How do I check mechanical, electrical and hydraulic drawings against the architectural drawings?

Check the services drawings against the architectural set in 5 passes: backgrounds, risers and plant rooms, ceiling space, fixtures counted both ways, and every note that says by builder or by others. Where the gaps usually sit.

TL;DR: Check mechanical, electrical and hydraulic drawings against the architectural drawings in 5 passes. Confirm the architectural background each services sheet was drawn over, check risers and plant rooms for space, check ceiling space at the tightest points, count fixtures and fittings both ways, and collect every note that says "by builder" or "by others". Each mismatch goes in a register with both sheet numbers and becomes an RFI or a line in a trade scope.

What does a mismatch look like?

A made-up example. Say an 84-apartment job. The mechanical drawings show a kitchen exhaust duct from every apartment running to a louvre on the facade. The architectural elevations show no louvres.

The mechanical subcontractor prices the duct to the wall and stops. The facade subcontractor prices the elevations. Nobody prices 84 louvres, the flashings around them or the penetrations through the facade.

It's found when the first duct reaches the wall. By then both packages are let, and the builder pays for the louvres.

Where do the mismatches usually sit?

  1. The background. Services consultants draw over an architectural background that's often a revision or 2 behind. A bathroom has flipped or a wall has moved, and the services still follow the old layout.
  2. Risers. The riser on the services drawing is bigger than the shaft on the architectural plan, or it doesn't stack between levels. Count the pipes and ducts in the riser and ask if they fit with access.
  3. Ceiling space. A duct, a sprinkler main and a cable tray crossing under a beam, with the ceiling height on the reflected ceiling plan leaving 250mm for all of it. Corridors and the run outside the core are the tight spots.
  4. Plant. Plant rooms and roof plant drawn at different sizes in the 2 sets. Condensers on balconies the architect drew without them. Hot water plant with no access path to get it in or out.
  5. Fixtures and fittings. The hydraulic drawings show 1 count of basins, floor wastes and tap points and the architectural plans show another. Power points that don't line up with the kitchen joinery. Light fittings on the electrical plan that differ from the reflected ceiling plan.
  6. Penetrations through rated walls. Services crossing fire-rated and acoustic walls, with no detail for the damper, collar or seal and no trade named to supply it.
  7. Roof and facade. Rainwater outlets, downpipes, overflows, exhaust louvres and hydrant booster cupboards that appear on the services drawings and are missing from the architectural roof plan and elevations.
  8. Builder's work. Plinths, access panels, trenching, penetrations and louvres marked "by builder" or "by others" on a services sheet. They're real scope, and they're drawn on the last sheets an estimator pricing concrete or facade would open.

How do I check it by hand?

  1. Check the revisions. Note the current revision of each architectural plan, then work out which architectural issue sits behind each services sheet. Anything behind is an RFI.
  2. Check the risers and plant rooms. List every riser by name. For each one, compare the size and position on the services plans against the shaft on the architectural plan, level by level. Do the same for plant rooms, switch rooms and meter cupboards.
  3. Check the ceiling space. Pick the tightest spots - corridors, under transfer beams, outside the lift core. Add up the depth of the services crossing there and compare it to the space between the structure and the ceiling.
  4. Count both ways. Take 1 of each apartment type and count the fixtures on the hydraulic, electrical and mechanical plans against the architectural plan and the fixture schedule. Then go the other way. Every fixture the architect drew should have a pipe, a wire or a duct going to it.
  5. Collect the notes. Search every services sheet and the services specifications for "by builder", "by others", "by architect" and "refer to". Each note gets a line and a trade.
  6. Raise the gaps. Design conflicts become RFIs that cite both sheets. Work that's drawn but owned by nobody is a scope gap, and it goes into a trade's scope of works before the package is let.

A synthetic register line looks like this - "M-301 rev B shows kitchen exhaust to facade louvre, all units. A-401 rev D elevations show no louvres. Missing. RFI to architect. Add louvres to facade scope."

What happens when a revision lands?

Services drawings usually trail the architecture. The architect reissues, and the services consultants catch up 2 or 3 weeks later, or at the next milestone.

So the check runs again each time either side moves. Record the pair of revisions you compared.

Doesn't BIM clash detection cover this?

It covers the hard clashes where the services and structure are both modelled. It won't tell you that 84 louvres are in nobody's price or that the fixture schedule and the hydraulic plan disagree on a count. More in AI drawing review vs BIM clash detection.

Doing it with CIM Build

CIM Build reads every drawing, specification, consultant report and brief on every revision and checks them against each other - drawings against specifications, one discipline against another. Each finding cites the sheet and the revision it came from.

Scope of works reads the drawings and specification into a scope register for each trade, with the sheet and clause behind every line. When quotes come back, they match against the register, so a gap between 2 packages shows up while both are still open.

AI takeoff counts fixtures and penetrations off the plans and marks up every one on the sheet, which makes the both-ways count quick to check. Revision tracking compares each new issue against the last and lists every change, including the changes nobody clouded.

Your team triages each finding as reviewed, needs action or RFI, and nothing goes to a consultant until a person sends it.

Book a briefing and bring the tender.

Frequently asked questions

Who is responsible for coordinating services with the architecture? It depends on the contract. The consultants are meant to coordinate their own documents, and on a design and construct contract that coordination commonly ends up with the builder's design team. Check the design obligations in your contract, and get a lawyer's advice on anything that turns on them.

What does "by builder" mean on a services drawing? It means the services consultant has drawn an item and left it outside the services trade. Plinths, penetrations, access panels and louvres are common. The services subcontractor will exclude it, so it needs a home in another trade's scope or in the builder's own allowances before the price goes in.

Can AI count fixtures off the services drawings? Yes. CIM Build counts fixtures and penetrations off the PDF set and marks up each one so an estimator can check the count. More in can AI count fixtures, joinery and FF&E.