How is reinforcement measured for a bill of quantities?

Bar reinforcement is measured by weight in tonnes: the length of each bar size multiplied by its mass per metre. Mesh is measured in m² by type. Laps, starters and trimmer bars are where a reinforcement measure comes up short.

TL;DR: Bar reinforcement is measured by weight, in tonnes, split by bar size. You work out the total length of each bar size from the structural drawings and multiply it by that bar's mass per metre. Mesh is measured in m² by mesh type. Whether laps, chairs and tie wire are measured or carried in the rate depends on the method of measurement the bill states.

The reo allowance was 310 tonnes. The steel fixer's schedule came in at 352.

Nobody measured a bar wrong. The takeoff counted the bars drawn on the plans and left out the laps, the starter bars at every column and the trimmers around the penetrations.

That's a made-up example. The 42 tonnes still gets fixed on site, and if it wasn't in the tender it comes out of the builder's margin.

What units is reinforcement measured in?

Bar size matters because a tonne of 12 mm bar is a lot more pieces to place and tie than a tonne of 32 mm bar.

Which drawings and schedules do I read?

  1. The structural general notes. Lap lengths, cover, bar grade and standard hooks and cogs are all here, usually as a table. Read them first, because laps aren't drawn on the plans.
  2. The slab reinforcement plans, bottom and top. Bars are called up by size and spacing, something like N16 at 200.
  3. The footing, column, beam and wall schedules. Each one gives bar numbers, sizes and tie spacing for a mark.
  4. The standard details. Starter bars, trimmer bars at openings, edge bars, steps and setdowns are drawn once and apply everywhere.
  5. The concrete outline. You need the element sizes, so do the concrete measure first - see how to measure concrete quantities from structural drawings.

How do I get from a bar callout to tonnes?

4 steps for each callout.

  1. Count the bars. Divide the width the bars are spread across by the spacing, and add 1.
  2. Work out the bar length. Take the length of the element, less cover at each end, plus any hooks or cogs.
  3. Multiply for total length of that bar size.
  4. Multiply by the mass per metre.

Mass per metre comes from the supplier's bar table. You can check it yourself, because steel is about 7,850 kg/m³, so a 16 mm bar works out near 1.58 kg/m.

Say a slab panel is 10 m by 8 m with N16 at 200 each way, top and bottom.

Bars running the 10 m direction - 8,000 divided by 200, plus 1, is 41 bars at 10 m. That's 410 m. Bars the other way - 51 bars at 8 m, 408 m. So 818 m a layer and 1,636 m for both layers.

1,636 m at 1.58 kg/m is about 2,585 kg. Call it 2.6 tonnes, before laps.

I've ignored cover to keep the numbers clean. On a real panel you'd take it off each bar.

What about laps, chairs and tie wire?

Stock bars come in set lengths, so a long run is made of several bars lapped together. The lap length for each bar size is in the general notes. Every lap is extra steel.

Whether that steel is a measured quantity or sits in the rate depends on the method of measurement. Quantity surveyors in Australia usually measure to the ANZSMM, sold by the AIQS, and its reinforcement section sets out how laps, chairs, spacers and tie wire are treated. If the bill says it follows the ANZSMM, read that section and price to it.

If you're measuring for your own tender, pick a rule and tell the subcontractors. "Laps measured, chairs and tie wire in the rate" is a common one. What matters is that your tonnes and the steel fixer's tonnes are counted the same way before you compare them.

What gets missed?

Can I check the tonnes without measuring every bar?

Yes, and you should.

Divide the reinforcement weight for an element by its concrete volume. You get kg of steel per m³ of concrete. Compare that figure across similar elements on the job - one typical floor against the next - and against jobs your team has built with the same structural system.

I won't give you a benchmark figure, because it swings with the engineer and the system. If 2 floors with the same slab come out 20% apart, go back to the markup.

How to check a quantity takeoff before pricing has the other checks.

How does AI takeoff handle reinforcement?

CIM Build's AI takeoff measures lengths, areas and counts off the PDF drawing set. You ask for the quantity in plain English, it calibrates the scale on each sheet, and it returns a results table with a marked-up copy of the sheet you can check.

The bill of quantities puts each line under the scope item it measures, with its unit, its quantity and the sheet or clause it came from. A scope item with no quantity stands out - trimmer bars and starters are worth looking for.

The mass per metre, the lap rule and the sign-off stay with the estimator.

Book a briefing and bring the tender.

Frequently asked questions

Is reinforcement measured in tonnes or kilograms? Tonnes in most bills, by bar size. Kilograms turn up on smaller jobs and in bar schedules. Either is fine if the unit is the same on every line.

Is mesh measured by weight or by area? By area, in m², by mesh type. Whether sheet laps are measured or allowed in the rate depends on the method of measurement stated in the bill, so check before comparing your area to a supplier's sheet count.

Who prepares the bar schedule? Usually the reinforcement supplier's scheduler, from the for-construction drawings, after the job is won. A tender takeoff is an estimate of that schedule, which is why the lap and starter allowances need to be stated.