How do I check a Section J report against the drawings and window schedule?

List every input the Section J report relies on with its clause or table number, find the window schedule line, wall type or spec clause that should carry it, and mark it shown, missing or conflicting. Start with the glazing.

TL;DR: To check a Section J report against the drawings, list every input the report relies on - glazing U-values and SHGC by facade, insulation R-values for roofs, walls and floors, shading, roof colour and services efficiencies - each with its table or clause number. Then find the window schedule line, wall type, finishes schedule entry or spec clause that should carry each one and mark it shown, missing or conflicting. Start with the window schedule, because glazing is where the money is. Rerun the register whenever the drawings or the report are reissued.

What does a mismatch look like?

A made-up example. Say an 84-apartment building with retail on the ground floor. The Section J report gives the retail shopfronts a maximum U-value and a maximum SHGC. The window schedule calls up clear laminated glass in a standard frame, with no performance values at all.

The glazier prices the schedule. The glass that meets the report is a different product in a different frame, with a longer lead time.

It gets found at shop drawings or when the certifier asks for evidence. By then the glazing package is let on the cheaper glass and the difference is the builder's cost.

What does a Section J report ask for?

Section J is the energy efficiency section of NCC Volume One. In NCC 2022 it has 9 parts, including building fabric (J4), building sealing (J5), air-conditioning and ventilation (J6) and artificial lighting and power (J7). Part J3 covers apartments.

The report shows how the design complies. That's either clause by clause against the Deemed-to-Satisfy provisions, or through a verification method in Part J1 - NABERS Energy (J1V1), Green Star (J1V2) or a reference building (J1V3). Here's the difference between Deemed-to-Satisfy and a Performance Solution.

Apartments can go through house energy rating software. Under J3D3 the units have to average at least 7 stars with no unit under 6. NSW is different - J1P2 doesn't apply there and BASIX applies.

Whichever path it takes, the report ends up fixing a list of inputs.

Clause numbers here are from NCC 2022. Check which edition and state variations apply to your job.

Where do the mismatches usually sit?

  1. The window schedule. The performance columns are blank, or they carry glass-only numbers. Specification 37 says Total System values account for the combined effect of the glass and the frame. A centre-of-glass U-value from a glass brochure is a different number.
  2. Window sizes. The report was calculated on the glazing areas at 1 revision of the drawings. The windows have grown since and the report hasn't been rerun.
  3. Shading. The calculation relied on a sunhood or a screen that was deleted in a value engineering round.
  4. Wall types. The report asks for a Total R-Value and the wall type legend shows thinner insulation, or a wall between a conditioned space and a car park has none.
  5. Soffits. Apartments or retail sit over an open car park, the report wants insulation under the slab, and it's on no drawing and in no trade's scope.
  6. Roof colour. The finishes schedule picks a dark roof sheet and the report assumed a light one.

How do I check it by hand?

  1. Build the register. Read the report end to end, including the appendices and the assumptions page. Give every input its own line with the table or clause number. Note which drawing revision the report says it was based on.
  2. Name the document that should carry it. Glazing goes to the window schedule and the glazing spec. Insulation goes to the wall type legend, the roof details and the spec. Roof colour goes to the finishes schedule. Lighting goes to the electrical drawings.
  3. Check each line. Shown, missing or conflicting. Write down the sheet and the revision you checked against.
  4. Go the other way for glazing. Take every window and glazed door on the elevations and confirm it has a schedule line with a U-value and an SHGC that meet the report for that facade.
  5. Raise the gaps. Each missing or conflicting line becomes an RFI citing the report table and the sheet. Send the question to the ESD consultant as well as the architect, because sometimes the fix is rerunning the report.

A synthetic register line looks like this - "Report table 3, north facade glazing, max Total System U-Value and SHGC stated. Window schedule A-610 rev C, W01 to W14, no performance values. Missing. RFI to architect and ESD consultant."

What happens when a revision lands?

The report goes stale faster than most. A bigger window, a deleted sunhood or a swapped wall system changes the calculation, and the report is still dated 4 months ago.

So rerun the register on each issue, and ask 1 extra question every time - has the facade changed since the report's base revision? If it has, the report needs reissuing before anyone orders glass.

Doing it with CIM Build

CIM Build's report compliance reads every consultant report against the drawing set and the specification and returns each finding cited to the clause and the sheet. A Section J report goes in with the acoustic, ESD and fire reports.

Schedule Creator handles the window side. It locates every door and window on the plans, reconciles them to the schedule both ways and flags what's missing.

Book a briefing and bring the tender.

Frequently asked questions

What's the difference between U-value and SHGC? The U-value measures how easily heat passes through the window, and a lower number insulates better. SHGC is the solar heat gain coefficient, the fraction of the sun's energy that ends up as heat inside, and a lower number lets in less. A Section J report usually sets a maximum for both.

Who makes sure the drawings match the Section J report? The ESD consultant writes the report, and the architect and services consultants are meant to carry it into their documents. On a design and construct contract the coordination commonly ends up with the builder's design team. Your contract decides, so check the design obligations in it.

Does a Section J report apply to apartments in NSW? Partly. The NCC says performance requirement J1P2 for apartment thermal performance doesn't apply in NSW, where BASIX applies, and NSW has its own variations to Section J. Ask the ESD consultant which parts of the building the report covers. More in what is a Section J report.