How do I measure brickwork and blockwork for a takeoff?

Brickwork and blockwork are measured in m² of wall by type and thickness. How to get lengths and heights off the plans and sections, turn area into units, and pick up lintels, core fill, ties and joints.

TL;DR: Measure brickwork and blockwork in m² of wall face, one total per wall type and thickness. Length comes from the floor plans, height from the sections, and openings come off. Then measure the items a bricklayer prices separately - lintels, core filling and reinforcement, ties, damp-proof courses, control joints - because the m² alone won't cover them.

The blockwork quote is priced on 2,900 m². Your takeoff says 3,400.

The plans are the same. The difference is height. The bricklayer measured the stair and lift core walls to the ceiling line at 2.7 m, and they run slab to slab at 3.1 m, every level.

That's a synthetic example, and it's the most common way a masonry measure comes up short.

What units are brickwork and blockwork measured in?

Measure the wall net, as built. Cutting, waste and mortar go in the rate.

What do I read off which drawing?

The architect draws where the wall is. The engineer draws what's inside it. You need both for the same wall.

How do I measure the wall area?

Length x height, less openings, by wall type.

Trace each masonry wall on the plan along its centreline and total the length by type per level. Then go to the sections for the height of each type. Don't use one height for a whole level. A core wall, a corridor wall and a parapet on the same plan can have 3 different heights.

For openings, deduct doors and windows at their structural opening size. Small penetrations for services are usually left in. State what you did, and if the bill is measured to the ANZSMM, follow its rules.

A cavity wall is 2 skins. Measure each skin as its own line when they're different units, like face brick outside and block inside.

As an example, a core wall type runs 46 m on plan per level, 3.1 m slab to slab, with 6 door openings of 1.0 x 2.1 m. That's 46 x 3.1 = 142.6 m², less 12.6 m², so 130 m² per level and 780 m² over 6 levels.

How do I turn m² into bricks or blocks?

Work it out from the unit's face size plus one mortar joint each way.

A brick with a 230 x 76 mm face and 10 mm joints takes up 240 x 86 mm of wall, which is about 48.5 bricks per m². A block with a 390 x 190 mm face and 10 mm joints takes up 400 x 200 mm, which is 12.5 blocks per m².

Check the unit size and the joint in the specification first, because both vary by product. And keep this number out of the bill. The bill carries net m². The bricklayer adds waste and orders the units.

What gets missed in a masonry takeoff?

Any of these with no trade against it gets built at the builder's cost.

Once it's measured, check it the way you'd check any trade. Wall area divided by wall length should give a height you can find on a section. There's more in how to check a quantity takeoff, and the right unit for each trade is in takeoff units of measurement.

How does AI takeoff handle brickwork and blockwork?

Wall lengths by type is the base measure, and it's one of the quantities you can ask for directly.

With CIM Build's AI takeoff you ask in plain English for wall lengths by type. It calibrates the scale on each sheet against the dimensions printed on it, measures, and returns a table with a marked-up copy of the sheet, so you can see which walls were traced as which type.

CIM Build reads the drawings and the specification into a scope of works for the trade, then measures against it to build the bill of quantities. Each line carries its unit, quantity and the sheet or clause it came from. So core filling called up on a structural sheet has a scope line, and a scope line with no quantity stands out.

Book a briefing and bring the tender.

Frequently asked questions

Is brickwork measured in m² or by the thousand bricks? Measure it in m² of wall by type. Bricklayers often quote a rate per thousand laid, and you convert using the bricks per m² for that unit and joint. Keeping the bill in m² means the quantity can be checked against the drawings.

Do I deduct openings in masonry walls? Yes for doors and windows, at the structural opening size. Small service penetrations are usually left in. Write the rule in the bill so every bricklayer quotes the same area, and follow the ANZSMM where the bill is prepared to it.

Who prices the lintels? Whoever your scopes say. Lintels can be supplied by the steel fabricator and built in by the bricklayer, or supplied and built in by the bricklayer. Put the supply in one scope and the install in one scope, each with a quantity.