What is the ANZSMM and when do builders need it?
The ANZSMM is the Australian and New Zealand Standard Method of Measurement, the rulebook for how building work is measured and described in a bill of quantities. Builders need it when the tender documents or the contract name it.
TL;DR: The ANZSMM is the Australian and New Zealand Standard Method of Measurement, a set of rules for how building work is measured and described in a bill of quantities. The Australian Institute of Quantity Surveyors (AIQS) sells it, and the current edition is the second, dated 2022. Builders need it when the tender documents or the contract name it as the basis of measurement, or when they're pricing a bill a quantity surveyor measured to it. For in-house trade bills, a consistent house format is usually enough.
A subcontractor rings about the partitions bill. Their measure is 6% over yours and they want to know whether you deducted the door openings.
You did. They didn't. Neither of you is wrong, because nobody said which rule applied.
A standard method of measurement exists to settle that before the bill goes out.
What is the ANZSMM?
It's a published rulebook for measuring building work. For each trade it says what gets measured, in which unit, what the description has to state and what's deemed to be included in the item.
The AIQS sells it in print and as a digital publication. At the time of writing the digital copy is listed at $85 for non-members and $70 for members, and it's read online while logged in to the AIQS site.
The New Zealand Institute of Quantity Surveyors (NZIQS) publishes guidance notes for using it in New Zealand. Those notes describe ANZSMM 2022 as the second edition and as an update to the 2018 version. They also point out that what Australians call a bill of quantities is a schedule of quantities in New Zealand.
What does the ANZSMM cover?
The whole building, trade section by trade section. The NZIQS notes list sections for the 2022 edition that include:
- preliminaries
- demolition, groundworks and piling
- concrete, formwork and reinforcement, each as its own section
- masonry, structural steel and metalwork
- windows, glazing, carpentry and joinery
- partitions, suspended ceilings, doors and hardware
- hydraulics, drainage, electrical, mechanical and fire protection
So it reaches well past the structure. If a bill is measured to the ANZSMM, the ceiling subcontractor and the electrician are pricing lines written under the same rulebook as the concreter.
Is the ANZSMM the same as the ASMM?
They're different documents, and you'll still see both names in tender documents.
The Australian Standard Method of Measurement of Building Works (ASMM) is the older Australian title. Master Builders NSW still lists it in its store, where it gives the purpose as "to provide a uniform basis for the measurement of building works". The store page says its methods apply to preparing bills of quantities before work starts, and equally to measuring finished work and variations.
Check which document and which edition your tender names. A bill "measured in accordance with the ASMM" and one measured to ANZSMM 2022 may group and measure some trades differently.
When does a builder need the ANZSMM?
4 situations.
- The tender documents or the contract name it. If the bill of quantities is stated to be measured to the ANZSMM, the rules in it decide what each line includes.
- You're pricing a bill a quantity surveyor prepared. To price a line properly you need to know what's deemed included in it. The ANZSMM tells you whether an item you'd normally price separately is already inside the measured line.
- A quantity is in dispute. When a subcontractor and a builder get different numbers for the same wall, the named method of measurement is the first place to look.
- You're engaging a quantity surveyor to measure for you and want to understand what you'll get back.
In each case, buy the edition the documents name and read the general rules and the section for your trade. They're short.
When doesn't a builder need it?
When you're preparing your own trade bills to send out with trade packages and nothing in the tender calls for a standard method.
A house format works if it's consistent - the same units across the trade, a written rule for openings, descriptions a subcontractor can price without opening the drawings, and the sheet or clause behind each line. State your rules on the first page of the bill so nobody has to guess. Should a builder prepare its own trade bills covers when that's worth doing, and which units each trade is measured in covers the units.
Don't write "measured to ANZSMM" on a bill that wasn't. A subcontractor is entitled to read that line as meaning what it says.
Is the ANZSMM mandatory?
No. It's an industry document, and it applies to a job when the tender documents or the contract adopt it.
What follows from that - whether the bill is a contract document, what happens when a quantity is wrong, how departures from the method are treated - is set by the contract. Read the clause on bills of quantities in your form and get legal advice if money turns on it. Bill of quantities vs schedule of rates explains how quantity risk commonly sits under each.
Where CIM Build fits
CIM Build reads the drawings and the specification into a scope of works for each trade, then measures the quantities against it with AI takeoff to build that trade's bill of quantities. Every line carries its unit, its quantity and the sheet or clause it came from, and the bill exports to Excel. The estimator checks it, adds rates and decides what goes out.
Book a briefing and bring the tender.
Frequently asked questions
Who publishes the ANZSMM? The Australian Institute of Quantity Surveyors sells it in print and digital form through its website. The New Zealand Institute of Quantity Surveyors publishes guidance notes for using the 2022 edition in New Zealand.
What is the current edition of the ANZSMM? The second edition, ANZSMM 2022, which the NZIQS guidance notes describe as an update to the 2018 version. Tender documents written before it came out may still name an earlier document, so check the edition your job refers to.
Do subcontractors need to know the ANZSMM? Only when they're pricing a bill measured to it. Then they need to know what each line is deemed to include, or they'll price an item twice or leave it out. On a builder's house-format bill, the rules on the first page do that job.