How do I level lump-sum subcontractor quotes that aren't itemised?

A one-page lump sum gives you a total and a list of exclusions. Level it by building your own scope register and quantities, sending every subcontractor the same return schedule, and comparing each total against the scope it confirms.

TL;DR: You can't level a lump sum line by line, so level it against your own scope. Write the trade scope and measure the quantities yourself, send every subcontractor the same return schedule and ask them to confirm each scope item as included, excluded or qualified, then adjust each total for what it leaves out. Use your own quantities to sanity-check the totals, and get a breakdown from the preferred subcontractor before the package is let.

Why is a lump-sum quote hard to level?

3 plasterboard quotes land on the estimator's desk the day before the tender closes. Each is a single page - a total, "as per drawings", and 6 exclusions in small type.

There's nothing to line up. One subcontractor may have measured every wall type, another may have priced from the floor area and a rate they keep in their head. The totals look comparable and the scope behind them is anyone's guess.

So the levelling has to come from your side of the table.

For the itemised case, with rates and a worked example, see how to level subcontractor quotes. This article covers the quote with no breakdown.

What do I build before I open the quotes?

2 things - a scope register and your own quantities.

The scope register lists what the trade must deliver, one line per item, with the sheet or spec clause behind it. For plasterboard on an apartment job that's wall types, ceilings, bulkheads, shaft walls, fire and acoustic sealing, access panels, setting level, and attendance items like scaffold and waste.

Then measure the main quantities yourself. You're after the 5 or 6 lines that carry the money, so wall area by type and ceiling area will do. A trade bill of quantities is the tidy version of this.

Now you have something to hold each lump sum against.

How do I get a lump sum onto the same basis as the others?

Send a return schedule. Same one to every subcontractor, same day.

It's your scope register with 2 extra columns - "included, excluded or qualified" and "comment". Add 4 questions at the bottom:

  1. Which drawing revisions and addenda is the price based on?
  2. What quantities did you allow for the main items?
  3. What's your price split across these 5 headings?
  4. What's excluded that isn't on this list?

If the tender is closing and nothing comes back, mark every unanswered line as silent and carry your own allowance against it. Keep silent separate from excluded. One is a position, the other is a question nobody answered.

How do I compare the totals once the schedules are back?

Adjust each total for what it leaves out, and keep the original offer visible beside the adjusted figure.

Here's a made-up example on an 84-apartment job. All figures are invented for illustration and exclude GST.

Sub ASub BSub C
Lump sum as quoted$1,920,000$2,050,000$2,180,000
Shaft wallsExcluded, +$85,000 allowanceIncludedIncluded
Fire and acoustic sealingSilent, +$40,000 allowanceExcluded, +$40,000 allowanceIncluded
Scaffold above 3 mExcluded, +$30,000 allowanceIncludedIncluded
Priced to addendum 2No, clarifyYesYes
Comparison total$2,075,000$2,090,000$2,180,000

Sub A looked $130,000 under Sub B on the cover page. On the same scope the gap is $15,000, and A still hasn't priced the addendum.

The allowances are yours. They make the comparison fair, and they don't put the work into anyone's subcontract. That happens when the subcontractor confirms it in writing.

Can I use my own quantities to test a lump sum?

Yes, as a sanity check.

Divide each comparison total by your measured quantity for the main item. In the example, say you measured 38,000 m2 of wall and ceiling lining. That gives about $55 per m2 for A and B and about $57 for C.

If one quote came out at $38, you'd ask what's missing before you'd celebrate. Usually it's a wall type, a level, or a whole building stage.

Keep the implied rate inside your own working. The subcontractor never offered it, so it can't be used to price a variation or a remeasure later. If you want rates you can rely on, ask for a schedule of rates as part of the offer. The difference is covered in bill of quantities vs schedule of rates.

What should I lock in before the package is let?

Get the breakdown from the subcontractor you intend to award to.

How those documents sit in the subcontract, and which one governs if they disagree, is a matter for the subcontract terms and your lawyer.

Where does CIM Build fit?

CIM Build's tender levelling reads each subcontractor quote against the trade scope from the drawings and specification. Inclusions, exclusions and qualifications are matched to the scope register, with the sheet and clause on every line, and the allowances one quote carries and the others leave out are flagged. The comparison exports to Excel, and CIM Build drafts the clarifications for each subcontractor. The estimator decides how each gap is carried.

The register itself comes from scope of works, and the quantities from the bill of quantities built against that scope.

Book a briefing and bring a trade package with the quotes that came back.

Frequently asked questions

Can I level a lump-sum quote without asking for a breakdown? You can get to a comparison, with more risk left in it. Map the quote's stated inclusions and exclusions to your scope register, treat everything it doesn't mention as silent, and carry an allowance for each silent item. Ask for the breakdown before award regardless.

Should I divide a lump sum by my quantities to get a rate? Only as a check on your side. An implied rate helps you spot a quote that's missing scope, and it tells you which subcontractor to question first. It was never offered by the subcontractor, so keep it out of the subcontract and out of any variation pricing.

What if a subcontractor refuses to itemise their price? Ask for the smallest thing that still works - a yes or no against each scope line and the drawing revisions they priced. If they won't give that either, weigh the unanswered scope as risk when you compare, and record why.