How do I measure floor finishes from the drawings and finishes schedule?

Floor finishes are measured in m² by finish code, with skirtings, trims and stair nosings in metres. How to read the finishes plan against the schedule, what sits under the finish, and the areas that get missed.

TL;DR: Measure floor finishes in m², one total per finish code. The code for each room comes from the finishes schedule or the finishes plan, the area comes from the floor plan, and skirtings, transition trims and stair nosings are measured in metres. Then measure what goes under the finish - screed, levelling, moisture barrier, acoustic underlay - because that's where flooring scope usually goes unpriced.

The carpet quote and the tiler's quote both look fine. Neither includes the acoustic underlay.

It's in the acoustic report, on page 14, as a requirement under hard flooring in every apartment. It isn't on the finishes schedule. So neither trade priced it, and on an 84-apartment job that's underlay to every living room and kitchen with nobody's money against it.

That's a made-up example. But the flooring takeoff is where you'd catch it.

What units are floor finishes measured in?

Measure net, as laid. Waste, offcuts and pattern matching go in the flooring contractor's rate.

What do I read off the finishes schedule and what off the plans?

The schedule tells you what the finish is. The plans tell you where it is and how much.

First check the schedule and the plans agree. Every room on the plan should have a floor code in the schedule, and every code in the schedule should have a definition. A room with no code is an RFI. Guessing it's the same as next door is how a store room ends up with carpet.

For tiles and vinyl in wet and public areas, read the slip rating too. Schedules normally give a classification tested to AS 4586, the standard for slip resistance classification of new pedestrian surfaces, and a tile that meets it can cost more than the one that doesn't.

How do I measure the areas?

Room by room, to the finished wall face, then total by code.

Measure the room's floor area and assign it to its code. Where 2 finishes meet in one room, split it at the line on the finishes plan.

Decide what happens under fixed joinery and state it. Kitchens are often tiled or laid wall to wall and wardrobes often aren't. The details or the specification should say. If they don't, ask.

Skirting is the room perimeter less door openings, and less any wall where joinery or full-height tiling sits against the floor.

As an example, take a 2-bed apartment of 78 m². Timber floor to living, kitchen and hall is 41 m², carpet to 2 bedrooms is 24 m², floor tiles to the bathroom, ensuite and laundry are 11 m², and 2 m² is under walls and ducts. The balcony is another 9 m² of external tile on a different line. That's 4 lines, 3 trades or more, and each one is multiplied by however many apartments share the layout.

What sits under the finish, and who has it?

This is the part to slow down on.

Give each one a line in m² under a named trade. Work that sits between 2 trades with no line gets settled on site, at the builder's cost.

Which areas get missed?

Then cross-check. Floor finishes area on a level should be close to the ceiling area for that level, and the total across all codes should be close to the level's internal area. There are more checks like that in how to check a quantity takeoff.

How does AI takeoff handle floor finishes?

Floor areas by finish is one of the quantities you can ask for directly.

With CIM Build's AI takeoff you upload the set and ask in plain English for floor areas by finish. It calibrates the scale on each sheet against the dimensions printed on it, measures, and returns a table with a marked-up copy of the sheet, so you can see which rooms went under which code.

CIM Build reads the drawings and the specification into a scope of works for each trade, then measures against it to build that trade's bill of quantities. Each line carries its unit, its quantity and the sheet or clause it came from, and a scope item with no quantity stands out.

Book a briefing and bring the tender.

Frequently asked questions

Do I add waste to floor finish quantities? No. Measure the net area as laid and let the flooring contractor price waste in the rate. They know the roll width, the tile size and the set-out. If you add waste and they add it again, you've paid for it twice.

Is skirting part of the flooring takeoff? Measure it with the floor, in metres, and put it under the trade that installs it. Tiled skirting goes with the tiler, vinyl coving with the vinyl layer, timber skirting usually with the carpenter and then the painter.

What if the finishes schedule and the finishes plan disagree? Raise an RFI while the tender is open, and price the one you've assumed with a qualification that says which. Which document takes precedence is set by the contract, so that's a question for the contract and your lawyer.


Published by CIM Build. This is the text of https://www.cim.build/au/blog/flooring-takeoff-guide without the site design. Index of all pages. Contact.