What does a design manager do on a design and construct project?

On design and construct the builder owns the design, and the design manager is the person who runs it. What the role covers from tender to practical completion, which documents the design gets checked against, and where the money goes when a check is skipped.

TL;DR: On a design and construct (D&C) project the builder takes on the design as well as the build, and the design manager runs that design for the builder. They manage the consultants, check every design issue against the Principal Project Requirements (PPR), the consultant reports and the NCC, and get drawings issued in time for procurement and site. They also keep the design inside what was priced at tender, and record every change that adds scope so it can be claimed.

What is design management in construction?

Say you've won an 84-apartment job on a D&C contract. The tender drawings are 60% complete, the architect and engineers are about to be novated to you, and the first slab pour is 5 months away.

Somebody has to get that design finished, coordinated, compliant and issued for construction before the pour. That's design management.

On a construct-only job the principal's team finishes the design and the builder builds what's drawn. On D&C the builder commonly carries responsibility for completing the design so it meets the principal's brief. AS 4902-2000 is the Standards Australia general conditions of contract written for design and construct, and plenty of D&C jobs run on an amended version of it or on a bespoke contract. How much design risk you carry depends on your contract, so read it and get legal advice on anything unclear. More in design and construct contracts explained.

What does a design manager do week to week?

Most of the week goes on 7 jobs.

  1. Run the design schedule. Each package has a date it must be issued for construction, set by when the trade needs to be let and when site needs the drawings. The design manager works back from those dates and chases the consultants to them.
  2. Chair the design meetings. Architect, structure, services, facade, fire, acoustic. The meeting decides who's drawing what and by when, and the minutes record it.
  3. Review every design issue. When a new revision lands, check it against the PPR, the reports, the code and the last revision before it goes any further.
  4. Coordinate between disciplines. A beam through a corridor ceiling full of services is cheaper to fix on paper. Here's how to check structural drawings against architectural.
  5. Raise and close RFIs. 1 question per RFI, with the sheet, revision and clause cited. Our guide on how to write an RFI covers the wording.
  6. Keep the registers. The drawing register, the RFI register, the design change register and the consultant deliverables list.
  7. Control change. Every change gets sorted into 3 piles - design development the builder already owns, a change the principal asked for, or a consultant error. The pile decides who pays.

How does the role change from tender to delivery?

At tender or early contractor involvement, the design manager reads the set for the estimators. What's missing, what's still to be designed, and what the PPR asks for that the drawings don't show. Those answers become allowances, RFIs or tender qualifications.

After award, the job is design development. The consultants take the tender design to issued-for-construction (IFC) drawings, and the design manager makes sure what comes out still matches what was priced. Here's the difference between tender drawings and IFC drawings.

During construction, the work moves to shop drawings, site RFIs, samples and late revisions. Revisions keep landing right up to practical completion, and each one needs the same check as the first.

Which documents does the design get checked against?

Look at 5.

What does it cost when a check gets skipped?

It costs margin, in 4 common ways.

A PPR requirement the drawings missed gets built wrong, and the correction is at the builder's cost because the brief was in the contract all along.

Design that runs past the brief gets built too. Say the PPR asks for 2.4 m ceilings in bedrooms and the architect draws 2.7 m. Nobody priced the extra wall lining, and nobody asked the principal to pay for it.

A package issued for construction 3 weeks late pushes the trade letting, and the schedule wears it.

And a change the principal asked for goes into a revision with no cloud. If nobody finds it, the variation is never raised and the builder builds the extra scope for free.

What tools do design managers use?

Mostly a document platform for the drawings and transmittals, a PDF markup tool, and spreadsheets for the registers. The reading is what runs short of hours.

CIM Build does that reading. PPR vs the drawings runs each clause of the brief against the drawings and the specification, and report compliance reads every consultant report against the set, with the clause and the sheet cited on each finding. Revision tracking brings matched drawing pairs, comparison status and detected findings into one review workflow. The design manager checks each finding against its source and decides what to do with it.

There's a longer list in AI tools for design managers. Book a briefing and bring the current set.

Frequently asked questions

Is a design manager the same as the architect? No. The architect produces the design. The design manager works for the builder and manages the architect and the other consultants so the design is complete, coordinated, on time and inside the price.

Does a construct-only job need a design manager? Usually a smaller version of the role. The builder still has to review revisions, coordinate shop drawings and raise RFIs, and on many construct-only jobs a project engineer or contract administrator does that work.

Who does the design manager report to? On most builders' teams the design manager reports to the project manager or construction manager during delivery, and works alongside the estimators at tender.

What's the difference between design development and a variation? Design development is the detail needed to finish a design the builder already agreed to deliver, and it's commonly at the builder's cost on D&C. A variation is a change to what the contract requires. Where the line sits depends on the contract wording, so check the contract and get legal advice before relying on either label.