How do I reduce RFIs during a tender?

You cut tender RFIs by checking the documents before you ask, grouping questions by issue, sending them early and deciding which findings are better carried as a qualification or an allowance. The method in 6 steps.

TL;DR: You reduce tender RFIs by asking fewer questions that didn't need asking. Check the full set and the addenda before you raise anything, group findings by issue, send the questions that change the price in week 1, and carry the rest as a tender qualification or an allowance. The aim is a short list of RFIs that each get a clear answer before the cut-off.

Why do tenders generate so many RFIs?

It's week 3 of a 4-week tender. The RFI cut-off is Friday, and the team has 60 questions in a spreadsheet.

Most tenders get there the same way. The documents are incomplete, the reports and the drawings were written by different people at different times, and each estimator raises questions as they hit them.

So the list fills up with 4 kinds of RFI that didn't need to exist.

  1. Questions the documents already answer. The answer's in a spec section, a schedule or a report nobody had opened yet.
  2. Duplicates. 3 people ask about the same wall type on 3 different sheets.
  3. Questions the last addendum answered. Often in a response to another tenderer.
  4. Questions that won't change the price. They matter in delivery. They don't need an answer by Friday.

Take those out and what's left is the list worth sending.

How do I cut the RFIs that didn't need asking?

6 steps.

  1. Review the whole package first. Do the cross-check in week 1, before trade-by-trade measuring starts. Our tender document review checklist covers what to read in each document.
  2. Keep 1 findings list. Everyone on the tender logs to the same list, with the sheet, revision and clause on every row. Duplicates show up when 2 rows cite the same detail.
  3. Search before you ask. For each finding, check the spec section, the relevant schedule, the consultant report and the latest addendum. If the answer's there, note where and close the row.
  4. Group by issue. 14 bathrooms with the same missing setdown is 1 RFI listing 14 rooms. Keep it to 1 topic per RFI so the answer is clean.
  5. Rank by price. Mark each finding with what it does to the number. The ones that move the price or the schedule go first.
  6. Re-check after every addendum. New documents answer old questions and raise new ones. Close what's been answered before the next batch goes out.

Should every finding become an RFI?

No. An RFI is 1 of 4 ways to deal with a finding at tender.

There's a commercial side to the choice too. On many tenders the responses to RFIs are issued to every tenderer, so a question can hand your finding to the competition. Check the conditions of tendering for how questions and answers are handled on your job. Some builders ask about the gaps everyone needs closed and qualify the ones that are specific to their method or price.

And check the clock. A question raised 2 days before the cut-off often comes back as "price as documented". That one was always going to be a qualification.

How do I write the RFIs I do send?

Write each one so it can be answered in a single pass.

Say, as an example, you're pricing a 6-storey job with 84 apartments. "Please clarify wall types" will come back with a question. "Wall type W3 on A-201 Rev B is tagged between apartments 3.04 and 3.05, and the acoustic report clause 5.2 requires a higher rating than W3 achieves. Please confirm the wall type between apartments" gets an answer you can price.

The full method, with a worked example, is in how to write an RFI.

What happens to the questions I don't send?

They stay on the list. That's the point of keeping one.

A finding you qualified at tender becomes a negotiation point at award. A finding you priced becomes a line in the trade's scope of works. A finding you parked because it didn't move the price becomes the design manager's first job after award.

Lose the list and the delivery team finds the same 60 issues again, on site, after the trades are let. The ones that add scope are harder to claim by then, because nobody can show what the tender was priced on.

More on carrying tender knowledge across in tender to contract.

Can software reduce tender RFIs?

It can do the search-before-you-ask step, which is where most of the hours go.

CIM Build's report compliance reads every consultant report against the drawing set and the specification, and PPR vs the drawings runs each clause of the brief against the drawings and the spec. Each finding cites the clause and the sheet, so the estimator can open the source, confirm it and decide whether it's an RFI, a qualification or a priced item. The team triages findings as reviewed, needs action or future RFI.

AI-suggested RFIs drafts the RFI from the finding, and a person reviews every draft before anything is sent. It's in beta with a small group of builders.

Book a briefing and bring the tender.

Frequently asked questions

Is a high number of tender RFIs a bad sign? It usually says the documents are incomplete, and that's worth pricing for. It can also mean the team is asking before reading. Check how many of your own RFIs were answered with a reference to a document you already had.

When should tender RFIs be sent? As early as the review allows, and before the cut-off in the conditions of tendering. Questions that change the price go first, because a late question often gets no useful answer and ends up as a qualification anyway.

Do other tenderers see my RFIs? Often, yes. Many principals issue the responses to all tenderers so everyone prices the same information, usually without naming who asked. The conditions of tendering set the rule for your job, so read them before you send anything.

Should I raise an RFI or qualify the tender? Raise the RFI when the answer changes your price and there's time to get it. Qualify when there isn't, or when the issue is specific to how you've priced the job. Check the tender conditions first, because some tenders limit qualifications or treat a qualified tender as non-conforming.