What is a trade package in construction, and how do scope gaps form between packages?

A trade package is the bundle of work a builder sends to market for one trade - the scope of works, the drawings, the spec sections and the conditions. Scope gaps form at the edges, where 2 packages each assume the other one has the work.

TL;DR: A trade package is the bundle of work a builder sends to market and lets to 1 subcontractor - the scope of works, the relevant drawings and specification sections, any bill of quantities, and the subcontract conditions. A multi-residential building can be split into 30 or more of them. Scope gaps form at the edges, where work touches 2 trades and each package assumes the other one has it. The fix is to give every interface item an owner in 1 package before either package is let.

What is a trade package?

It's how a builder buys the job.

A builder on a commercial project does very little of the physical work with its own labour. It splits the building into packages - concrete, formwork, structural steel, waterproofing, tiling, partitions and ceilings, joinery, hydraulic, mechanical, electrical, fire services and so on - and lets each one to a subcontractor.

You'll hear them called subcontract packages or work packages too. The Australian Institute of Quantity Surveyors' competency standards list determining the trade breakdown as a step in preparing a bill of quantities, and the bill's sections follow the trades.

What goes in a trade package?

5 things, usually.

  1. A scope of works. The written list of the work this trade is pricing. More on writing one in our scope of works guide.
  2. The drawings and schedules that show the work, with their revisions listed.
  3. The specification sections for the trade, plus the general sections that apply to everyone.
  4. A bill of quantities or pricing schedule, if you want the quotes back on the same basis.
  5. The commercial terms. Subcontract conditions, the schedule dates, insurances, site rules.

The scope of works matters most. The drawings show the building. The scope says which part of it this subcontractor is pricing.

How does a builder decide the split?

By how the market prices the work.

Packages follow the way subcontractors are set up. A partition contractor does stud walls and ceilings, so they go out together. Some waterproofers tile and some don't, so the split depends on who you're asking to quote.

Size and sequence matter too. Say an 84-apartment job has a precast facade and a small amount of precast in the stair cores. You might let them as 1 package for the buying power, or as 2 because the cores are needed months earlier.

There's no standard list, and the split shifts from job to job.

How do scope gaps form between packages?

The drawings are drawn by discipline. The packages are let by trade. The 2 don't line up, and every place they don't line up is an edge someone has to assign.

A scope gap is work the documents require that isn't in anyone's price. Between packages, they form in 4 ways. The examples are made up.

1. Both trades assume the other has it. The floor build-up shows a screed under the tiles. The waterproofer prices to the drawings and leaves the screed to the tiler. The tiler leaves it to the waterproofer. Both quotes look complete.

2. The work sits on another discipline's drawings. Fire stopping around pipe penetrations is detailed in the fire engineering report and on the hydraulic drawings. The partition contractor never opened either. The plumber assumed the wall contractor seals walls.

3. The scope was copied from the last job. The template says the door supplier provides hardware. On this job, 40 doors have electric strikes wired to the access control system. The door supplier excludes anything with a cable. The electrician priced the access control drawings, which show the reader and leave out the strike.

4. The documents changed after the package went out. An addendum adds a hob to every balcony door threshold. The concreter's quote was already in, and nobody sent the revised detail to the waterproofer either.

Exclusions in the quotes make it worse. A subcontractor is entitled to exclude work, and most do. An exclusion only becomes a gap when no other package picks it up.

What happens when a gap gets through?

The work still gets built.

It turns up on site when a subcontractor says it's outside their scope. By then both packages are let, so the builder prices it again at a worse rate with no competition, and the margin pays for it.

There's usually nothing to claim upstream. The work was in the tender documents all along, so it isn't a change. Whether a particular item is in or out of a subcontract comes down to that subcontract's wording, so the contract and a lawyer decide.

How do you close the gaps before the packages are let?

4 habits do most of it.

  1. Write each scope from this job's documents. Read the drawings and the specification for the trade and list what they show, with the sheet or clause next to each line.
  2. Keep an interface list. Every item that touches 2 trades goes on 1 list with 1 owner. Screeds, fire stopping, lintels, cast-in plates, flashings, access panels, penetrations, electrified hardware, making good.
  3. Line every exclusion up against the scope. When the quotes come back, match each exclusion to the scope line it removes, then check another package carries it. Our guide to levelling subcontractor quotes walks through it.
  4. Re-check on every addendum. If a detail changed, ask which packages it touches and whether their quotes were priced on the new issue.

Done by hand, that's reading the set once per trade, so under tender pressure it gets done from memory.

Where does CIM Build fit?

This is the reading CIM Build does.

Scope of works reads the drawings and the specification into a scope register for each trade, in the order the work happens, with the sheet and clause behind every line. When quotes come back, tender levelling matches each quote's inclusions, exclusions and qualifications to the register, so the gap shows up while both packages are still open.

The estimator decides which package carries it.

Book a briefing and bring a trade package and the quotes that came back.

Frequently asked questions

Is a trade package the same as a scope of works? No. The scope of works is 1 document inside the package. The package also includes the drawings, the specification sections, any bill of quantities and the subcontract conditions.

How many trade packages does a typical building have? It depends on the job and on how the builder likes to buy. A multi-residential building can run to 30 or more, and a builder can combine or split trades to suit the subcontractors it's pricing with.

Who is responsible for a gap between 2 trade packages? In practice the builder usually ends up paying for it, because the builder wrote the packages and holds the contract with the client for the whole job. Whether a subcontractor is liable for a particular item depends on the wording of that subcontract. That's a question for the contract and a lawyer.