How do I measure waterproofing areas for wet areas and balconies?

Measure waterproofing in m² of membrane: the floor area plus the upturns at every wall, hob and threshold, plus shower walls. Count wastes and penetrations, measure junctions in m, and keep each membrane system on its own line.

TL;DR: Measure waterproofing in m² of membrane, by membrane system and location. Each room or balcony is its floor area, plus the upturn at every wall, hob and door threshold, plus the shower walls to the height shown on the detail. Junctions and angles are measured in m, and floor wastes and penetrations are counted.

The bathroom floor is 4.3 m². The membrane in that bathroom is 8.8 m².

The floor plan gives you the first number. The second one comes from the wet area detail - the upturn around the perimeter and the shower walls - and it's what the waterproofer prices.

Those are made-up numbers for one bathroom. Across 84 apartments, measuring floor area only leaves about half the membrane out.

What do I measure, and in what units?

Screeds laid to falls are usually a separate line, in m², and you need to decide which trade carries them.

Which documents set the extent?

The drawings and the specification tell you where the membrane goes on your job. Read these:

  1. The wet area details. Upturn heights, shower wall heights, hob and threshold details.
  2. The balcony and roof details. Upturn height at the door sill, the balustrade base and the slab edge.
  3. The finishes schedule and finishes plans, for which rooms are tiled wet areas. See what a finishes schedule is.
  4. The specification section for waterproofing, for the membrane type, the number of coats and the testing.
  5. The hydraulic drawings, for the number of floor wastes and penetrations.
  6. The structural drawings, for setdowns and hobs.

2 standards usually sit behind the specification.

For wet areas, NCC 2022 Volume One clause F2D2 says building elements in wet areas in Class 2 and 3 buildings and Class 4 parts must comply with AS 3740. Clause F2D4 on the same page sets the fall to a floor waste, where one is installed, at between 1:80 and 1:50.

For balconies, roofs and podiums, clause F1D5 requires a membrane of materials complying with AS 4654.1, designed and installed in accordance with AS 4654.2.

If the details show less than the standard asks for, raise an RFI before you price it.

How do I measure a bathroom?

Take the dimensions off the wet area detail for that bathroom type. The heights below are an example.

Say a bathroom is 2.4 m by 1.8 m.

Total 8.82 m² of membrane, against 4.32 m² of floor.

Then the items that aren't area. 1 floor waste, 1 shower waste, the penetrations for the toilet and basin, 8.4 m of bond breaker at the wall and floor junction, and a waterstop angle at the door.

Measure each bathroom type once, check it, and multiply by how many times the type appears. Count the types off the plans yourself, because a revision can change a unit type on one level only.

How do I measure a balcony?

Same method, different detail.

Floor area from the plan, to the outside edge of the slab or the inside face of the hob, whichever the detail shows. Then the upturns - at the door sill, up the wall, up the balustrade hob. Read each height off the detail, because they're often different on each side.

Count the balcony outlets and overflows from the hydraulic drawings.

Planter boxes are measured on the inside faces and the base.

What gets missed?

Any of these left out of the waterproofing package still gets built, at the builder's cost.

Cross-check against the tiling. Wet area floor tiling for a level should sit close to the wet area membrane floor area for that level. How to check a quantity takeoff before pricing has more of these.

How does AI takeoff handle waterproofing?

CIM Build's AI takeoff measures lengths, areas and counts off the PDF drawing set. You ask in plain English - floor areas by room or by finish, counts of fixtures or penetrations - and it calibrates each sheet's scale and returns a results table with a marked-up copy of the sheet.

The scope of works and the bill of quantities are built from the same drawings and specification, and each bill line sits under the scope item it measures. A scope item with no quantity stands out, which is how a missed laundry or planter box gets found.

The estimator still reads the detail for the upturn heights and signs off the bill.

Book a briefing and bring the tender.

Frequently asked questions

Is waterproofing measured in m² of floor or m² of membrane? Membrane. That means the floor, the upturns and any wall areas added together. If you send out floor areas only, say so, and give the upturn lengths and heights so the subcontractor can work out the rest.

How high does the membrane go up the wall? Read it off the wet area or balcony detail and the specification for your job. AS 3740 covers internal wet areas and AS 4654.2 covers external above-ground membranes, and the NCC calls up both. If the detail and the standard disagree, raise an RFI.

Who prices the screed to falls? It varies. It can sit with the tiler, the waterproofer or the concreter, and whether the membrane goes under or over the screed changes the answer. Name the trade in each scope of works so the screed is priced once.