How does a bill of quantities make subcontractor quotes comparable?

A bill of quantities gives every subcontractor the same items, units and quantities to price. The gap between 2 quotes then comes down to rates, exclusions and qualifications, and you can see which.

TL;DR: A bill of quantities gives every subcontractor the same list of items, the same units and the same measured quantities to price. Without one, each subcontractor measures the job their own way and the quotes are built on different amounts of work. With one, the gap between 2 quotes comes down to rates, exclusions and qualifications, and you can see which line it sits on.

3 partition quotes come back on an 84-apartment job. $1.92m, $2.24m and $2.41m.

The lowest is $490,000 under the highest. The estimator has 2 days to work out whether that's a sharp price or a missing floor.

That's a made-up example, and so are the numbers below. But every estimator has had that week.

Why are quotes hard to compare without a bill?

Because each subcontractor has priced a different job.

Ring the 3 of them and ask what area they measured, and you might hear this.

SubcontractorQuoteArea they measuredWorks out at
A$1.92m11,800 m²$163 per m²
B$2.24m13,400 m²$167 per m²
C$2.41m13,900 m²$173 per m²

The rates are within $10 of each other. Most of the $490,000 is quantity.

Subcontractor A left out the shaft walls, or measured to the ceiling where the wall type runs to the slab, or missed a level. You can't tell from a lump sum. And if you let the package to A, the missing area turns up on site as a claim, or as a subcontractor in trouble halfway through the job.

What changes when every subcontractor prices the same bill?

The quantity stops being a variable.

Say your bill has 13,650 m² of partitions split across 6 wall types. Every subcontractor puts a rate against the same 6 lines. Now a difference between 2 quotes is 1 of 3 things:

All 3 can be dealt with in a phone call. A difference in measured area can't, because neither of you knows who's right until somebody measures it again.

What does the bill need for this to work?

A bill only makes quotes comparable if every subcontractor reads each line the same way.

  1. Descriptions that can be priced without opening the drawings. "W3 acoustic partition, 92 mm stud, 2 layers of 13 mm board each side, to underside of slab" works. "Partition type 3" sends 3 subcontractors to 3 different assumptions.
  2. 1 unit per kind of work. Partitions in m² on every level.
  3. The sheet or clause behind each line, so a query can be settled in a minute.
  4. An instruction to price every line, and to list separately anything they think the bill has missed.
  5. A request to flag any quantity they disagree with, and by how much.

Point 4 gets you a free scope check from the people who build the work. Point 5 gets you a free check on your measure.

How to prepare a bill of quantities covers the measuring and the descriptions step by step.

What does a bill of quantities miss?

A bill makes the measured work comparable. It does less for everything around it.

Scope with no quantity is the first gap. If the specification calls for fire stopping at every penetration and the bill has no line for it, 3 subcontractors will each make their own call. Finding scope items with no quantity is a check to run before the bill goes out.

The covering letter is the second. Exclusions, access assumptions, working hours, who supplies the scaffold and how long the price holds all sit outside the bill, and they still have to be read and lined up. That's tender levelling, and a bill makes it shorter.

And some subcontractors will send a lump sum anyway. Levelling lump-sum quotes that aren't itemised covers what to do with those.

What if a subcontractor disputes a quantity?

Good. It means they measured.

Ask for their number and their markup, open yours, and find the difference. It's usually 1 area - a level, a wall type, a height. Fix the bill if they're right and tell the other tenderers, so everyone is still pricing the same thing.

Who pays if a quantity is still wrong after the package is let depends on the subcontract. A bill issued for guidance and a bill listed as a contract document are treated differently, so read the clause in your own form and ask a lawyer if you're unsure.

Where CIM Build fits

CIM Build reads the drawings and the specification into a scope of works for each trade, then measures the quantities against it to build that trade's bill of quantities. Every line carries its unit, its quantity and the sheet or clause it came from, and it exports to Excel to go out with the trade package.

When the quotes come back, CIM Build levels them. It reads every quote against the trade scope, lines them up item by item, and shows where 1 quote has allowed for work the others left out. The estimator decides how each gap is carried.

Book a briefing and bring a trade package and the quotes that came back.

Frequently asked questions

Do subcontractors have to price the builder's bill? You can make it a condition of tendering, and most will if the bill is clear and comes with the drawings. Some will still send a lump sum. Ask them to break it down against the bill lines before you compare it with the others.

Should the bill show the builder's rates? No. Send it with the quantities filled in and the rate column blank. Your own rates are your estimate, and showing them tells every subcontractor what you expect to pay.

Does a bill of quantities replace reading the quotes? No. The bill lines up the measured work. Exclusions, qualifications and assumptions sit in the covering letter. Read every letter against the scope.

Can the bill rates be used for variations later? Often, yes. A priced bill gives you an agreed rate for each kind of work, which is the obvious starting point when a revision adds scope. Whether the subcontract makes those rates binding for variations is a question for the contract.