← Back to blog
6 min read

How do I measure painting for a takeoff?

Painting is measured in m² by surface and paint system, with doors counted and trims in metres. What to read off the finishes schedule, the RCPs and the specification, and the surfaces that get left out.

TL;DR: Measure painting in m² of surface, split by paint system. Walls are perimeter x height less the openings you've decided to deduct, ceilings come off the reflected ceiling plans, doors and frames are counted, and skirtings, architraves and handrails are measured in metres. The paint system for each surface comes from the finishes schedule and the specification, and the split matters because a 2-coat wall and a 3-coat wet area ceiling carry different rates.

The painter's quote says "all painting as per drawings". It's one line and one number.

Then the fire stairs come up at the first site walk. 2 stairs, 6 storeys, walls and soffits, and nobody can show whether they were in the price.

A measured painting takeoff is how you find that out before the package is let.

What units is painting measured in?

Mostly m², by surface and by system.

Measure the surface as it's finished, net. Coats, primer and waste belong in the rate.

What do I read off which drawing?

Painting has almost no drawings of its own. You're reading other trades' documents.

Start with the finishes schedule and build a list of systems. Every quantity you measure sits under one of them.

How do I measure the walls and ceilings?

Walls are the length of each painted face x the painted height.

If you've already measured partitions for the plasterer, reuse it. A partition has 2 faces, so the painted area starts at twice the partition area, plus the internal face of the external walls, less whatever is tiled, panelled or behind joinery. The plasterboard takeoff guide covers that measure.

Height is where it goes wrong. Paint usually stops at the ceiling, and the plasterboard often runs past it. So painted height is floor to ceiling, read from the RCP, and it changes room to room.

For openings, pick a rule and write it down. Deducting every door and window in full gives a net area. Some estimators leave small openings in and let that cover the reveals. Either is workable as long as the painters quoting know which one you used, and if your bill is measured to the ANZSMM, use its rule.

Ceilings are the room area from the RCP. Add the vertical faces of bulkheads and any dropped edges. They're small and there are a lot of them.

As an example, take a 2-bed apartment with 62 m of partition at a 2.7 m ceiling. That's 62 x 2.7 x 2 = 335 m² of partition face before deductions. Take off 28 m² of wall tiling and 12 m² behind the kitchen joinery and you're at 295 m². Multiply an error in that by 84 apartments.

Which surfaces get missed?

The ones that aren't in a room on the finishes schedule.

Each of these is either in the painter's scope with a quantity, or in another trade's, or excluded on purpose. If it's none of the 3, it gets painted at the builder's cost when the defects list comes round.

How do I check the painting quantities?

Against the other trades.

Painted ceiling area should be close to the plasterboard ceiling area. Painted wall area should reconcile with twice the partition area less tiling. The count of painted doors should match the door schedule less the prefinished ones.

There are more of these cross-checks in how to check a quantity takeoff.

How does AI takeoff handle painting?

Painting is areas by finish, lengths by wall type and door counts, and those are the quantities you can ask for directly.

With CIM Build's AI takeoff you ask in plain English - wall lengths by type, areas by room or finish, doors by fire rating. It calibrates the scale on each sheet, measures, and returns a table with a marked-up copy of the sheet so you can check what was traced.

CIM Build also reads the drawings and the specification into a scope of works for the trade, with the sheet and clause behind every line. The bill of quantities is measured against that scope, so a line like the fire stairs with no quantity against it stands out.

Book a briefing and bring the tender.

Frequently asked questions

Do I measure each coat separately? No. Measure the surface once and describe the system - primer, number of coats, sheen. The painter prices the coats in the rate. If 2 surfaces have different systems, they're 2 lines.

Should I deduct doors and windows from painted walls? Decide a rule and state it in the bill. A full deduction gives a net area and the reveals get measured as their own item. If the bill is prepared to the ANZSMM, follow its deduction rules so every painter is quoting the same quantity.

Are prefinished items part of the painting takeoff? List them as excluded so nobody assumes. Prefinished doors, powder-coated windows, laminate joinery and factory-finished panels need no paint, and saying so in the scope stops them being priced twice or argued about later.


Published by CIM Build. This is the text of https://www.cim.build/us/blog/painting-takeoff-guide without the site design. Index of all pages. Contact.