What is the difference between a deemed-to-satisfy solution and a performance solution?
Both are ways to meet the NCC's Performance Requirements. A deemed-to-satisfy solution follows the provisions written in the code. A performance solution is a design-specific answer that has to be assessed and documented in a final report. Here's how each works and what changes for the builder.
TL;DR: Both are ways to meet the Performance Requirements of the National Construction Code (NCC). A Deemed-to-Satisfy (DTS) Solution follows the provisions written in the code and is deemed to comply. A Performance Solution is a design-specific answer that has to be shown to meet the Performance Requirements, or to be at least equivalent to the DTS Provisions, and documented in a final report. One building can use both.
The code gives a number. Then a consultant's report gives a different number for the same thing, and the drawing follows the report.
That usually means the design has moved from one compliance path to the other for that item. Which path each item is on changes what you price and what you check.
What does the NCC ask for?
The NCC is written around Performance Requirements. The ABCB calls them the minimum level that buildings must meet.
Clause A2G1 of NCC Volume One, Part A2 says compliance is achieved by complying with the Governing Requirements and the Performance Requirements. The Performance Requirements can be satisfied 3 ways - a Performance Solution, a Deemed-to-Satisfy Solution, or a combination of the 2.
What is a deemed-to-satisfy solution?
It's the recipe.
The NCC glossary defines Deemed-to-Satisfy Provisions as provisions which are deemed to satisfy the Performance Requirements. Clause A2G3 says a solution that complies with them is deemed to have met the Performance Requirements.
So if the design follows the clause, nobody has to argue the engineering behind it. Compliance is shown through evidence of suitability or Expert Judgement. Part A5 lists what counts as evidence, including a CodeMark certificate, a report from an Accredited Testing Laboratory, or a certificate or report from a professional engineer.
Most of a typical building is DTS.
What is a performance solution?
It's an answer written for one building.
Under clause A2G2, a Performance Solution has to demonstrate compliance with all relevant Performance Requirements, or that the solution is at least equivalent to the DTS Provisions.
It's shown through one or more of the NCC's 4 Assessment Methods:
- evidence of suitability
- a Verification Method
- Expert Judgement
- comparison with the Deemed-to-Satisfy Provisions
The ABCB's guide to the process says Performance Solutions are commonly used for innovative designs, unique buildings or situations where no DTS Provision exists.
How is a performance solution developed?
Clause A2G2(4) sets 4 steps, and the ABCB's guide walks through them.
- Agree how compliance will be shown. A performance-based design brief (PBDB) is prepared with the relevant stakeholders. It sets the scope, the Performance Requirements, the acceptance criteria and the Assessment Methods.
- Analyse the proposal using the methods agreed in the brief.
- Evaluate the results against the acceptance criteria. If they fall short, the design is revised and assessed again.
- Write the final report. It records the Performance Requirements addressed, the Assessment Methods used, the outcomes, and any assumptions, conditions or limitations.
Step 4 is the document that reaches the builder. On fire safety it's the fire engineering report, covered in what is a fire engineering report.
How do the 2 compare?
| Deemed-to-Satisfy Solution | Performance Solution | |
|---|---|---|
| What it is | The design follows the provisions in the code | A design-specific answer to the Performance Requirements |
| NCC clause | A2G3 | A2G2 |
| How it's shown | Evidence of suitability or Expert Judgement | One or more of the 4 Assessment Methods |
| Process | Check the design against the clause | PBDB, analysis, evaluation, final report |
| What the builder gets | Drawings that match the code | Drawings plus a report with conditions and limitations |
Can a building use both?
Yes, and most larger ones do.
Clause A2G4 allows a combination. Where a Performance Solution sits beside DTS Solutions, the relevant DTS Provisions have to be identified, along with the Performance Requirements they relate to and any Performance Requirements in other sections or parts that the solution affects.
That last part matters on site. A change made for fire can reach into access or energy, and the report should say which requirements it touched.
What changes for the builder?
3 things.
The drawings won't match the DTS number. Say an 84-apartment job has a fire engineer's Performance Solution for a longer path of travel to an exit. Anyone checking that floor plate against the DTS clause will flag it. The finding is real, and the answer is in the report. Triage it against the report before anyone raises an RFI.
The conditions become scope. The final report lists the conditions and limitations the solution depends on. Each one has to appear on a drawing, a schedule or in the specification, or nobody prices it and it gets built at your cost. We wrote up the check for fire engineering reports.
A site change can undo it. A Performance Solution was assessed for one design. If a product is substituted or a wall moves, the item goes back to the person who wrote the report.
On design and construct, check what your contract says about who carries the design obligations. The contract and your lawyer decide that.
Where CIM Build fits
Report compliance reads each consultant report against the drawing set and the specification and returns each finding cited to the clause and the sheet. So the conditions in a Performance Solution report get checked against what was drawn.
BCA assessment reads the architectural set against the provisions for the building's class and construction type, with the clause, the sheet and the revision behind every finding. How an AI check treats Performance Solutions is covered in can AI assess performance solutions.
Book a briefing and bring the set and its reports.
Frequently asked questions
Is a performance solution a lower standard than deemed-to-satisfy? It has to meet the same Performance Requirements, or be shown to be at least equivalent to the DTS Provisions. The path to proving it is longer - a design brief, analysis, evaluation and a final report.
Who approves a performance solution? The NCC glossary calls it the appropriate authority - the relevant authority with the statutory responsibility to determine the matter. The ABCB's roles and responsibilities page has certifiers and building surveyors reviewing plans and confirming whether work meets the regulatory requirements. The ABCB itself doesn't assess individual designs.
Does a deemed-to-satisfy design still need evidence? Yes. Clause A2G3 says a DTS Solution is shown through evidence of suitability or Expert Judgement, and Part A5 sets out the forms that evidence can take.
How do I know which items on my job are performance solutions? Ask for the performance solution reports and the BCA report, which normally lists the departures from the DTS Provisions. More in what is a BCA report.