How do I measure plasterboard and partitions for a takeoff?
Measure partitions in m² by wall type - length off the wall type plan, height off the wall type detail - then work out board from the layers on each side. Linings, bulkheads, shaft walls and trims are measured as their own lines.
TL;DR: Measure partitions in m² by wall type. Take the length of each type off the wall type plan and the height off the wall type detail and the sections, then multiply by the number of board layers on each side to get board area. Measure linings to concrete and masonry, shaft walls, bulkheads and trims as separate lines, because each one has a different rate.
The partition quotes all come back well over the allowance. Same drawings, same wall lengths.
The estimator measured every wall to the ceiling at 2.7 m. The wall type detail shows the party walls running to the underside of the slab at 3.0 m, with 2 layers of fire-rated board each side.
That's a made-up example, but height and layers are where a partition takeoff usually goes wrong. Length is the easy part.
What do I measure, and in what units?
Most of the trade is area. A partition takeoff for a builder usually has these lines:
- Partitions by wall type, in m² of wall (length by height).
- Linings to concrete, blockwork and columns, in m², one side only.
- Shaft and riser walls, in m², kept separate because they're built from one side.
- Bulkheads, in m, with the girth stated, or in m² if your subcontractors price them that way.
- Ceilings, in m², off the reflected ceiling plan. That's its own exercise - see how to take off ceilings from a reflected ceiling plan.
- Cornice, shadowline and square-set junctions, in m.
- Insulation in the cavity, in m², by wall type.
- Access panels, in number.
Pick the units once and hold them across every level. Which units each trade is measured in covers the other trades.
Which drawings and schedules do I read?
4 documents, and they all have to agree.
- The wall type plans. Each wall carries a tag - W1, W2, W3 - and you measure the length of each tag.
- The wall type schedule or details. This is where the stud size, the board type, the number of layers each side and the insulation sit. It also shows where the wall stops - at the ceiling, 150 mm above it, or at the underside of the slab.
- The sections and the reflected ceiling plans, for ceiling heights and slab-to-slab heights.
- The fire engineering report and the acoustic report. They set the ratings the wall types have to meet, and the wall type schedule doesn't always keep up with them.
If the plan shows a tag that isn't in the schedule, raise an RFI before you measure it as the nearest type.
How do I get from wall area to board area?
Wall area is length by height. Board area is wall area by the layers on each side.
Say a 6-storey job with 84 apartments has 1,000 m of party wall, type W3, running slab to slab at 3.0 m. That's 3,000 m² of wall.
W3 has 2 layers of 13 mm fire-rated board each side. So it's 4 layers, and 12,000 m² of board.
Price that wall as a standard 1-layer partition to a 2.7 m ceiling and you've allowed 5,400 m² of board. Less than half.
Measure net and keep waste out of the quantity. Subcontractors carry sheet waste in their rate, and adding it to the quantity as well is how it gets paid for twice.
Do I deduct door and window openings?
Decide the rule once and write it at the top of the takeoff.
Quantity surveyors in Australia usually measure to the ANZSMM, sold by the AIQS, and it sets out how openings are treated for each trade. If the bill says it follows the ANZSMM, follow that section.
If you're measuring for your own pricing, a house rule is fine. Whichever you choose, tell the subcontractors, so their quotes are on the same basis as your quantity.
What gets missed?
These are the ones I'd check on every job, because each of them is work that gets built whether it was priced or not.
- Walls that run past the ceiling. Fire and acoustic walls usually go to the slab. Measured to the ceiling, every one of them is short by the ceiling void.
- Layers. 1 layer priced where the detail shows 2.
- Walls with different linings each side. A wall between a bathroom and a bedroom has wet area board on one face and standard board on the other.
- Column and blade wall linings. They're on the plans as a thin line around the concrete and they don't carry a wall tag.
- Shaft walls and riser walls. Often drawn on the services drawings more clearly than on the architectural set.
- Bulkheads over kitchens, wardrobes and corridors. They show on the reflected ceiling plan and the sections, and almost never on the wall type plan.
- Fire sealant at the head of rated walls and acoustic sealant at the base.
- Access panels, especially the fire-rated ones.
Then run one cross-check. Divide the partition area by the partition length for a level. The answer should be a height you can find on the sections. If it comes out at 2.7 and half the walls are slab to slab, something's short. There's more of this in how to check a quantity takeoff before pricing.
How does AI takeoff handle partitions?
In CIM Build you ask for the quantity in plain English - wall lengths by type is one of the standard requests. AI takeoff calibrates the scale on each sheet against the dimensions printed on it, measures, and returns a results table with a marked-up copy of the sheet. You can see which walls were picked up under W3 and which weren't.
The bill of quantities then puts each line under the scope item it measures, with its unit and the sheet or clause it came from. A scope item with no quantity against it stands out - bulkheads are a common one.
The estimator still reads the wall type detail, decides the heights and signs off the bill.
Book a briefing and bring the tender.
Frequently asked questions
Is plasterboard measured in m² of wall or m² of board? Either works if it's stated. Most builders measure m² of wall by wall type, because the wall type fixes the studs, layers and insulation and the subcontractor prices it as a system. If you measure board area, show the layers.
How do I find the height of a partition? From the wall type detail first, then the sections. The detail shows where the wall stops, and the section gives you the ceiling height and the slab-to-slab height for that level.
Should I add waste to a plasterboard takeoff? Keep the measured quantity net and let waste sit in the rate. If your subcontractor wants a sheet count, give it as a separate figure next to the net area so nobody adds waste twice.