What is a BCA report (BCA compliance assessment), and who prepares it?

A BCA report is a consultant's written assessment of a design against the Building Code of Australia, Volumes One and Two of the NCC. Here's what it contains, who usually writes it, how it differs from an approval, and what a builder should take from it.

TL;DR: A BCA report is a consultant's written assessment of a building design against the Building Code of Australia (BCA), which is Volumes One and Two of the National Construction Code (NCC). It records the building's classification and lists where the design follows the Deemed-to-Satisfy Provisions, where it departs from them, and where a Performance Solution is proposed. It's usually prepared by a BCA consultant or building surveyor engaged by the developer, the design team or the builder. The approval itself is a separate decision made by the certifier or building surveyor for the job.

The tender pack has a BCA report in the consultant folder, dated 8 months before the drawings.

Section 5 is a table of items marked "to be addressed at detailed design". On a design and construct job, that table can be a list of design work you've just agreed to finish.

What is the BCA?

The ABCB states that the NCC includes the Building Code of Australia, which comprises NCC Volume One and NCC Volume Two. Volume Three is the Plumbing Code of Australia.

So the BCA is the building half of the NCC, and "BCA report" and "NCC report" get used for the same document. Which volume covers which building is in NCC volumes explained.

What is a BCA report?

It's a read of the design against the code, written down.

"BCA report" is an industry term. The NCC doesn't define it or set a format, so the content varies by consultant and by stage. A typical one for a Volume One building covers:

The classification comes first because everything else hangs off it. Part A6 classes buildings by use, and one building can hold several classes. Say an 84-apartment job with shops at ground and basement parking - that's Class 2, Class 6 and Class 7a, each read against its own provisions.

Why does it list departures?

Because the NCC allows them, as long as they're dealt with properly.

Clause A2G1 of Part A2 lets a design meet the Performance Requirements with a Performance Solution, a Deemed-to-Satisfy Solution or a combination. A departure from a DTS clause is either designed out or carried as a Performance Solution, with its own process and final report.

So the BCA report is the map. It tells you which items are plain DTS and which ones have another report behind them - a fire engineering report for the fire departures, for example. We cover the 2 paths in deemed-to-satisfy vs performance solution and the fire document in what is a fire engineering report.

Who prepares a BCA report?

Usually a BCA consultant or a building surveyor, engaged by whoever needs the answer at that stage. That's the developer or architect during design, and often the builder at tender or during design development.

The report is advice, and the approval is a separate step.

The ABCB's roles and responsibilities page has certifiers reviewing plans and inspecting work to confirm whether it meets the regulatory requirements, and building surveyors reviewing applications before construction. It puts designing and constructing to the NCC on builders and designers.

The rules on who can do which job are set by each state. In NSW, the government describes a certifier as an independent regulator of building work and a public official who must act in the public interest and manage conflicts of interest. So whether the person advising on the design can also certify it is a question for the state's legislation and the regulator.

When is a BCA report prepared?

There's no single point. They commonly turn up at 3 stages:

  1. Early design, to find the big departures while the layout can still move.
  2. Tender, where the builder receives the developer's report or commissions its own.
  3. Before approval, to support the application to the certifier or building surveyor.

Each one is a snapshot of a drawing revision.

What should a builder take from a BCA report?

5 checks before the price goes in.

  1. The edition and the state. NCC 2025 was published on 1 May 2026 and the states adopt it on different dates. Confirm the report's edition is the one the approval will be assessed under.
  2. The drawing revisions. If the set you're pricing is later than the set the report read, the report's conclusions cover an earlier design.
  3. The open departures. Each one is either a design change or a Performance Solution somebody has to commission, coordinate and build. Find out which, and who pays.
  4. The "to be confirmed" items. Each is design work with no answer yet. On design and construct, the contract decides whether closing it is yours, so read the design obligations and get advice.
  5. The report against the drawings. A clause the report says is satisfied should be visible on a sheet. Where it isn't, raise an RFI while the consultant can still fix it for free.

Where CIM Build fits

BCA assessment reads the architectural set against the provisions that apply to the building's class and construction type, and cites the clause, the sheet and the revision behind every finding. The assessment re-runs on each issue, so a report that's 2 revisions old isn't the only read you have.

Report compliance reads each consultant report against the drawing set and the specification and returns each finding cited to the clause and the sheet.

The certifier or building surveyor still makes the decision. What an AI check can be relied on for is in can AI check drawings against the NCC.

Book a briefing and bring the BCA report and the set.

Frequently asked questions

Is a BCA report the same as a building approval? They're separate. A BCA report is a consultant's assessment of the design. The approval is a statutory decision made by the certifier or building surveyor under the state's building legislation.

Does a BCA report cover plumbing? The BCA is Volumes One and Two. Plumbing and drainage sit in Volume Three, the Plumbing Code of Australia, so check the report's scope before assuming hydraulics were assessed.

Does a BCA report need updating when the drawings change? It assessed a named set of drawings. When the layout, the classification or a fire or egress element changes, the affected sections need another read against the new revision.

Can a builder commission its own BCA report? Yes, and builders often do at tender or during design development on design and construct, so they know the departures before they carry the design.