs the drawings, the specification, the consultant reports and the brief. In CIM Build you upload the PDF set directly or pull it from where the project keeps it. It connects to Procore, Aconex, Autodesk Construction Cloud and SharePoint, plus Google Drive and Outlook. Nobody redraws or re-tags anything.

IT sign-off. Your IT team will want to know where the data sits and who can see it before a tender pack goes anywhere. Start that conversation first, because it runs on IT's calendar. The questions they'll ask are in what IT will ask before approving AI drawing review.

Deciding who reviews. Findings need owners. Usually the estimator takes scope and quantities, and the design manager takes compliance and coordination. Sort that out before the first run.

Your own checks, if you want them. Lessons learnt turns what past jobs taught the business into checks that run on every new set. That's optional on day 1. The code, brief and report audits run without it.

How long does the review itself take to run?

Minutes, on CIM Build's feature pages. I'll quote them and leave it there.

I won't put a single number on a full tender set. It depends on how many sheets and reports are in it, and we haven't published one. Time it on your own set.

How long does the manual version take?

This is the comparison that matters, and you know your own numbers better than I do.

CIM Build's feature pages describe the manual jobs this way:

Manual jobHow the feature page describes it
Consultant reports against the drawingsA week-long read
Comparing 400 sheets against the previous issueA week
Door schedule against the plans2 days of cross-referencing
Takeoff on a mid-size tenderDays tracing walls and counting symbols

In practice the bigger problem is that these jobs get done in part. Under tender pressure the team reads the reports it already worries about and trusts the rest.

Where do my team's hours go?

Into reviewing the findings.

Each finding carries a reference box with the clause, the sheet and the revision. The reviewer opens the source, confirms it, and triages it as reviewed, needs action or future RFI. Report compliance describes that confirmation as taking seconds.

Do the arithmetic on an example. Say a review of a made-up 84-apartment tender returns 150 findings, and your reviewer averages 1 minute each. That's 2.5 hours for one person, or an afternoon split between the estimator and the design manager. Your count and your pace will differ, and that's the number to measure in a trial.

Then there's acting on them. Pricing a gap, writing a qualification, sending an RFI. That part takes as long as it always did, and it's the work the tender was short of time for. More in finding time for AI findings during a live tender.

What happens when the set is reissued mid-tender?

The review runs again on the new issue.

Addenda are where a manual check falls over, because nobody has the days to re-check every sheet. With software the re-run is the cheap part. The code assessment page puts a reissue at minutes, and the registers re-run as revisions land, so your team reviews what changed.

For a whole-set comparison, bulk compare runs the set in 1 pass on an instruction written in plain English, and saves the instruction as a template for the next issue.

How do I time it on my own tender?

Book a briefing and bring a current tender pack or a set from a job you know well. The team runs it through CIM Build and walks you through what comes back, cited to your own sheets.

Bring a stopwatch and note 4 times:

  1. From handing over the set to the first findings.
  2. How long your reviewer takes on 20 findings.
  3. How many of the 20 were worth acting on.
  4. How long the re-run takes when you add the addendum.

Hold those against what the same tender cost you by hand. A fuller method is in how to pilot AI drawing review.

Book a briefing and bring the tender.

Frequently asked questions

How long does it take to set up AI drawing review? Setup is getting the documents in and agreeing who reviews the findings. CIM Build takes a PDF set by upload or from Procore, Aconex, Autodesk Construction Cloud or SharePoint, and doesn't publish a setup duration. IT approval is the step to start first.

How long does AI take to review a full tender set? CIM Build's feature pages say the whole set is assessed against the code in minutes and the week-long read of consultant reports is done in minutes. It doesn't publish one figure for a full tender set, so time it on your own documents at a briefing.

Do we need to train the AI on our projects first? No. The code, brief and consultant report audits run on the set you bring. Adding your own checks from past jobs is optional and can come later.

Is there enough time to use it on a 3-week tender? The run itself is the short part. Plan the review time. Give the findings an owner on day 1, and review them early enough that an RFI can still go out and a gap can still go into the price.