How do I review tender documents before pricing?

A checklist for reviewing a tender package before you price it, by document type: drawings, specification, consultant reports, the PPR and addenda. What to check in each, the order to read them in, and what to do with what you find.

TL;DR: Review tender documents in 3 passes before pricing. First check the package is complete and current, then read each document type against a checklist, then read the documents against each other, because most missed scope sits where a report, the PPR or the spec asks for something the drawings don't show. Every finding ends as 1 of 4 things - it's priced, it's an RFI, it's a tender qualification, or it's an allowance.

Where do I start with a tender package?

The package lands on Monday. 240 drawings, a 600-page spec, 9 consultant reports and a brief, and the tender closes in 4 weeks.

Start with what you've been sent.

  1. Check the transmittal against the files. Every sheet and document listed should be there, at the revision listed.
  2. Read the conditions of tendering. Note the RFI cut-off date, the contact for questions, the form the price goes in on and whether alternatives are allowed.
  3. Read the contract. Lump sum or design and construct, the form it's based on, the order of precedence between documents, and who carries design, latent conditions and authority approvals. Flag the unusual clauses for whoever does your contract review.
  4. Set up a findings list. 1 row per finding with the document, the sheet or clause, and what you'll do about it.

Then go document by document.

What do I check in the drawings?

What do I check in the specification?

What do I check in the consultant reports?

Each report holds requirements the drawings are meant to have picked up. List them with their clause numbers, then find each one on the drawings.

Also check the date and revision of each report against the drawings it was written for. A report written against an earlier issue may describe a different building.

What do I check in the PPR?

On design and construct, the Principal Project Requirements are commonly what you're contracted to deliver, drawn or not.

There's a step-by-step in how to check the drawings against the PPR.

What do I check in the addenda?

More in do tender addenda need re-checking against the drawings.

What do I do with the findings?

Sort every finding into 1 of 4.

  1. Price it. The documents are clear enough, so it goes in the estimate and in the trade's scope of works.
  2. Raise an RFI. The documents conflict or something's missing, and there's time before the cut-off. See how to write an RFI.
  3. Qualify it. No answer in time, so the tender states what you've priced. More in tender qualifications and exclusions.
  4. Carry an allowance. The scope is real but undefined, and you've put a number against it.

A finding with none of the 4 against it is a scope gap. It turns up on site, and the builder pays for it out of margin.

How does CIM Build help with a tender review?

CIM Build's report compliance reads every consultant report against the drawing set and the specification, and PPR vs the drawings runs each clause of the brief against the drawings and the spec. Every finding cites the clause and the sheet. Scope of works reads the drawings and the specification into a scope register for each trade. The estimator checks each finding and decides how it's carried.

Book a briefing and bring the tender.

Frequently asked questions

How long does a tender document review take? It depends on the size of the package and how many people read it. By hand, cross-checking the reports and the PPR against a full drawing set takes days, which is why it usually gets sampled. Plan the review for week 1 so RFIs go out before the cut-off.

Who should review the tender documents? The estimator leads, with a design manager on the drawings, reports and PPR for a design and construct tender, and someone commercial or legal on the contract.

Which document wins if the drawings and the spec disagree? Check the contract. Many contracts set an order of precedence between the documents, and some require the builder to raise any discrepancy it finds. Don't assume either way. Raise an RFI or qualify the tender, and get legal advice on the clause if the amount matters.