What are provisional quantities and when should a builder use them?
A provisional quantity is an estimated quantity for work that can be described but can't be measured yet. How it differs from a provisional sum, when to use one, and how it commonly gets adjusted.
TL;DR: A provisional quantity is an estimated quantity for work that can be described and rated but can't be measured accurately at tender. It commonly gets remeasured once the work is done and paid at the tendered rate, though the contract decides how. A builder should use one where the type of work is known and the extent isn't, such as rock in excavation or fire stopping around services that aren't coordinated yet. Where the work itself can't be described, a provisional sum is the usual tool.
The geotech report has 4 boreholes across a basement the size of a football field. 2 of them hit rock at 3 metres.
Nobody knows how much rock is between them. The excavator can give you a rate per m³ for rock tomorrow. What nobody can give you is the m³.
That's a made-up job, and it's the textbook case for a provisional quantity.
What is a provisional quantity?
It's a line in a bill of quantities with a description, a unit, a rate and a quantity that everyone knows is an estimate.
The RICS rules of measurement, NRM 2, define a provisional quantity as one that can't be accurately determined, so the figure in the bill is an estimate. That's a UK document, but the idea is used the same way on Australian bills.
The line is marked provisional so nobody treats the quantity as measured.
How is a provisional quantity different from a provisional sum?
A provisional quantity fixes the rate and leaves the quantity open. A provisional sum is a dollar allowance for work that isn't defined well enough to rate at all.
| Provisional quantity | Provisional sum | |
|---|---|---|
| What's known | The type of work | That some work is needed |
| What's unknown | How much of it | The detail, and often the extent |
| What's in the bill | Description, unit, estimated quantity, rate | Description and a dollar figure |
| Commonly adjusted by | Remeasuring and applying the rate | Replacing the sum with the actual cost, as the contract sets out |
Say rock excavation is carried at 400 m³ provisional. If the site turns up 520 m³, the adjustment is arithmetic.
Say a provisional sum of $60,000 for "external lighting, design to be confirmed". It has no rate inside it, so the adjustment depends on what the contract says about valuing it. We cover that side in provisional sum vs prime cost.
When should a builder use a provisional quantity?
When you can write the description and get a rate, and the quantity depends on something nobody can see yet.
Typical cases on a multi-residential new build:
- Rock, soft spots or contaminated spoil in excavation.
- Pile lengths before the founding level is proven.
- Fire stopping to penetrations before the services are coordinated.
- Extra reinforcement or concrete where the structural design is still moving.
- Make-good and remedial work at the interface with an existing structure.
It's the wrong tool when the work is fully drawn and somebody ran out of time to measure it. And if you can't describe the work at all, that's a provisional sum or an RFI.
How does a provisional quantity get adjusted?
Commonly the work is remeasured once it's complete and the tendered rate is applied to the actual quantity. The detail sits in the contract, and contracts differ.
Check these before you rely on one.
- Is the bill part of the contract? Some contracts include a bill of quantities and adjust for the actual quantities. Many lump sum contracts leave quantities at the builder's risk whatever the bill says.
- Which clause does the adjusting? AS 4000-1997, for example, has clauses on the bill of quantities and on adjustment for actual quantities. Standards Australia published AS 4000:2025 in June 2025, so check which edition yours is and whether it's been amended.
- Is there a limit? Some contracts set limits of accuracy, and a quantity outside them can open the rate up for review.
- Who measures, and when? Agree how the actual quantity gets recorded before the rock is carted away.
That's how it commonly works. It's general information, and your contract and your lawyer decide what applies on your job.
How do I set the number?
Make the estimate honestly and show how you got there.
Write the basis on the line - "400 m³ provisional, based on boreholes BH2 and BH4, geotech report section 5". Then anyone reviewing the tender can see what the allowance assumes, and the remeasure has a starting point.
Don't lowball it to sharpen the tender total, because everyone downstream plans around that number. And get a real rate. The rate is the part that carries through to the final account.
Should provisional quantities go in subcontract packages too?
Yes, where the same uncertainty passes down. If your contract with the principal carries rock as a provisional quantity, the excavation subcontract should carry it the same way, with the same unit and the same measurement rule.
The risk is a mismatch. If you're paid on remeasure upstream and you've let the package as a fixed lump sum downstream, or the other way round, the difference lands with you.
Keep provisional lines visible when you level the quotes as well. A subcontractor who priced 200 m³ of rock looks cheaper than one who priced 400. More in how to level subcontractor quotes.
Where does CIM Build fit?
CIM Build reads the drawings and specification into a scope of works for each trade, and measures against it to build a bill of quantities with the unit, the quantity and the source sheet or clause on every line.
A scope item with no quantity stands out, so the estimator can see what was measured and decide which of the rest is carried as provisional. The decision and the contract terms stay with your team.
Book a briefing and bring the tender.
Frequently asked questions
What is a provisional quantity in a bill of quantities? It's an estimated quantity for work that can be described and rated but can't be measured accurately at tender. It's marked provisional in the bill and is commonly remeasured when the work is complete.
Is a provisional quantity the same as a provisional sum? No. A provisional quantity has a description, a unit and a rate, with only the quantity uncertain. A provisional sum is a dollar allowance for work that isn't defined well enough to rate.
Who carries the risk on a provisional quantity? Commonly the tenderer is held to the rate and the quantity is adjusted to what's actually built, but that depends on the contract. On many lump sum contracts quantities are at the builder's risk unless the contract says otherwise. Read the clause and get legal advice where it matters.