How do I check an existing bill of quantities for scope gaps against the drawings?

4 passes for a bill of quantities somebody else measured: the revision it came from, every scope item ticked against a bill line, every bill line traced back to a sheet or clause, and a re-measure of the lines that carry the most money.

TL;DR: Check an existing bill of quantities in 4 passes: confirm the drawing revision it was measured from, tick every scope item in the drawings and specification against a bill line, trace every bill line back to a sheet or clause, and re-measure the few lines that carry the most money. A scope item with no line is a gap. A line with no source is a question for whoever wrote the bill.

Say the tender for an 84-apartment job lands with a bill of quantities already in it. 1,400 lines, measured by the client's quantity surveyor, and a note on the cover that says it was prepared from the DA set.

The tender drawings are 2 revisions on from the DA set.

That's a made-up example, but it's the usual position. Somebody else measured the bill, at a different time, from different drawings, and you're about to put your rates on it. The bill can be right on every line it has and still be short, because it only holds what the measurer saw.

Which drawings was the bill measured from?

Start here. It takes 20 minutes and it tells you how much to trust everything else.

Look for a drawing list in the bill's preambles or cover sheet. Compare it to the current drawing register, sheet by sheet and revision by revision. You're looking for 3 things:

If the bill doesn't say what it was measured from, ask. If nobody can tell you, treat it as a guide and plan to measure the big trades yourself.

For the sheets that have moved on, compare the revisions and list what changed. Each change is either already in the bill, or it's your first scope gap.

How do I find scope that's in the drawings but missing from the bill?

This is the pass that finds money, and it runs from the documents to the bill. Never the other way first.

Take one trade at a time. Read the drawings, the specification section and the schedules for that trade, and write down each thing the trade has to supply or do. That list is the trade's scope of works. Then go down the list and find the bill line for each item.

Tick the ones that have a line. What's left is one of 4 things:

Decide which, item by item, and write it down.

The places I'd look first are the ones that sit between trades and the ones that live in notes. Wet area screeds and falls. Fire stopping at penetrations. Acoustic sealant and insulation called up in the acoustic report and nowhere on the wall types. Lintels, cavity flashings, movement joints. Temporary works. Anything that appears once in a specification clause and never on a drawing.

A bill measured off the architectural set won't carry a requirement that only the fire engineering report or the geotech report mentions.

How do I find bill lines with nothing behind them?

Now run it the other way. Take each bill line and find the sheet or clause it came from.

Most lines will trace in seconds. The ones that don't are worth a look:

Check the measurement rules while you're there. If the preambles say the bill follows a standard method such as the Australian and New Zealand Standard Method of Measurement, that tells you what each line is meant to include. If they don't say, you can't assume waste, laps or fixings are in or out, so ask.

Which quantities should I re-measure?

You won't re-measure 1,400 lines in a tender period, so don't try.

Sort the bill by what each line is likely to cost and take the top 10 or so. For most apartment jobs that's concrete, reinforcement, formwork, facade, partitions, ceilings, floor finishes and waterproofing.

Measure each of those yourself on one typical level and multiply out. If your number sits close to the bill's, move on. If it doesn't, find out why before you price anything else in that trade. The checks in how to check a quantity takeoff apply the same way to a bill someone else wrote.

What do I do with the gaps I find?

Each gap goes one of 3 ways during the tender: raise an RFI and get the bill corrected by addendum, price it and say so, or qualify it in your submission.

Which one is right depends on who carries the quantity risk. Some contracts make the bill a contract document and set out how errors in it are adjusted. Others issue the bill for information only and leave the quantities with the builder. The conditions of tendering and the contract decide that, and it's worth a lawyer's hour if the wording is unclear.

Either way, keep the list. If a gap you raised at tender turns up on site 14 months later, the list with the sheet reference and the date is what supports the variation.

Where CIM Build fits

CIM Build reads the drawings and the specification into a scope of works for each trade, with the sheet and clause behind every line.

It then measures the quantities against that scope to build its own bill of quantities per trade, with the unit, the quantity and the source on every line, and exports it to Excel. Put that beside the bill you were given and the scope items with no matching line stand out.

Book a briefing and bring the tender and the bill.

Frequently asked questions

How long does it take to reconcile a bill of quantities against the drawings by hand? It depends on the size of the set and how many trades you check. The revision check is quick. The scope pass is the slow one, because it means reading the drawings and specification once per trade, so most teams only do it properly on the trades that carry the most cost.

Is the builder responsible for errors in a bill of quantities the client supplied? It depends on the contract. Some forms treat the bill as a contract document and adjust for errors, and others say the bill is for information and the builder prices the drawings and specification. Read the conditions of tendering and the contract, and get legal advice before you rely on either position.